Pin to quick picksEnergean Oil & Gas Regulatory News (ENOG)

Share Price Information for Energean Oil & Gas (ENOG)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 1,103.00
Bid: 1,099.00
Ask: 1,100.00
Change: 24.00 (2.22%)
Spread: 1.00 (0.091%)
Open: 1,120.00
High: 1,120.00
Low: 1,077.00
Prev. Close: 1,079.00
ENOG Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Trading Statement & Operational Update

18 May 2023 07:00

RNS Number : 7978Z
Energean PLC
18 May 2023
 

 

THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION

 

 Energean plc

("Energean" or the "Company")

 

Trading Statement & Operational Update

London, 18 May 2023 - Energean plc (LSE: ENOG, TASE: אנאג) is pleased to provide an update on recent operations and the Group's trading performance in the 3-months to 31 March 2023.

Highlights - Financial and Corporate

· Revenues for the period were $288.8 million, a 69% increase versus Q1 2022 ($170.7 million)

· EBITDAX for the period was $162.2 million, a 81% increase versus Q1 2022 ($89.6 million)

· Group cash as of 31 March 2023 was $379.6 million (including restricted amounts of $11.5 million) and total liquidity was $943.5 million

· Q1 2023 dividend of 30 US$ cents/share declared today, scheduled to be paid on 30 June 2023

· Emissions intensity[1] for the period was 11.1 kgCO2e/boe, a 36% reduction versus Q1 2022 (17.2 kgCO2e/boe)

Emissions intensity1 in the four-months to 30 April 2023 was 10.1 kgCO2e/boe

Highlights - Operational

· Production for the period was 94.4 kboed, a 161% increase versus Q1 2022 (36.1 kboed)

Production in the four-months to 30 April 2023 was 100.0 kboed (82% gas)

· Commercial period under the gas sales agreements in Israel commenced for gas buyers on or before 1 April 2023[2], with production continuing to ramp up

· Three hydrocarbon liquid cargoes cumulating in approximately 1 million bbls from Karish sold to Vitol year to date

· The second gas export riser was successfully installed at Karish in March 2023; followed by key Karish North infrastructure in March and April 2023

· Olympus development concept chosen to align with strategy to optimise free cash flows and shareholder value

Tie-back to Energean Power FPSO, with Olympus prioritised over Tanin

Production plateau maintained by monetising newly discovered resources that do not incur seller royalties nor carry export restrictions

Focus maintained on capital discipline: Lower cost development versus Tanin driving lower capital expenditure for the next phase of tie-backs to the Energean Power FPSO; plus avoiding significant capital expenditure to add capacity through FPSO expansion projects or a new FPSO/FPU

Production expected to underpin existing gas sales agreements plus target international markets that can be accessed through existing and planned third party infrastructure

Outlook

· Full year production guidance revised to 125 - 140 kboed (from 131 - 158 kboed) due primarily to:

Revised gas sales forecast in Israel with full year quantities now expected to be 4.5 - 5.0 bcm (versus 4.5 - 5.5 bcm) due to the ramp up profile of buyer offtake and ongoing optimisation of the operations of the Energean Power FPSO

Higher-than-expected decline from NEA#6 in Egypt following the positive initial flow rates. There is no expected read-across to the PY#1 and NI#1 wells; extended flow testing is required at NEA#5 to confirm no read-across for this well. These three remaining NEA/NI wells are expected onstream over the course of 2023; NEA#5 drilling was completed in May 2023 with results in line with pre-drill geological expectations.

· Karish growth projects on track for completion by end-2023

· On track to deliver near-term targets of 200 kboed, $2.5 billion revenues, $1.75 billion EBITDAX and leverage < 1.5x in 2H 2024, and pay dividends in line with previously communicated policy

· Final investment decision on the Olympus Area expected in late 2023

· Orion 1X spud expected towards the end of the year

 

Mathios Rigas, Chief Executive Officer of Energean, commented:

"We are ramping up production from the Karish field and have seen four months of solid gas and liquids production in Israel, whilst optimising the operations of the Energean Power FPSO. Our Israeli gas contracts have moved to commercial status and our buyers are increasing nominations. This year, Energean expects to supply a significant proportion of Israel's gas demand.

