Charles Jillings, CEO of Utilico, energized by strong economic momentum across Latin America. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksFresnillo Regulatory News (FRES)

Share Price Information for Fresnillo (FRES)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 582.00
Bid: 582.00
Ask: 583.00
Change: -2.00 (-0.34%)
Spread: 1.00 (0.172%)
Open: 584.00
High: 588.00
Low: 581.00
Prev. Close: 584.00
FRES Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Second Quarter Production Report

14 Jul 2010 07:00

RNS Number : 3162P
Fresnillo PLC
14 July 2010
 



Fresnillo Plc

28 Grosvenor Street

London W1K 4QR

United Kingdom

www.fresnilloplc.com

 

14 July 2010

 

Production Report

for the three months ended 30 June 2010

Overview

·; Second quarter (9.6moz) and first half (19.1moz) silver production each achieved record levels when compared to same periods of previous years.

·; Quarterly attributable gold production achieved a new record at 91,254 ounces, an increase of 33.9% over the corresponding period last year.

·; Attributable gold production at Soledad & Dipolos continued ramping-up to 16,298 ounces.

·; Construction of the Saucito development project and the expansion of Ciénega's milling capacity are progressing according to schedule.

·; Cost reduction efforts and efficiency initiatives remain firmly on track.

 

 

Jaime Lomelín, Chief Executive Officer, said:

"We have accomplished another quarter of stable silver production and promising exploration results. Quarterly gold production has reached a new record level once again, thanks to the efficient ramping-up of production at Soledad-Dipolos. Our exploration programme remains firmly on track and we continued working hard over the quarter on the development of the Saucito project and on the expansion of milling capacity at Ciénega. Although we are pleased with these outcomes, which bear out our solid experience in developing and operating mines, we will continue improving performance at the mines. We remain committed to managing costs and delivering on our growth programme. "

 

Total Production - Attributable

 

2Q 10

2Q 09

% change

1Q 10

YTD 10

YTD 09

% change

Silver prod'n (kOz)

9,615

9,587

0.3

9,492

19,107

18,805

1.6

Silverstream prod'n (kOz)

989

867

14.1

827

1,816

1,759

3.2

Total Silver production (kOz)

10,604

10,454

1.4

10,319

20,923

20,564

1.7

Gold prod'n (Oz)

91,254

68,166

33.9

85,097

176,351

132,894

32.7

Lead prod'n (t)

4,654

4,226

10.1

4,489

9,144

8,446

8.3

Zinc prod'n (t)

5,784

4,842

19.5

5,040

10,825

10,199

6.1

 

As expected, quarterly attributable silver production across the group remained broadly stable recording a modest increase on the previous period. However, the increase was sufficient to ensure second quarter and first half silver production each achieved record levels when compared to corresponding periods of previous years.

In accordance with the Silverstream contract, Fresnillo accrued 989,000 silver ounces over the second quarter of the previous year, an increase of 14.1% due to an abnormally high silver ore grade. We expect the average ore grade for the full year to be in line with last year.

Attributable gold production in the second quarter, as in the first quarter, received a significant boost from the start-up of commercial production at Soledad-Dipolos. As a result, record levels of gold production were achieved. Second quarter gold production increased by 7.2% when compared to the previous quarter due to the continued ramp-up at Soledad-Dipolos and to a lesser extent, higher ore grades at Ciénega.

Regarding the Group's by-products, quarterly lead and zinc production increased by 10.1% and 19.5% respectively compared to the same period of the previous year mainly as a result of higher throughput and better ore grades at the Fresnillo mine.

The Company is well on track to achieve full year 2010 production targets. We expect to produce approximately 38moz of silver and with the contribution of Soledad-Dipolos we expect to produce approximately 340,000oz attributable gold.

