Liqhobong Diamond Mine Update

14 Apr 2016 07:00

RNS Number : 1419V
Firestone Diamonds PLC
14 April 2016

14 April 2016

Firestone Diamonds plc

("Firestone", the "Group" or the "Company") (AIM: FDI)

Liqhobong Diamond Mine Update

Firestone Diamonds plc, the AIM-quoted diamond development company, is pleased to announce an update for the Liqhobong Diamond Mine ("Liqhobong" or the "Project"), which is owned 75% by Firestone and 25% by the Government of Lesotho.

Highlights

Construction 72% complete as at the end of March 2016

Project remains on track for initial production in Q4 2016

Number of Project items now complete or over 98% complete include

o Residues Storage Facility ("RSF") starter wall

o Design and Engineering

o Procurement

o Earthworks

o Structural Steel Fabrication

Revised capital budget of ZAR2.1 billion, remains within the original project budget of US$185.4 million

Zero lost time injury record maintained, with approximately 2.2 million man hours worked as at the end of March 2016

Stuart Brown, Chief Executive Officer, commented:

"Firestone has achieved another strong quarter of progress at Liqhobong, which, as at 31 March 2016, was 72% complete and on track for initial production in Q4 2016.

The last quarter saw favourable weather conditions at site and the granting of a number of work permits by the Government of Lesotho, our 25% partner in the Project, contributing towards completing a number of key project components.

Firestone remains fully funded to completion of the Project, production ramp up and the first sale of its Liqhobong diamonds and I look forward to providing further updates as we move towards project commissioning in Q4."

Project Update

Construction at Liqhobong continued in earnest during the quarter ending 31 March 2016. Activities were helped by the granting of further work permits by the Government of Lesotho and the favourable weather conditions experienced at site in recent months.

The Company continues its water storage activities and now has in excess of 500,000 cubic metres of water on site, sufficient for the first year of production, thus de-risking the Project further by mitigating one of the critical early start-up risks.

As previously announced all significant civils and earthworks have now been completed and in December 2015, the site was handed over to the Structural, Mechanical, Plate and Pipework contractors for the erection of the main plant. As a result, during this quarter, a number of Project areas have been completed or are over 98% complete including the RSF starter wall, the design, engineering and procurement elements alongside the structural steel fabrication. As expected the detailed mine planning continues to be refined and reviewed as the Project progresses towards production. Operational readiness, led by the Project team, is well underway and the team's main focus during this quarter was contract placement and staff recruitment.

Throughout Liqhobong's development Firestone has enforced a rigorous safety policy and has continued to maintain its lost time injury free record, with approximately 2.2 million man hours worked as at the end of March 2016.

As at the end of March 2016, the Project was 72% complete and in line with the revised construction schedule. The Project also remains within the original US$185.4 million budget and as at 31 March 2016, ZAR1.5 billion (US$129.9 million) or 70% had been spent on the Project against the revised capital budget of ZAR2.1 billion. The cash on hand at the end of March 2016 was US$14.8 million and the Company also had US$47.0 million available pursuant to the ABSA debt facility, resulting in forecast headroom available to the Company of approximately US$9.0 million as at the end of December 2016, which does not include the US$15.0 million standby facility available to the Company.

Each month the Company updates its media gallery to include images to illustrate the Project's progress and these can be found on Firestone's website: www.firestonediamonds.com/media.

For more information contact:

Firestone Diamonds plc

+44 (0)20 8741 7810

Stuart Brown

Strand Hanson Limited (Nomad)

+44 (0)20 7409 3494

Stuart Faulkner

Richard Tulloch

James Dance

Macquarie Capital (Europe) Limited (Joint Broker)

Raj Khatri

+44(0)20 3037 2000

Nick Stamp

Mirabaud Securities LLP (Joint Broker)

Rory Scott

+44 (0)20 7878 3360

Ed Haig-Thomas

+44 (0)20 7878 3447

Tavistock (Public and Investor Relations)

+44 (0)20 7920 3150

Jos Simson

+44 (0)7788 554 035

Emily Fenton

Background information on Firestone

Firestone is an international diamond development company with operations focused on Lesotho. Firestone is currently in the process of developing the Liqhobong Mine Development Project in Lesotho to become a one million carat per annum producer.

