Liqhobong Mine Development Project Update

2 Dec 2014 07:00

RNS Number : 5467Y
Firestone Diamonds PLC
02 December 2014
 



2 December 2014

 

Firestone Diamonds plc

("Firestone" or the "Company") (AIM: FDI)

 

Liqhobong Mine Development Project Update

 

Firestone Diamonds plc, the AIM-quoted diamond company, is pleased to provide an update on the Liqhobong Mine Development Project ("Liqhobong" or the "Project"). The Project, which commenced in June 2014, is expected to take 24 months to construct and includes the construction of the new 500 tonne per hour main treatment plant and supporting infrastructure to treat 3.6 million tonnes of ore and recover plus 1 million carats per year. Initial production is expected to commence at the end of Q2 2016.

 

HIGHLIGHTS

 

· Project commenced in June 2014, following completion of the Project financing in May 2014;

· The Project is currently on time and on budget;

· The Company has now secured all major contracts and placed orders for all long lead items;

· Approximately ZAR400 million has been spent on the Project to date;

· The grid power project is progressing on time and connection to grid power is expected to be achieved during the second half of 2015;

· The final conditions precedent for the US$82.4 million Absa project debt facility ("Absa Facility") are expected to be completed well before the need to draw down the Absa Facility, which is expected to be late March 2015; and

· The Project team is now in place. The Project has created over 400 jobs and Liqhobong has maintained its target of zero lost time injuries.

 

Following completion of the Project financing, in May 2014, the Company commenced the Project in June 2014 with the finalisation of the major contracts and the commencement of the site establishment, general earthworks and the decommissioning and removal of the pilot plant.

 

To date the Project is progressing well and is on time and on budget, with the pilot plant having now been removed and the earthworks progressing on schedule. Fortunately the winter season was mild, with no snow, which allowed the Project team to progress certain work streams ahead of schedule, in advance of the rainy season, which commenced in late October.

 

A total of ZAR1.28 billion in orders out of the total budget of the ZAR1.43 billion Engineering, Procurement, Construct and Manage ("EPCM") contract have been placed. The three largest contracts under the EPCM contract, totalling ZAR943 million, have been agreed on a fixed price basis to remove the escalation risk. The Project team's budget of ZAR280 million, which contains, inter alia, the escalation, contingency and Project team salary costs is in line with the budget. To date, approximately ZAR400m has been spent on the Project, which is as per the budgeted schedule.

 

The provision of electrical infrastructure to connect the mine to grid power is a separate project which is also progressing as planned. The total project cost is ZAR165 million with Firestone funding ZAR145 million with the balance, ZAR20 million, being funded by the local company engaged to construct the power infrastructure. All equipment and long lead item orders have been placed and site preparation for the substations is well advanced. Connection to grid power is expected to be achieved during the second half of 2015, ahead of the initial schedule, which will enable the Company to realise savings against the Project's budget, as it will be able to use grid power instead of diesel-generated power.

 

The final conditions precedent for draw down of the US$82.4 million Absa Facility are progressing on schedule and are expected to be completed well before the need to draw down on the Absa Facility, which is likely to be late March 2015.

 

The Project team is now in place and Firestone has already created over 400 jobs at Liqhobong, which will continue to rise over the course of the Project. The rainy season has now commenced and the increased project execution risk, due to the potential of heavy rainfall, is being well managed. Liqhobong has maintained its target of zero lost time injuries.

 

The Company will shortly make available a number of photos showing the Project's progress on its website www.firestonediamonds.com.

 

The support from the Government of Lesotho has been positive with keen interest in the Project's progress being expressed. The ongoing difficulties that the coalition Government has been experiencing have not disrupted the Project in any way. Firestone remains supportive of the Government and hopes that they continue along the agreed Southern African Development Community (SADC) brokered solution. Elections are expected to be held in early 2015, and Firestone looks forward to a continued positive relationship with the Government, the Company's 25% partner in the Liqhobong Diamond Mine.

 

**ENDS**

 

For more information contact

 

Firestone Diamonds plc

+44 (0)20 8741 7810

Stuart Brown

Strand Hanson Limited (Nomad)

+44 (0)20 7409 3494

Stuart Faulkner

Richard Tulloch

James Dance

GMP Securities Europe LLP (Joint Broker)

+44 (0)20 7647 2800

Richard Greenfield

Alexandra Carse

Mirabaud Securities LLP (Joint Broker)

Rory Scott

+44 (0)20 7878 3360

Ed Haig-Thomas

+44 (0)20 7878 3447

Tavistock Communications

+44 (0)20 7920 3150

Jos Simson

+44 (0)7788 554 035

Emily Fenton

Nuala Gallagher

 

Background information on Firestone

 

Firestone is an international diamond development company with operations focused on Lesotho. Firestone is currently in the process of developing the Liqhobong Mine Development Project in Lesotho to become a plus 1 million carat per annum producer.

