Commencement of earthworks at Liqhobong

26 Jun 2014 07:00

RNS Number : 5693K
Firestone Diamonds PLC
26 June 2014
 



26 June 2014

 

Firestone Diamonds plc

("Firestone" or the "Company") (AIM: FDI)

 

Commencement of earthworks at Liqhobong

 

Firestone Diamonds plc, the AIM-quoted diamond company, is pleased to provide the first update on its development programme at the Liqhobong Diamond Mine ("Liqhobong") in the Lesotho Highlands, following completion of the project financing in May 2014. Construction and development is expected to take 24 months, with nameplate production (300,000 tonnes per month) achieved in H1 2016.

 

HIGHLIGHTS

· Decommissioning and removal of the Pilot Plant at Liqhobong underway and 30% complete;

· Engineering, Procurement, Construction and Management ("EPCM"), including civils and earthworks and Residue Storage Facility contracts have been signed or agreed;

· Commenced general site earthworks, including widening and rerouting the site access road, building the residue slimes retaining wall and early civil works;

· The overhead power line and main substation contract is signed and site mobilisation has been initiated;

· Major equipment long lead items have been approved and contracts placed; and

· All major equipment deliveries are aligned to current schedule.

 

Following completion of the project financing in May 2014, Firestone has commenced its development programme to build and commission the Main Treatment Plant and supporting infrastructure at Liqhobong, to ensure it is delivered in H1 2016 and, as importantly, on budget. The development programme is being executed by Firestone's projects team, led by the Chief Project Officer, Glenn Black, who was appointed to the Company in February 2014.

 

To date the Company has commenced decommissioning and removal of the existing Pilot Plant and this is approximately 30 per cent. complete. The EPCM, including earthworks and civils and residue storage facility contracts have been signed or agreed and Firestone has commenced general site earthworks. The site earthworks include; widening and rerouting the site access road; building the residue slimes retaining wall; and early civil works. Importantly, overhead power line and main substation mobilisation has begun with the first mining fleet already installed safely at site. Further, major equipment long lead items have been approved by the tender board committee and contracts have been placed. Lastly, major equipment deliveries are aligned to the Company's current baseline development schedule. To date, approximately 73 per cent. of the EPCM budget has been committed.

 

A presentation titled; 'June 2014 update' including the latest images from site is available on the Company's website: www.firestonediamonds.com.

 

Stuart Brown, Chief Executive Officer of Firestone commented:

 

"I am pleased to announce commencement of the earthworks programme at our Liqhobong diamond mine in Lesotho, which follows the recent completion of the financing. To date, we have committed approximately 73 per cent. of the expenditure required for the development and construction of the Main Treatment Plant and related infrastructure. I look forward to keeping shareholders abreast of future developments during the 24 months build."

 

**ENDS**

 

For more information contact

 

Firestone Diamonds plc

+44 (0)20 8741 7810

Stuart Brown

Strand Hanson Limited (Nomad)

+44 (0)20 7409 3494

Stuart Faulkner

Richard Tulloch

James Dance

GMP Securities Europe LLP (Joint Broker)

+44 (0)20 7647 2800

Richard Greenfield

Alexandra Carse

Mirabaud Securities LLP (Joint Broker)

Rory Scott

+44 (0)20 7878 3360

Ed Haig-Thomas

+44 (0)20 7878 3447

Tavistock Communications

+44 (0)20 7920 3150

Jos Simson

+44 (0)7788 554 035

Emily Fenton

Nuala Gallagher

 

Background information on Firestone

 

Firestone is an international diamond development company with operations focused on Lesotho and Botswana. Firestone is currently in the process of developing the Main Treatment Plant at the Liqhobong Mine in Lesotho to become a plus-one million carat per annum producer.

 

Lesotho is emerging as one of Africa's significant new diamond producers, and hosts Gem Diamonds' Letseng Mine, Firestone's Liqhobong Mine, as well as Namakwa Diamonds' Kao Mine and the Mothae development project.

 

For more information please visit: www.firestonediamonds.com.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCFMGZVLKDGDZM
Date   Source Headline
25th Mar 20204:41 pmRNSSecond Price Monitoring Extn
25th Mar 20204:36 pmRNSPrice Monitoring Extension
25th Mar 20208:05 amRNSSuspension of Operations to combat Coronavirus
20th Mar 20205:30 pmRNSFirestone Diamonds
13th Mar 202011:38 amRNSResult of Meeting
13th Mar 20209:05 amRNSSecond Price Monitoring Extn
13th Mar 20209:00 amRNSPrice Monitoring Extension
26th Feb 20207:05 amRNSSecond Price Monitoring Extn
26th Feb 20207:05 amRNSPrice Monitoring Extension
26th Feb 20207:04 amRNSSecond Price Monitoring Extn
26th Feb 20207:03 amRNSPrice Monitoring Extension
26th Feb 20207:02 amRNSSecond Price Monitoring Extn
26th Feb 20207:01 amRNSPrice Monitoring Extension
25th Feb 20202:06 pmRNSSecond Price Monitoring Extn
25th Feb 20202:00 pmRNSPrice Monitoring Extension
25th Feb 202011:05 amRNSSecond Price Monitoring Extn
25th Feb 202011:00 amRNSPrice Monitoring Extension
25th Feb 20209:05 amRNSSecond Price Monitoring Extn
25th Feb 20209:00 amRNSPrice Monitoring Extension
25th Feb 20207:01 amRNSQuarterly Update on Operations
25th Feb 20207:00 amRNSProposed cancellation of AIM listing
19th Feb 202011:05 amRNSSecond Price Monitoring Extn
19th Feb 202011:00 amRNSPrice Monitoring Extension
17th Jan 202012:23 pmRNSIssue of Shares
17th Jan 202011:36 amRNSResult of AGM
6th Jan 20209:05 amRNSSecond Price Monitoring Extn
6th Jan 20209:00 amRNSPrice Monitoring Extension
20th Dec 20197:00 amRNSFinal results for the year ended 30 June 2019
4th Dec 20199:42 amRNSGrid Power Restored
19th Nov 20194:35 pmRNSPrice Monitoring Extension
1st Nov 20193:53 pmRNSIssue of Shares
1st Nov 20197:00 amRNSProduction resumes at Liqhobong Mine
23rd Oct 20197:00 amRNSQuarterly Update on Operations
17th Oct 20195:30 pmRNSResults of General Meeting
15th Oct 20192:03 pmRNSUpdate on power disruptions
4th Oct 20192:06 pmRNSSecond Price Monitoring Extn
4th Oct 20192:00 pmRNSPrice Monitoring Extension
4th Oct 201912:06 pmRNSProduction disruption due to power fluctuations
1st Oct 20193:23 pmRNSShareholder Circular and Notice of General Meeting
25th Jul 20197:00 amRNSQ4 Operations Update and Guidance for FY2020
22nd Jul 20197:00 amRNSBoard Changes
8th Jul 20197:00 amRNSRecovery of 54 Carat Fancy Yellow Diamond
1st Jul 201912:16 pmRNSBank and Bondholder Support for Covenant Waiver
30th Apr 20199:01 amRNSBoard Changes
25th Apr 20197:00 amRNSQuarterly Update on Operations
15th Apr 201911:49 amRNSIssue of Shares re: Eurobond
8th Apr 20197:00 amRNSRecovery Of 72 Carat Yellow Diamond
28th Mar 20197:00 amRNSUnaudited results for six months to 31 Dec 2018
12th Feb 20197:00 amRNSRecovery of 70 Carat White Gem Diamond
4th Feb 20197:00 amRNSQuarterly Update on Operations

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.