Quarterly Update on Construction & Commissioning

26 Jan 2017 07:00

RNS Number : 1386V
Firestone Diamonds PLC
26 January 2017
 

26 January 2017

 

Firestone Diamonds plc

("Firestone", the "Group" or the "Company") (AIM: FDI)

 

Quarterly Update on Construction and Commissioning Activities

 

Firestone Diamonds plc, the AIM-quoted diamond company, is pleased to provide its quarterly update on construction and commissioning activities at its Liqhobong Diamond Mine ("Liqhobong" or the "Project") for the quarter ended December 2016. Liqhobong is owned 75% by Firestone and 25% by the Government of Lesotho.

 

Highlights for the quarter ended 31 December 2016

· Project construction 100% complete and ramping up to nameplate capacity

· First diamond recoveries commenced in late October 2016

· Recovery of over 20 special stones larger than 10.8 carats, with the largest being a 37 carat white diamond, as well as several fancy yellow diamonds

· Processing of lower grade stockpiles and diluted ore in the quarter produced 58,000 carats at a grade of 14.4 carats per hundred tonnes

· 402,000 tonnes treated by the processing plant and nameplate capacity achieved on multiple occasions

· Strong operating cost management of US$12 per tonne treated at bottom end of guidance

· Zero lost time injury record maintained, with approximately 3.6 million man hours worked

· Strong financial position with cash and available facilities of US$18 million, alongside a further US$15 million standby facility available

· First sale of Liqhobong diamonds will be held in Antwerp, Belgium from 6-10 February 2017

 

Stuart Brown, Chief Executive Officer, commented:

 

"Construction activities at Liqhobong were completed early in the quarter and we are currently in the commissioning and ramp up stage of the Project. We have been pleased with the tonnes processed by the plant, which has already seen nameplate production reached on multiple occasions at this early stage of ramp up.

 

As previously guided, the commencement of commissioning has seen the processing of historic low grade stockpiles, diluted ore and low grade ore from the main pit which at the end of December had produced 58,000 carats. Pleasingly, we have recovered over 20 special stones (larger than 10.8 carats) including a 37 carat white stone and numerous smaller yellow and fancy yellow stones, with no breakages of larger stones to date. At this stage of the ramp up, we have encountered the normal commissioning challenges and these are being addressed by our team in a methodical way.

 

We look forward to providing further updates on the ramp up programme, as well as the diamond sale next month."

 

Project and Commissioning Update

 

As at 31 December 2016, construction was 100% completed at Liqhobong and first ore was treated through the plant at the end of October 2016, which was well within the revised delivery target. By the end of December 2016, 402,000 tonnes of ore (being from historic low grade stockpiles, diluted ore and low grade ore from the main pit) had been treated through the plant with a total of 58,000 carats having been recovered, including over 20 special stones larger than 10.8 carats, with the largest being a 37 carat white diamond, as well as several fancy yellow diamonds.

 

As is normal during the commissioning phase of a new plant, we have had to modify or change certain operating parameters. The current grade of 14.4 carats per hundred tonnes has been below the initial commissioning estimates and the Company is currently focused on making adjustments and investigating potential causes for the under recovery of lower value finer diamonds.

 

During the commissioning process we will continue mining in the lower quality ore areas until the recoveries have reached required levels, following which we will then move into the better quality ore areas within the main pit, where the higher value diamonds are expected to be recovered. The recovery tailings from the commissioning phase are being stored separately and will be retreated once the commissioning adjustments have been made.

 

Operations at the plant have seen good volumes being treated, and on a few occasions during the ramp up stage, the plant has already met the nameplate capacity target of 500 tonnes per hour for 24 consecutive hours. The Company remains on target to achieve nameplate production by the beginning of Q2 2017.

 

During the commissioning phase we have been careful to manage costs in line with the planned tonnage volumes, at US$12 per tonne treated, we are at the bottom end of the guidance of US$12-14 per tonne.

 

The rainy season has also begun and water is being collected and stored in the various water storage facilities for future operations in the dry season.

 

Health & Safety

 

At the end of the quarter, the Project maintained its outstanding health and safety record, having reached 3.6 million man hours worked without a single Lost Time Injury.

 

Financial

 

The Company continues to manage its cash prudently. At the end of the year, cash on hand was US$4 million with US$14 million available under the ABSA debt facility and a further US$15 million available under the standby facility.

 

At the end of December 2016, 95% of the capital budget had been spent on the project with the remaining US$8 million to be spent in Q1 2017.

 

Diamond Sales

 

Firestone has scheduled its first diamond sale to take place in Antwerp in the week of 6-10 February 2017. Results are expected to be announced during the week commencing 13 February 2017. Thereafter, the Company expects to host two sales per quarter with the second auction due late Q1 2017.

 

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 ("MAR").