"This is why we are moving quickly to develop our newly discovered Olympus Area resource, as efficiently as possible. As there is limited incremental capex, the initial development concept is in line with our stated commitment to remain capital disciplined. With no seller royalty payments or export restrictions, this strategy will create sustainable value for all our stakeholders and allow us to maintain and grow our stated sector-leading dividend policy.

"We continue to focus on our Net Zero stated path through continuous reductions in our carbon intensity. We are and will remain a responsible hydrocarbon producer. We are committed to being the best version of Energean we can be: provide a secure and reliable energy supply, support our communities and underwrite the transition."

 

Enquiries

 

For capital markets: ir@energean.com

 

Kate Sloan, Head of IR and M&A Tel: +44 7917 608 645

 

For media: pblewer@energean.com

 

Paddy Blewer, Head of Corporate Communications Tel: +44 7765 250 857

 

 

 

Energean Operational & Financial Review

 

Production

Average working interest production for the three months to 31 March 2023 was 94.4 kboed, increasing to 100 kboed (82% gas) for the 4-months to 30 April 2023.

Energean's full year production guidance is significantly second half-weighted due to the timing of its projects, and particularly the ramp up of production from Karish. Energean is adjusting its full year 2023 production guidance range to 125 - 140 kboed (from 131 - 158) kboed for reasons outlined in the country-specific sections below.

In Israel:

· Commercial sales under the gas sales agreements commenced on or before 1 April 2023[3] following the completion of commissioning under the GSPAs.

· Energean is narrowing its full year gas production guidance to 4.5 - 5.0 bcm (from 4.5 - 5.5 bcm), reflecting the above commencement date of commercial sales and the ramp up profile of buyer offtake from long-term contracted gas buyers (i.e. excluding spot sales) as they exit their obligations to other suppliers, combined with completion of activities to optimise the operations of the Energean Power FPSO.

· Energean has sales contracts with aggregate Annual Contracted Quantities ("ACQ") of 7.4 bcm on plateau. Buyers nominate volumes on a daily basis up to their Daily Contracted Quantities (ACQ divided by 365 days). On an annual basis the take-or-pay averages 75% of the ACQs.

· Oil production guidance reduced to between 13 and 16 kboed (previously 15 - 18 kboed) reflecting the revision to the expected management of production between the wells. There has been no change to the estimated hydrocarbon liquids yields across the fields.

In Egypt:

· As previously reported, NEA#6 delivered first gas on 6 March 2023. Initial rates were in line with expectations, but subsequently, the rate of decline has been higher than expected.

· NEA#5 completed drilling in May 2023, with results in line with pre-drill expectations. The well will be flow tested ahead of first gas later this year. The El Qaher-1 rig has now moved to drill the PY#1 well, after which NI#1 will be drilled. These three remaining NEA/NI wells are expected onstream over the course of 2023; there is no expected read-across to the PY#1 and NI#1 wells; extended flow testing is required at NEA#5 to confirm no read-across for this well.