 

Lesotho is emerging as one of Africa's significant new diamond producers, and hosts Gem Diamonds' Letseng Mine, Firestone's Liqhobong Mine, as well as Namakwa Diamonds' Kao Mine and the Mothae development project.

 

For more information please visit: www.firestonediamonds.com.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCEAPAFESSLFFF
Date   Source Headline
25th Mar 20204:41 pmRNSSecond Price Monitoring Extn
25th Mar 20204:36 pmRNSPrice Monitoring Extension
25th Mar 20208:05 amRNSSuspension of Operations to combat Coronavirus
20th Mar 20205:30 pmRNSFirestone Diamonds
13th Mar 202011:38 amRNSResult of Meeting
13th Mar 20209:05 amRNSSecond Price Monitoring Extn
13th Mar 20209:00 amRNSPrice Monitoring Extension
26th Feb 20207:05 amRNSSecond Price Monitoring Extn
26th Feb 20207:05 amRNSPrice Monitoring Extension
26th Feb 20207:04 amRNSSecond Price Monitoring Extn
26th Feb 20207:03 amRNSPrice Monitoring Extension
26th Feb 20207:02 amRNSSecond Price Monitoring Extn
26th Feb 20207:01 amRNSPrice Monitoring Extension
25th Feb 20202:06 pmRNSSecond Price Monitoring Extn
25th Feb 20202:00 pmRNSPrice Monitoring Extension
25th Feb 202011:05 amRNSSecond Price Monitoring Extn
25th Feb 202011:00 amRNSPrice Monitoring Extension
25th Feb 20209:05 amRNSSecond Price Monitoring Extn
25th Feb 20209:00 amRNSPrice Monitoring Extension
25th Feb 20207:01 amRNSQuarterly Update on Operations
25th Feb 20207:00 amRNSProposed cancellation of AIM listing
19th Feb 202011:05 amRNSSecond Price Monitoring Extn
19th Feb 202011:00 amRNSPrice Monitoring Extension
17th Jan 202012:23 pmRNSIssue of Shares
17th Jan 202011:36 amRNSResult of AGM
6th Jan 20209:05 amRNSSecond Price Monitoring Extn
6th Jan 20209:00 amRNSPrice Monitoring Extension
20th Dec 20197:00 amRNSFinal results for the year ended 30 June 2019
4th Dec 20199:42 amRNSGrid Power Restored
19th Nov 20194:35 pmRNSPrice Monitoring Extension
1st Nov 20193:53 pmRNSIssue of Shares
1st Nov 20197:00 amRNSProduction resumes at Liqhobong Mine
23rd Oct 20197:00 amRNSQuarterly Update on Operations
17th Oct 20195:30 pmRNSResults of General Meeting
15th Oct 20192:03 pmRNSUpdate on power disruptions
4th Oct 20192:06 pmRNSSecond Price Monitoring Extn
4th Oct 20192:00 pmRNSPrice Monitoring Extension
4th Oct 201912:06 pmRNSProduction disruption due to power fluctuations
1st Oct 20193:23 pmRNSShareholder Circular and Notice of General Meeting
25th Jul 20197:00 amRNSQ4 Operations Update and Guidance for FY2020
22nd Jul 20197:00 amRNSBoard Changes
8th Jul 20197:00 amRNSRecovery of 54 Carat Fancy Yellow Diamond
1st Jul 201912:16 pmRNSBank and Bondholder Support for Covenant Waiver
30th Apr 20199:01 amRNSBoard Changes
25th Apr 20197:00 amRNSQuarterly Update on Operations
15th Apr 201911:49 amRNSIssue of Shares re: Eurobond
8th Apr 20197:00 amRNSRecovery Of 72 Carat Yellow Diamond
28th Mar 20197:00 amRNSUnaudited results for six months to 31 Dec 2018
12th Feb 20197:00 amRNSRecovery of 70 Carat White Gem Diamond
4th Feb 20197:00 amRNSQuarterly Update on Operations

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.