Operations and Project Update

1 Mar 2011 09:00

Europa Oil & Gas (Holdings) plc

1 March 2011Operations and Project UpdateWest Firsby, UK

Drilling of new production well WF-9 was completed on 17th February 2011. Since completing WF-9, the HH102 rig has moved over the WF-3 well to re-perforate this well for use as a water injector. These operations, in close proximity to the WF-9 wellhead, have prevented the surface beam pump from being commissioned until WF-3 operations are complete. Perforating has now taken place on WF-3 and the rig will move away over the coming days to allow full access to the WF-9 wellhead to complete the beam pump installation. The well will test the flow rates from Zone 1 and Zone 2 individually, initially producing from Zone 2 before moving on to Zone 1. Currently, associated gas from Zone 2 is building up in the shut-in well, an encouraging indication.

With regard to the existing producers in the field, a change in the WF-7 bottom hole assembly (BHA) is required and a plan has been submitted to the HSE to undertake a workover to replace the BHA to bring the well back up to full production capacity. This work will take place around mid-March.

Overall, production since early December has been low, due to a combination of weather-related and operational issues. This has brought the average production for the 6 months to 31 January 2011 down to 151bopd. It is anticipated that, with WF-9 coming onstream and the forthcoming WF-7 repairs, production will soon be back on-track.

Berenx, France

The technical work has indicated that there is ample evidence on the reprocessed 3D seismic data for the development of faulted structures developed all along the front of the Berenx fault-block system to the east of the existing wells. Data appertaining to a short interval drill stem test in the Berenx-2 well conducted in 1974 has recently been obtained from legacy archives and these data demonstrate that the well produced dry gas to surface but did not adequately test the fracture system in the reservoir.

Maintaining open fractures in the wellbore is critical for a successful test and can be achieved principally by two methods: managed pressure drilling and non-cemented completion techniques. In order to properly plan this challenging well, the Directors are currently in the final stages of selecting the drilling engineering team from a short-list to plan and manage the Berenx-3 well.

Planning for the deep HPHT Berenx-3 well will take over 12 months, with long lead items with specialist steel fabrication needing to be committed to in mid-2011. There is a strong technical case for acquiring additional 3D seismic coverage over the western part of the Berenx structure prior to drilling and we are currently looking at the possibility of 3D seismic acquisition during the well planning period.

Barchiz, Romania

The JV partners have reviewed the results of the Barchiz-1 well. The partners are discussing the forward programme for both Barchiz and the block as a whole. The option favoured by Europa is to penetrate a thicker section of the oil-bearing Oligocene sandstone and to test the main prospect target, which remains untested by the original wellbore. The course of action will be determined following a technical meeting on the 25th of March and the Company will provide an update on the Barchiz forward programme soon after this meeting.

Paul Barrett, Managing Director, said `We are aware that shareholders, like ourselves, are anxious to quantify the fruits of our labours at West Firsby, especially considering the current oil price. We expect the WF-9 well to perform in line with expectations and we will inform shareholders as soon as we know the results.

With regard to Berenx and Barchiz, we have made significant progress in understanding both the challenges and potential of both of these projects and again, will be looking to update the market as developments progress.'

Further information:

Europa Oil & Gas

Paul Barrett / Phil Greenhalgh Tel: +44 1235 553 266

finnCap

Sarah Wharry / Henrik Persson, Corporate Finance Tel: +44 207 220 0567 Joanna Weaving, Corporate Broking Tel: +44 207 600 1658

EUROPA OIL & GAS (HOLDINGS) PLC
Date   Source Headline
21st Jul 20147:00 amPRNCommencement of Drilling onshore UK & Operations Update
19th Jun 201411:41 amPRNFavourable Holmwood Court of Appeal Decision
29th May 20147:00 amPRNUpdate on Drilling of Wressle Prospect, Onshore UK
15th Apr 20147:00 amPRNInterim Results
24th Feb 20147:00 amPRNRenewal of Tarbes Val d’Adour Permit, France
12th Feb 20147:00 amPRNIssue of Options
10th Feb 20147:00 amPRNH1 Production & Revenue Update & Board Appointment
7th Feb 20145:05 pmPRNNewsletter
30th Jan 201410:37 amPRNDirector Share Purchase
27th Jan 20147:00 amPRNNotification of Interest in Shares
23rd Jan 20142:41 pmPRNDirector's Dealings
22nd Jan 20144:29 pmPRNNotification of Interest in Shares
20th Jan 20147:00 amPRNResult of Open Offer
15th Jan 201410:06 amRNSWithdrawal of requisition notice
13th Jan 20145:33 pmPRNNotification of Interest in Shares
13th Jan 20147:00 amPRNExtension of Licence PEDL 181, East Lincolnshire
10th Jan 20144:58 pmPRNNotification of Interest in Shares
10th Jan 20147:00 amPRNNotification of Interest in Shares
9th Jan 20148:59 amPRNCompletion of Placing
8th Jan 20143:00 pmRNSRequisition of General Meeting
23rd Dec 20131:18 pmPRNOpen Offer Shares Qualify for EIS and VCT Schemes
20th Dec 20137:00 amPRNOpen Offer
16th Dec 20132:00 pmRNSDirector dealing
16th Dec 20137:00 amPRNPlacing and Open Offer
10th Dec 20134:47 pmPRNResult of AGM
10th Dec 20137:00 amPRNAGM Statement
24th Oct 20137:00 amPRNCompletion of 3D Seismic Offshore Ireland
11th Oct 20137:00 amPRNFinal Results
3rd Oct 20133:15 pmPRNRenewal of Béarn des Gaves Permit, Onshore France
23rd Sep 20137:00 amPRNUpdate on Holmwood, Onshore UK
9th Sep 20137:00 amPRNOperations Update
25th Jul 20133:56 pmPRNFavourable Holmwood High Court Decision
24th Jul 20133:12 pmPRNDirectors Dealing
24th Jul 20137:00 amPRNDirector's Dealings
23rd Jul 20137:00 amPRNUpdate re French Exploration Permits
15th Jul 20137:00 amPRNCommencement of 3D Seismic, Offshore Ireland
24th Jun 20137:00 amPRNPlanning Application Granted to Drill Well Onshore UK
21st May 20137:00 amPRNRelinquishment of Licences in Romania & the SADR
13th May 20137:00 amPRNKosmos Farm-in to Europa’s Irish Licences Approved
26th Apr 20137:00 amPRNInterim Results
18th Apr 20137:00 amPRNKosmos Energy to Farm-in to Europa’s Irish Licences
19th Mar 20137:00 amPRNSeismic Acquisition Commences on PEDL181, UK Onshore
19th Feb 20137:00 amPRNUpdate on First Half Production and Revenues
16th Jan 20137:00 amPRNUpdate on Irish Atlantic Margin Prospects
12th Dec 201211:56 amPRNResult of AGM
11th Dec 20127:00 amPRNAGM Statement
6th Nov 20127:00 amPRNPositive Update on Irish Atlantic Margin Prospects
1st Nov 20127:00 amPRNHolmwood Prospect Appeal Decision to be Contested
25th Oct 20127:01 amPRNAward of Options
16th Oct 20127:00 amPRNFinal Results

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.