· Abu Qir is performing in line with expectations

· As a result of the impact on NEA#6, Energean is revising its 2023 production guidance for Egypt to 23 - 25 kboed (from 28 - 32 kboed)

 

Rest of portfolio:

· 1Q 2023 production of 10.9 kboed was towards the top end of the guidance range following continued strong production across the Italian portfolio. Full year guidance is narrowed to 10 - 11 kboed

 

 

Three-months to 31 March 2023

Kboed

Three-months to 31 March 2022

Kboed

% change

Four-months to 30 April 2023

Kboed

FY 2023 guidance

Kboed

Israel

59.0

(inc. 0.7 bcm of sales gas)

-

-

64.5

(inc. 1.1 bcm of sales gas)

92 - 104 kboed

(including 4.5 - 5.0 bcm of sales gas)

Egypt

24.6

25.2

(2%)

24.9

23 - 25

Rest of portfolio

10.9

10.9

0%

10.7

10 - 11

Total production (including Israel)

94.4[4]

36.1

162%

100.04

125 - 140

 

 

Development

Israel - Karish Growth Projects

The completion of the second gas export riser, second oil train and Karish North projects will increase the total gas processing capacity of the Energean Power FPSO to a maximum of 8 bcm/yr (at 100% uptime). Energean has made good progress on these projects in the year-to-date: the second gas export riser was successfully installed in March 2023; the Karish North flowline in March 2023; and the Karish North manifold in April 2023. Completion of this suite of projects remains on track for the end of the year.

 

Israel - Olympus

The Olympus area is planned to be developed as a tie-back to the Energean Power FPSO, prioritised over the Tanin development, which is now expected to be deferred into the 2030s. The development concept has been selected to align with Energean's strategy of maximising shareholder value, which this concept achieves by optimising the free cash flow profile of the business because:

· Olympus resources can be developed at lower cost than those of Tanin due to closer proximity to the FPSO, resulting in lower capex for the next phase of tie-backs

· Significant capital expenditure on FPSO expansion projects is avoided as well as new major infrastructure investments

· Olympus resources carry no seller royalties: gas produced from the Karish and Tanin reservoirs bears 7.5% / 8.25% (pre-and post Sheshinsky levy) royalty on the value of production at the wellhead

Energean expects to submit the final field development plan for the Olympus Area to the Israeli Government in 3Q 2023 for approval and take final investment decision before year-end 2023.

Olympus gas production is anticipated to be sold into the Israeli domestic market under the existing gas sales agreements. As there are no export restrictions on gas produced from block 12, production in excess of domestic gas buyer nominations is expected to target demand in Egypt (including international markets through the LNG facilities) and Jordan, utilising existing export infrastructure and spare capacity in the Energean Power FPSO. Exports to Cyprus remain an option provided new pipeline infrastructure is developed by third parties.

 

Egypt

The remaining three NEA/NI well developments are expected to come onstream later in 2023, following which the project will reach peak production.

At Abu Qir, further infill and exploration targets to support production from the field are being studied for drilling in 2024.

 

Italy - Cassiopea

First gas remains on track for 2024. Offshore seabed survey campaigns have been completed ahead of the planned pipeline installation.

 

Greece

Energean has begun FEED activities on the Prinos CCS project.

 

Croatia

Energean expects to take final investment decision for the Irena gas field development in 2023. The field has 2P reserves of 13.3 Bcf (2.3 MMboe).

 

Exploration and Appraisal

The Orion-1X (Energean, 30%), located on the North East Hap'y Concession, offshore Egypt, is expected to spud in late 2023. Energean is finalising the farm out of 12% of its working interest (new ownership is 18%).

The Izabela-9 well (Energean, 70%) located offshore Croatia, is expected to spud in Q2/Q3 2023.

In Greece, 3D seismic interpretation on Block 2 (Energean, 75%) and a drill or drop decision on the Ioannina licence (Energean, 100%) is expected to be completed in 2023.

On 16 May 2023, Energean submitted notice of its intention to terminate its Montenegrin exploration licences (Blocks 26 and 30).

 

Corporate

Financing

Energean intends to refinance its 2024 Energean Israel Limited bond to maintain an efficient capital structure.

ESG

The Group's Scope 1 and 2 carbon emissions intensity in Q1 2023 was estimated to be approximately 11.1 kgCO2e/boe, a 36% reduction versus 2022 emissions levels; and a 83% reduction versus the 2019 base measurement year. Energean expects to further reduce emissions intensity to 7.0 - 9.5 kgCO2/boe in 2023 on its path to net zero by 2050.