 

For more information contact:

 

Firestone Diamonds plc

+44 (0)20 8741 7810

Stuart Brown

Strand Hanson Limited (Nomad)

+44 (0)20 7409 3494

Stuart Faulkner

Richard Tulloch

James Dance

Macquarie Capital (Europe) Limited (Joint Broker)

+44(0)20 3037 2000

Raj Khatri

Nick Stamp

Mirabaud Securities LLP (Joint Broker)

Rory Scott

+44 (0)20 7878 3360

Ed Haig-Thomas

+44 (0)20 7878 3447

Tavistock (Public and Investor Relations)

+44 (0)20 7920 3150

Emily Fenton

+44 (0)7788 554 035

Jos Simson

Barney Hayward

 

Background information on Firestone

 

Firestone is an international diamond mining company with operations focused on Lesotho. Firestone is currently in the process of commencing production at the Liqhobong Diamond Mine in Lesotho to become a one million carat per annum producer.

 

Lesotho is emerging as one of Africa's significant new diamond producers, hosting Gem Diamonds' Letseng Mine, Firestone's Liqhobong Mine and Namakwa Diamonds' Kao Mine.

 

For more information please visit: www.firestonediamonds.com.

 

**ENDS**

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDBRGDBLGDBGRU
Date   Source Headline
1st Nov 20167:00 amRNSFinal results for the year ended 30 June 2016
24th Oct 20164:50 pmRNSHolding(s) in Company
21st Oct 20167:00 amRNSLiqhobong Commences Production Ramp-up
13th Oct 20163:00 pmRNSIssue of shares
6th Oct 20167:00 amRNSLiqhobong Mine Enters Final Commissioning Stages
22nd Sep 20164:45 pmRNSDirector dealing
12th Sep 20167:00 amRNSUpdate on the sale of the Botswana operations
30th Aug 20167:25 amRNSUpdate on the sale of the Botswana operations
29th Jul 20167:00 amRNSUpdate on the sale of the Botswana operations
25th Jul 20165:30 pmRNSHolding(s) in Company
21st Jul 20161:04 pmRNSIssue of shares
20th Jul 20167:00 amRNSLiqhobong Diamond Mine Construction Update
14th Apr 20167:00 amRNSLiqhobong Diamond Mine Update
8th Apr 20162:30 pmRNSIssue of shares
6th Apr 20167:00 amRNSUpdate on the sale of the Botswana operations
16th Mar 20167:00 amRNSInterim Results
9th Feb 20167:00 amRNSLiqhobong Diamond Mine Presentation and Update
25th Jan 20167:00 amRNSLiqhobong Diamond Mine Update
14th Jan 20162:47 pmRNSIssue of shares
2nd Dec 201511:26 amRNSResult of AGM
30th Nov 20157:00 amRNSDirector Dealing
23rd Nov 20157:00 amRNSDirector dealing
4th Nov 20157:00 amRNSAppointment of Joint Broker
27th Oct 201511:36 amRNSPosting of Annual Report & Notice of AGM
26th Oct 20152:51 pmRNSDirector dealing
22nd Oct 20154:32 pmRNSIssue of shares
13th Oct 20157:00 amRNSUpdate on the sale of the Botswana operations
6th Oct 20157:01 amRNSUpdate for Liqhobong & Capital Markets Day
6th Oct 20157:00 amRNSFinal results for the year ended 30 June 2015
2nd Oct 20151:06 pmRNSUpdate on the sale of the Botswana operations
23rd Sep 20157:00 amRNSFirst drawdown of Absa Debt and Notice of Results
27th Aug 20154:30 pmRNSHolding(s) in Company
9th Jul 20157:00 amRNSSale of Botswana operations
23rd Jun 20158:42 amRNSReplacement - Liqhobong Mine Project Update
23rd Jun 20157:00 amRNSLiqhobong Mine Development Project Update
11th May 201512:00 pmRNSResult of General Meeting
24th Apr 20157:00 amRNSStandby facility & restructuring of mezz facility
12th Mar 20157:00 amRNSInterim Results
2nd Dec 20147:00 amRNSLiqhobong Mine Development Project Update
26th Nov 20143:28 pmRNSResult of AGM
3rd Nov 201412:59 pmRNSPosting of Annual Report and Notice of AGM
28th Oct 20145:00 pmRNSHolding(s) in Company
2nd Oct 20147:00 amRNSFinal Results
1st Oct 201410:47 amRNSHolding(s) in Company
25th Sep 20147:00 amRNSNotice of Results
14th Aug 20147:07 amRNSDisposal process re Company's Botswana assets
25th Jul 20147:00 amRNSDirector dealing
23rd Jul 201411:44 amRNSHolding(s) in Company
26th Jun 20147:00 amRNSCommencement of earthworks at Liqhobong
25th Jun 20149:36 amRNSDirector Declaration

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.