Roundtable Discussion; The Future of Mineral Sands. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksEnergean Oil & Gas Regulatory News (ENOG)

Share Price Information for Energean Oil & Gas (ENOG)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 1,106.00
Bid: 995.00
Ask: 1,147.00
Change: 0.00 (0.00%)
Spread: 152.00 (15.276%)
Open: 0.00
High: 0.00
Low: 0.00
Prev. Close: 1,106.00
ENOG Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Edison E&P Transaction Update

29 Jun 2020 07:00

RNS Number : 2946R
Energean PLC
29 June 2020
 

THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION

 

Energean plc

("Energean" or the "Company")

 

Edison E&P Transaction Update

Revised Combined Group Guidance

 

London, 29 June 2020 - Energean plc (LSE: ENOG, TASE: אנאג), the gas producer focused on the Mediterranean, issues an update on its acquisition of Edison E&P and revised group guidance.

Further to its announcement on 19 May 2020, Energean is pleased to announce that it has entered into further amended terms for its acquisition of Edison E&P following which, inter alia, the Norwegian subsidiary will be formally excluded from the transaction perimeter. Combined with the previously announced exclusion of the Algerian asset, $466 million of total reductions to the original consideration1 have now been agreed. Had completion occurred on 31 May 2020, the net consideration payable under the acquisition agreement, as now amended, would have been $178 million.

Highlights

Revised terms

· The gross consideration[1] for the transaction is now $284 million, which compares to the original sum of $750 million.

· The combined amendments to the original Sale and Purchase Agreement ("SPA") will, inter alia, result in a $466 million reduction to the gross consideration1 . This includes:

i) $155 million reduction relating to the exclusion of the Algerian asset from the transaction perimeter;

ii) $200 million reduction relating to exclusion of the Norwegian subsidiary from the transaction perimeter; and

iii) $111 million of additional reductions relating to the macro environment.

· Under the amended SPA, the net consideration which would have been payable had completion occurred on -31 May 2020 (which would have taken into account 17 months of business results since the locked-box date of the transaction), would have been $178 million. Energean does not expect this number to change materially before actual completion.

· The UK North Sea subsidiaries, which includes interests in the large Glengorm and Isabella gas-condensate discoveries, will now be retained within the perimeter of the transaction, further supplementing the growth potential of the enlarged group.

· The $100 million Cassiopea contingent payment will now vary between $0 and $100 million, depending on future Italian gas prices at the point in time at which first gas production is delivered from the field.

 

The path to closing

· A $220 million Reserve Based Lending facility has been signed with ING, Natixis and Deutsche Bank and has replaced the acquisition bridge facility that was put in place on 3 July 2019.

· Publication of the Shareholder Circular and Prospectus is expected later today, subject to FCA approvals, and the General Meeting to approve the transaction has been scheduled for 20 July 2020.

· Grant of the outstanding formal government approvals and completion of the carve-outs of the Algerian assets and Norwegian subsidiary is expected in the next few months.

· Energean is working to complete the transaction as soon as possible in 2H 2020.

 

Updated guidance for the combined group, post completion of the Edison E&P acquisition

· The Energean group will have working interest 2P reserves plus 2C resources of more than 800 million barrels of oil equivalent ("mmboe"). 72% of this is gas, approximately 96 billion cubic metres ("bcm"), of which - approximately 85 bcm - will be sold under long-term gas pricing contracts that largely insulate the group's revenues from global commodity price fluctuations.

· 2020 pro forma production guidance is 44.5 - 51.5 thousand barrels of oil equivalent per day ("kboed").

· 2020 pro forma capital expenditure guidance has been further reduced to $760 - 780 million from $840 million. This decrease is despite the inclusion of $25 - 30 million of capital expenditure expected on the UK North Sea assets and, therefore, reflects a further $85 - 110 million reduction to underlying capital expenditure guidance.

 

Mathios Rigas, Chief Executive, Energean commented:

"We are pleased to have agreed revised terms for our acquisition of Edison E&P, which will now exclude the Algerian assets and Norwegian subsidiary, and for which we have agreed $466 million of total reductions to the original consideration. I look forward to completing the transaction, which I believe represents excellent value for our shareholders and also enhances our material, gas-focused platform for value creation in the Eastern Mediterranean. Upon completion, our core focus, alongside the Karish project, will be integrating our teams and portfolios, which will further secure our long-term, resilient cash flow profile and option-rich portfolio.

"Following completion, around 70% of our production will be sold under long-term gas sales agreements that insulate our future revenues against oil price volatility. We will continue to own and operate the majority of our asset base, and are well-funded for all of our projects.

"Our financial and operational positioning will ensure that we can continue to grow the business but also respond quickly and appropriately to changes in the macro environment, if needed, to protect our business and our shareholders."

 

Amendments to the SPA

On 4 July 2019, Energean entered into a conditional sale and purchase agreement to acquire Edison E&P from Edison S.p.A. for $750 million[2], with additional contingent consideration of $100 million payable following first gas production from the Cassiopea development.