 

Financial

 

The table below presents Energean's key results to 31 March 2023.

 

Three months to 31 March 2023

Three months to 31 March 2022

% change

Revenues

$ million

288.8

170.7

69%

Cost of production

$ million

116.5

62.3

87%

Cost of production

$/boe

13.7

19.2

(29%)

Cash G&A

$ million

11.7

8.2

42%

Adjusted EBITDAX

$ million

162.2

89.6

81%

Capital expenditure

$ million

92.8

74.3

25%

Exploration expenditure

$ million

14.3

5.8

147%

Decommissioning expenditure

$ million

1.2

0.6

100%

Cash (including restricted amounts)[5]

$ million

379.6

812.7

(53%)

Net debt - consolidated

$ million

2,646.8

2,148.3

23%

Net debt - plc excluding Israel

$ million

214.2

119.8

79%

Net debt - Israel

$ million

2,432.6

2,028.4

20%

 

 

2023 Guidance

FY 2023

Revised Guidance

FY 2023

Previous Guidance

Production

 

 

Israel (kboed)

92 - 104

94 - 115

Egypt (kboed)

23 - 25

28 - 32

Rest of Portfolio (kboed)

10 - 11

9 - 11

Total Production (kboed)

125 - 140

131 - 158

 

 

 

Consolidated net debt ($ million)

2,700 - 2,900

2,600 - 2,800

Cash Cost of Production (operating costs plus royalties)

Israel ($ million)

300 - 350

350 - 400

Egypt ($ million)

40 - 50

50 - 60

Rest of portfolio ($ million)

160 - 200

200 - 240

Total Cash Cost of Production ($ million)

500 - 600

600 - 700

 

 

 

Development and production capital expenditure

Israel ($ million)

170 - 200

140 - 160

Egypt ($ million)

140 - 150

140 - 150

Rest of portfolio ($ million)

270 - 290

300 - 330

Total development & production capital expenditure ($ million)

580 - 640

580 - 640

Exploration expenditure ($ million)

50 - 60

40 - 60

Decommissioning expenditure ($ million)

20 - 30

30 - 40

 

Inside Information

Some of the information contained within this announcement is considered by Energean to constitute inside information, as defined under the EU Market Abuse Regulation, EU No.596/2014 (which forms part of domestic UK law pursuant to the European Union (Withdrawal) Act 2018. By the publication of this Announcement via a Regulatory Information Service, this inside information is now considered to be in the public domain. The person responsible for arranging for the release of this announcement on behalf of Energean is Eleftheria Kotsana, Company Secretary.

 

Forward looking statements

This announcement contains statements that are, or are deemed to be, forward-looking statements. In some instances, forward-looking statements can be identified by the use of terms such as "projects", "forecasts", "on track", "anticipates", "expects", "believes", "intends", "may", "will", or "should" or, in each case, their negative or other variations or comparable terminology. Forward-looking statements are subject to a number of known and unknown risks and uncertainties that may cause actual results and events to differ materially from those expressed in or implied by such forward-looking statements, including, but not limited to: general economic and business conditions; demand for the Company's products and services; competitive factors in the industries in which the Company operates; exchange rate fluctuations; legislative, fiscal and regulatory developments; political risks; terrorism, acts of war and pandemics; changes in law and legal interpretations; and the impact of technological change. Forward-looking statements speak only as of the date of such statements and, except as required by applicable law, the Company undertakes no obligation to update or revise publicly any forward-looking statements, whether as a result of new information, future events or otherwise. The information contained in this announcement is subject to change without notice.