Lesotho is emerging as one of Africa's significant new diamond producers, and hosts Gem Diamonds' Letseng Mine, Firestone's Liqhobong Mine, as well as Namakwa Diamonds' Kao Mine.

For more information please visit: www.firestonediamonds.com.

**ENDS**

This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCZMGMDMFNGVZZ
Date   Source Headline
25th Mar 20204:41 pmRNSSecond Price Monitoring Extn
25th Mar 20204:36 pmRNSPrice Monitoring Extension
25th Mar 20208:05 amRNSSuspension of Operations to combat Coronavirus
20th Mar 20205:30 pmRNSFirestone Diamonds
13th Mar 202011:38 amRNSResult of Meeting
13th Mar 20209:05 amRNSSecond Price Monitoring Extn
13th Mar 20209:00 amRNSPrice Monitoring Extension
26th Feb 20207:05 amRNSSecond Price Monitoring Extn
26th Feb 20207:05 amRNSPrice Monitoring Extension
26th Feb 20207:04 amRNSSecond Price Monitoring Extn
26th Feb 20207:03 amRNSPrice Monitoring Extension
26th Feb 20207:02 amRNSSecond Price Monitoring Extn
26th Feb 20207:01 amRNSPrice Monitoring Extension
25th Feb 20202:06 pmRNSSecond Price Monitoring Extn
25th Feb 20202:00 pmRNSPrice Monitoring Extension
25th Feb 202011:05 amRNSSecond Price Monitoring Extn
25th Feb 202011:00 amRNSPrice Monitoring Extension
25th Feb 20209:05 amRNSSecond Price Monitoring Extn
25th Feb 20209:00 amRNSPrice Monitoring Extension
25th Feb 20207:01 amRNSQuarterly Update on Operations
25th Feb 20207:00 amRNSProposed cancellation of AIM listing
19th Feb 202011:05 amRNSSecond Price Monitoring Extn
19th Feb 202011:00 amRNSPrice Monitoring Extension
17th Jan 202012:23 pmRNSIssue of Shares
17th Jan 202011:36 amRNSResult of AGM
6th Jan 20209:05 amRNSSecond Price Monitoring Extn
6th Jan 20209:00 amRNSPrice Monitoring Extension
20th Dec 20197:00 amRNSFinal results for the year ended 30 June 2019
4th Dec 20199:42 amRNSGrid Power Restored
19th Nov 20194:35 pmRNSPrice Monitoring Extension
1st Nov 20193:53 pmRNSIssue of Shares
1st Nov 20197:00 amRNSProduction resumes at Liqhobong Mine
23rd Oct 20197:00 amRNSQuarterly Update on Operations
17th Oct 20195:30 pmRNSResults of General Meeting
15th Oct 20192:03 pmRNSUpdate on power disruptions
4th Oct 20192:06 pmRNSSecond Price Monitoring Extn
4th Oct 20192:00 pmRNSPrice Monitoring Extension
4th Oct 201912:06 pmRNSProduction disruption due to power fluctuations
1st Oct 20193:23 pmRNSShareholder Circular and Notice of General Meeting
25th Jul 20197:00 amRNSQ4 Operations Update and Guidance for FY2020
22nd Jul 20197:00 amRNSBoard Changes
8th Jul 20197:00 amRNSRecovery of 54 Carat Fancy Yellow Diamond
1st Jul 201912:16 pmRNSBank and Bondholder Support for Covenant Waiver
30th Apr 20199:01 amRNSBoard Changes
25th Apr 20197:00 amRNSQuarterly Update on Operations
15th Apr 201911:49 amRNSIssue of Shares re: Eurobond
8th Apr 20197:00 amRNSRecovery Of 72 Carat Yellow Diamond
28th Mar 20197:00 amRNSUnaudited results for six months to 31 Dec 2018
12th Feb 20197:00 amRNSRecovery of 70 Carat White Gem Diamond
4th Feb 20197:00 amRNSQuarterly Update on Operations

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.