 

Fresnillo mine production

 

2Q 10

2Q 09

% change

1Q 10

YTD 10

YTD 09

% change

Silver prod'n (kOz)

9,022

9,044

-0.2

8,799

17,820

17,544

1.6

Gold prod'n (Oz)

5,890

6,497

-9.3

5,598

11,488

12,577

-8.7

Lead prod'n (t)

3,057

2,648

15.4

2,779

5,836

5,031

16.0

Zinc prod'n (t)

3,301

2,760

19.6

2,713

6,014

5,873

2.4

 

As expected, the quarterly silver production at the Fresnillo mine remained stable when compared to the previous quarter and the corresponding period of 2009. Quarterly gold production decreased by 9.3% compared to the second quarter of last year with a minimal economic impact, mainly as a result of lower ore grades, while it increased by 5.2% over the first quarter of 2010 due to higher volumes of ore milled.

 

Production figures do not include production from the development ore at Saucito which was processed at the Fresnillo mill. In the second quarter of 2010, 208,112 oz silver, 830 oz gold and 38 tonnes of lead were extracted from the Saucito project, all of which are included in the total production figures but not in the Fresnillo mine figures.

As part of the ongoing cost reduction initiatives and efficiency projects, the operation of the sewage water treatment plant at Fresnillo contributed to lowering our production costs. More importantly it enabled Fresnillo plc to reduce fresh water consumption during the first half of 2010 to approximately 658,000m3 in a region where water is a scarce resource. Additionally, the local community benefited from the elimination of sewage water, thus avoiding a potential source of contamination.

The sinking of the San Carlos shaft reached 36o metres of a planned total of 560 metres, which when completed by third quarter of 2011, will reduce haulage costs at the Fresnillo mine.

 

Ciénega mine production

 

2Q 10

2Q 09

% change

1Q 10

YTD 10

YTD 09

% change

Gold prod'n (Oz)

28,564

24,475

 16.7

27,208

55,772

47,625

17.1

Silver prod'n (kOz)

310

432

-28.2

366

676

751

-10.0

Lead prod'n (t)

1,559

1,569

-0.6

1,669

3,228

3,360

-3.9

Zinc prod'n (t)

2,483

2,072

19.8

2,328

4,811

4,284

12.3

Quarterly gold production increased by 16.7% compared to the corresponding period in 2009 as a result of higher volumes of ore milled and improved ore grades. The increased ore throughput was achieved by the timely preparation of new stopes, maintenance improvements and the implementation of Six Sigma quality control methodology. Similarly, quarterly gold production increased by 5.0% over the first quarter of 2010 as a result of the aforementioned development activities at the mine, which allowed the extraction of minerals from veins with higher ore grades.

Quarterly silver production declined by 28.2% and 15.2% when compared to the corresponding period of 2009 and the previous quarter respectively due to lower silver ore grades. Nevertheless, the favourable economic effect of the increased gold production was more than two times the adverse effect of the lower silver production.

At Ciénega, the shaft sinking to gain access to deeper ore reserves remained on track during the quarter, reaching 214.5 metres out of a planned total 300 metres. This US$13.3 million project will be concluded in the second half of 2011 and is expected to reduce costs.

 

Herradura mine production - Attributable

 

2Q 10

2Q 09

% change

1Q 10

YTD 10

YTD 09

% change

Gold prod'n (Oz)

39,672

36,916

7.5

39,897

79,569

71,428

11.4

Silver prod'n (kOz)

67

44

52.3

55

122

87

40.2

Attributable gold production in the second quarter increased by 7.5% compared to the corresponding period in 2009 due to higher volumes of ore deposited at the leaching pads.

Silver production in the second quarter increased by 52.3% and 20.9% when compared to the corresponding period in 2009 and the first quarter of 2010 respectively as a result of higher silver ore grades.

The construction of the eighth leaching pad at Herradura progressed well over the period.

 

Soledad-Dipolos mine production - Attributable

 

2Q 10

2Q 09

% change

1Q 10

YTD 10

YTD 09

% change

Gold prod'n (Oz)

16,298

-

N/A

11,226

27,524

-

N/A

Silver prod'n (kOz)

8

-

N/A

3

11

-

N/A

As anticipated, the open pit mine continued ramping-up in the second quarter and gold production reached 16,298 ounces. This increase was achieved through higher volumes of ore deposited, better recovery by controlling solution quality and optimising the size of the ore through better blasting practices.

Construction of the second leaching pad at Soledad-Dipolos remained on track.