 

 


[1] Scope 1 and 2 emissions

[2] With the exception of one GSPA, whose commercial period begins in November

[3] With the exception of one GSPA, whose commercial period begins in November

[4] Total differs to the sum of the countries due to rounding

[5] Restricted amounts of $11.5 million

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
TSTARMPTMTTBBRJ
Date   Source Headline
22nd Apr 20244:05 pmRNSDirector/PDMR Shareholding
19th Apr 20241:00 pmRNSAnnual Financial Report and Notice of AGM
10th Apr 20247:00 amRNSMorocco Farm-in Completed and Rig Contract Signed
10th Apr 20247:00 amRNSCompletion of Energean Transaction
4th Apr 20244:10 pmRNSDirector/PDMR Shareholding
4th Apr 20244:10 pmRNSDirector/PDMR Shareholding
4th Apr 20244:10 pmRNSDirector/PDMR Shareholding
2nd Apr 20243:53 pmRNSDirector/PDMR Shareholding
2nd Apr 20243:53 pmRNSDirector/PDMR Shareholding
21st Mar 20247:01 amRNSEnergean Israel Full Year 2023 Accounts
21st Mar 20247:00 amRNS2023 Full Year Results
6th Mar 20245:07 pmRNSBlock Listing Six Monthly Return
29th Feb 20247:00 amRNSKarish North Online and New GSPA Signed
22nd Feb 20247:00 amRNS4Q 2023 Dividend Declaration
9th Feb 20244:26 pmRNSHolding(s) in Company
31st Jan 202412:47 pmRNSChanges to Board Committee Membership
18th Jan 20247:00 amRNSTrading Statement & Operational Update
29th Dec 202310:30 amRNSTotal Voting Rights
20th Dec 202312:30 pmRNSDirector/PDMR Shareholding
13th Dec 20236:10 pmRNSConversion of Convertible Loan Notes
13th Dec 20237:57 amRNSSecondary placing of shares in Energean plc
7th Dec 20237:00 amRNSMorocco Country Entry
24th Nov 20233:41 pmRNSHolding(s) in Company
16th Nov 20237:01 amRNSEnergean Israel 3Q 2023 Accounts
16th Nov 20237:00 amRNSDirectorate Change and Board Committee Membership
16th Nov 20237:00 amRNS3Q 2023 Dividend Declaration
16th Nov 20237:00 amRNSTrading Statement & Operational Update
14th Nov 20237:00 amRNSDirectorate Change
12th Oct 20233:53 pmRNSDirector/PDMR Shareholding
25th Sep 20234:25 pmRNSDirector/PDMR Shareholding
11th Sep 20234:10 pmRNSDirector/PDMR Shareholding
7th Sep 20235:35 pmRNSTASE Record Date Correction
7th Sep 20233:48 pmRNSBlock Listing Six Monthly Return
7th Sep 20237:02 amRNSEnergean Israel Half Year 2023 Accounts
7th Sep 20237:00 amRNS2Q 2023 Dividend Declaration
7th Sep 20237:00 amRNSResults for Half Year Ended 30 June 2023
28th Jun 20237:00 amRNSPricing of US$750m Senior Secured Notes
19th Jun 20237:00 amRNSLaunch of US$650m Senior Secured Notes Offering
5th Jun 20233:57 pmRNSDirector/PDMR Shareholding
25th May 202310:42 amRNSDirector/PDMR Shareholding
22nd May 20231:27 pmRNSDirector/PDMR Shareholding
22nd May 20231:27 pmRNSDirector/PDMR Shareholding
22nd May 20231:27 pmRNSHolding(s) in Company
18th May 20233:07 pmRNSEnergean Israel 1Q 2023 Accounts
18th May 20231:47 pmRNSResult of AGM
18th May 20237:00 amRNS1Q 2023 Dividend Declaration
18th May 20237:00 amRNSTrading Statement & Operational Update
28th Apr 202312:00 pmRNSTotal Voting Rights
27th Apr 20232:30 pmRNSDirector/PDMR Shareholding
26th Apr 20232:30 pmRNSDirector/PDMR Shareholding

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.