 

Update on exploration

 

During the second quarter of 2010, drilling was carried out at the Saucito, Noche Buena, San Ramón (Ciénega), Minera Juanicipio (56% Fresnillo Plc), Orisyvo and San Julián projects. New resource estimates are in progress at Noche Buena. Positive results have been obtained at each of these 6 properties, with particularly good results at Saucito and Orisyvo, where new extensions of mineralization were discovered in the period. Presently the company has 40 exploration drill rigs operating around our mines and projects. Further details regarding the exploration projects and prospect will be provided in the interim report that will be released on the 3rd of August.

 

·; Juanicipio

 

The Juanicipio Joint Venture (56% Fresnillo plc and 44% MAG Silver) appointed SRK Consulting to conduct an audit of Juanicipio's total resources, which confirmed the indicated and inferred resources estimated by the company. With this new level of certainty, Juanicipio has appointed AMC Mining Consultants (Canada) Ltd. to undertake a prefeasibility study for the development of a stand alone underground silver mine. The prefeasibility study is expected to be completed by the end of calendar 2010.

 

Update on development projects

 

·; Ciénega

The expansion of Ciénega's milling capacity from 755,000 to 930,000 tonnes per year is on track to become operational in the first half of 2011 and is expected to increase gold production and reduce unit costs. In the second quarter of 2010, engineering and activities to clear the required area for the expansion continued and development of the foundations for the milling and flotation areas began. Orders for main equipment were placed and the contractors were selected.

 

·; Saucito

Construction of the Saucito project is proceeding according to schedule. Orders of all equipment and contracts have been placed. Several components for the concentrator were received in June and additional key equipment is expected to arrive in July and August. The mine has already advanced 24,035 metres of ramps and development workings.

The Saucito shaft is fully operational while sinking of the Jarillas shaft reached 208 metres depth out of a total 645 metres.

 

 

There will be a conference call for analysts and investors on Wednesday 14 July at 9.00am BST (London time). The dial in details are as follows:

 

Participants' dial in number: +44 (0)1452 541 076

Conference ID: 8657 6584

A replay of the conference call will be available for one week on the following number:

Dial in number: +44 (0)1452 550 000

Conference ID: 8657 6584

 

 

For further information, please visit our website www.fresnilloplc.com or contact:

Fresnillo plc

London Office

Octavio Alvidrez, Head of Investor Relations

Tel: +44 (0)20 7399 2470

Mexico City Office

 Gabriela Mayor

Tel: +52 55 52 79 3203

Brunswick Group

Carole Cable

David Litterick

 

Tel: +44 (0)20 7404 5959

 

About Fresnillo plc

 

Fresnillo Plc is the world's largest primary silver producer and Mexico's second largest gold producer, listed on the London Stock Exchange under the symbol FRES.

Fresnillo has four producing mines, all of them in Mexico - Fresnillo, Ciénega, Herradura and Soledad-Dipolos; one development project - Saucito; and five advanced exploration prospects - Noche Buena, San Juan, San Julián, Orysivo and Juanicipio as well as a number of other long term exploration prospects and, in total, has mining concessions covering approximately 1.75 million hectares in Mexico.

Fresnillo has a strong and long tradition of mining, a proven track record of mine development, reserve replacement, and production costs in the lowest quartile of the cost curve for both silver and gold.

Fresnillo's goal is to maintain the Group's position as the world's largest primary silver company, producing 65 million ounces of silver and over 400,000 ounces of gold by 2018.

 

Forward Looking Statements

Information contained in this announcement may include 'forward-looking statements'. All statements other than statements of historical facts included herein, including, without limitation, those regarding the Fresnillo Group's intentions, beliefs or current expectations concerning, amongst other things, the Fresnillo Group's results of operations, financial position, liquidity, prospects, growth, strategies and the silver and gold industries are forward-looking statements. Such forward-looking statements involve risk and uncertainty because they relate to future events and circumstances. Forward-looking statements are not guarantees of future performance and the actual results of the Fresnillo Group's operations, financial position and liquidity, and the development of the markets and the industry in which the Fresnillo Group operates, may differ materially from those described in, or suggested by, the forward-looking statements contained in this document. In addition, even if the results of operations, financial position and liquidity, and the development of the markets and the industry in which the Fresnillo Group operates are consistent with the forward-looking statements contained in this document, those results or developments may not be indicative of results or developments in subsequent periods. A number of factors could cause results and developments to differ materially from those expressed or implied by the forward-looking statements including, without limitation, general economic and business conditions, industry trends, competition, commodity prices, changes in regulation, currency fluctuations (including the US dollar and Mexican Peso exchanges rates), the Fresnillo Group's ability to recover its reserves or develop new reserves, including its ability to convert its resources into reserves and its mineral potential into resources or reserves, changes in its business strategy and political and economic uncertainty.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCEZLBFBDFXBBX
Date   Source Headline
24th Apr 20247:00 amRNS1Q24 Production Report
23rd Apr 20245:45 pmRNSAnnual Financial Report and Notice of AGM
23rd Apr 20247:00 amRNSConversion rate for 2023 final dividend
28th Mar 20245:40 pmRNSBoard changes
5th Mar 202412:37 pmRNSBoard and Committee Changes
5th Mar 20247:39 amRNSFY23 Preliminary Results
24th Jan 20243:23 pmRNSReplacement RNS for 4Q23 Production Report
24th Jan 20247:00 amRNS4Q23 Production Report
1st Dec 20237:00 amRNSNew Executive Roles
25th Oct 20237:09 amRNS3rd Quarter Production Report
15th Aug 20237:00 amRNSConversion Rate for 2023 Interim Dividend
1st Aug 20237:00 amRNSHalf-year Report
26th Jul 20237:00 amRNS2Q23 Production Report
29th Jun 20237:00 amRNSReport on Payments to Governments for 2022
23rd May 20236:34 pmRNSResults of AGM 2023
23rd May 20237:00 amRNSAnnual General Meeting Statement
15th May 20237:00 amRNSHerradura Operational Update
12th May 20234:41 pmRNSListing Rule 9.6.14R(2) Disclosure
9th May 20237:00 amRNSUpdate on new Mexican Mining Law
3rd May 20237:00 amRNSConversion rate for 2022 Final Dividend
26th Apr 20237:00 amRNS1Q23 Production Report
19th Apr 20235:52 pmRNSAnnual Financial Report and Notice of AGM
7th Mar 20237:00 amRNSFY22 Preliminary Results
2nd Feb 20237:00 amRNSListing Rule 9.6.14R(2) Disclosure
25th Jan 20237:00 amRNSFourth quarter production report
28th Dec 20227:00 amRNSJuanicipio project update
22nd Nov 20227:00 amRNSJuanicipio project update
26th Oct 20227:00 amRNS3rd Quarter Results
13th Sep 20227:00 amRNSStatement re Juanicipio commissioning update
16th Aug 20229:00 amRNSConversion Rate for 2022 Interim Dividend
2nd Aug 20227:00 amRNS1H22 Interim Results
27th Jul 20227:00 amRNS2Q22 Production Report
23rd Jun 20223:15 pmRNSReport on Payments to Governments for 2021
17th May 20223:00 pmRNSResult of AGM
17th May 20228:38 amRNSAGM Statement
4th May 20223:00 pmRNSConversion Rate for 2021 Final Dividend
27th Apr 20227:00 amRNSListing Rule 9.6.14R(2) Disclosure
27th Apr 20227:00 amRNS1Q22 Production Report
14th Apr 20227:00 amRNSAnnual Financial Report and Notice of AGM
13th Apr 20227:00 amRNSTR-1: Notification of major holdings
17th Mar 20221:55 pmRNSFresnillo recognised by Ethisphere
8th Mar 20227:00 amRNSFY21 Preliminary Results
4th Feb 20227:19 amRNSDeath of our Honorary Chairman
26th Jan 20227:00 amRNS4Q21 Production Report
29th Dec 20217:00 amRNSJuanicipio Commissioning Update
27th Oct 20217:00 amRNS3Q21 Production Report
17th Aug 202110:00 amRNSConversion Rate for 2021 Interim Dividend
3rd Aug 20217:00 amRNS1H21 Interim Results
28th Jul 20217:00 amRNS2Q21 Production Report
24th Jun 20212:17 pmRNSResult of AGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.