 

Since this date, Energean and Edison have agreed a number of amendments to the SPA, in which:

· The Algerian assets will be excluded from the scope of the acquisition;

o In recognition of the exclusion of the Algerian assets, there will be an adjustment to the gross consideration of the acquisition of $155 million[3];

· The Norwegian subsidiary will be excluded from the scope of the acquisition;

o In recognition of the exclusion of the Norwegian subsidiary of Edison E&P, there will be a $200 million reduction to the gross consideration for the acquisition3;

· There will be an additional reduction to the gross consideration of $111 million3, reflecting the changes in the macro environment since July 2019; and

· The $100 million Cassiopea contingent payment will now vary between $0 and $100 million, depending on future gas prices in Italy at the point in time at which first gas production is delivered from the field.

o $0 will be payable if the arithmetic average of the year one (i.e. the first year after the year in which first gas production occurs) and year two (i.e. the second year after the year in which first gas production occurs) Italian PSV futures prices is equal to or less than €10/Mwh (equivalent to approximately $3.4/mcf) when first gas production is delivered from the field.

o $100 million is payable if that average price is equal to or exceeds €20/Mwh (equivalent to approximately $6.8/mcf)

Separately, following the drilling of the North East Hap'y and North Thekah Offshore wells, neither of which resulted in a commercial discovery, the requirement to pay an 8% royalty on profit oil generated by commercial discoveries in North East Hap'y or North Thekah related to these two wells will no longer be triggered.

Consideration reconciliation

 

Following the various amendments to the SPA, the estimated consideration payable for the transaction can be described by the following steps, and is reconciled in the table below:

 

Gross consideration2 before economic performance of the assets to be acquired:

1. The original enterprise value of the transaction, as announced on 4 July 2019, was $750 million;

2. There is an effective reduction to the gross consideration of $155 million3 relating to exclusion of the Algerian assets from the perimeter of the transaction;

3. There is an effective reduction to the gross consideration of $200 million3 relating to exclusion of the Norwegian subsidiary from the perimeter of the transaction;

4. There is reduction of $31 million, relating to the schedule of provisions and other items not included within the enterprise value; and

5. The original enterprise value of the transaction has been reduced by $80 million, reflecting changes in the macro environment since 4 July 2019.

As a result of the above adjustments, the gross consideration3 for the transaction has been reduced to $284 million from an original enterprise value of $750 million.

 

Between 1 January 2019 and 31 May 2020, the assets to be retained within the transaction perimeter have generated net cash flows of:

- $206 million of Free Cash Flow (after development and production capital expenditure)

- $89 million of Free Cash Flow, after development and production capex and further deducting $117 million of exploration capital expenditure associated with the drilling of four exploration wells, all of which were either deepwater or complex wells, and can be considered as one-off expenditures.

The sale and purchase agreement signed on 4 July 2019 also contained several adjustments relating to provisions and other items not reflected in the enterprise value of Edison E&P. The net impact of these adjustments is to reduce the gross consideration by a further $17 million. Offsetting these items against the gross consideration of $284 million above gives an estimated net consideration (net of cash acquired) of $178 million. This figure is subject to change according to the economic performance of the assets to be retained between 31 May 2020 and completion of the transaction. Energean does not expect the net consideration payable to change materially on completion.

 

 

 

Amount

$ million

Resulting Net Consideration

$ million

Original Consideration

750

 

Algeria removed from perimeter

(155)

 

Further SPA provisions adjustments

(31)

 

Norway removed from perimeter

(200)

 

Sale and Purchase Agreement adjustments

(80)

 

Net Enterprise Value at locked-box date (1 January 2019)

 

284

 

 

 

Working capital adjustments as of locked box date

(17)

 

Economic performance to 31 May 2020 before exploration capital expenditure - assets to be acquired

(206)

 

Exploration capital expenditure over the period

117

 

Net consideration payable, net of cash acquired had the transaction completed on 31 May 2020

 

178

 

 

Inclusion of UK North Sea

Following the withdrawal of Neptune Energy from its agreement to acquire the UK North Sea and Norwegian subsidiaries in May 2020, Energean will now retain the UK subsidiaries within the perimeter of the transaction. The UK portfolio includes a 25% interest in the Glengorm discovery and a 10% interest in the Isabella discovery, announced in 2019 and 2020, respectively. Glengorm is one of the biggest discoveries in the UK North Sea in the last decade and contained an estimated 250 million barrels of oil equivalent (gross) based on operator estimates. A two-well appraisal programme is scheduled to commence in 4Q 2020 / 1Q 2021 and could represent an attractive source of resource upside for the enlarged group's portfolio. An appraisal programme is also expected on the Isabella discovery in a similar timeframe, contributing additional near-term value creation potential.

 

DeGolyer & Macnaughton ("D&M") Competent Person's Report ("CPR")

D&M has prepared an independent CPR on the Edison E&P assets being acquired, which will be published in full in the Shareholder Circular that is expected to be published later today. At 31 December 2019, D&M certifies 190 mmboe of 2P reserves and 36 mmboe of 2C resources, excluding any contribution from the Glengorm and Isabella discoveries in the UK North Sea.

 

Country

Working Interest 2P Reserves - mmboe

Working Interest 2C Resources -

mmboe

Working Interest 2P + 2C

mmboe

Egypt

114

-

114

Southern Europe[4]

73

36

109

UK North Sea

4

-

4

Total Edison E&P assets to be acquired

190

36

226

Energean standalone

342

260

602

Combined Business

532

296

828

 

 

Financing Update

On 20 June 2020, Energean signed a $220 million Reserve Based Lending facility ("RBL") with ING (in its capacity as Mandated Lead Arranger, Facility Agent, Documentation Bank and Technical Bank), Natixis (in its capacity as Mandated Lead Arranger, Technical Bank and Modelling Bank) and Deutsche Bank (in its capacity as Mandated Lead Arranger and Account Bank). The RBL has replaced the outstanding $255 million acquisition bridge facility and which is available for both debt and issuance of letters of credit. The acquisition bridge facility was reduced from the original $600 million facility on 20 May 2020 in order to match the approximate size of the RBL.

The RBL has a tenor of six years from the closing date and is subject to semi-annual redeterminations. The interest rate on the RBL is LIBOR plus a margin of 4.75% per annum during the first, second and third years after closing, and 5.75% thereafter. The RBL carries covenants that are customary for this type of facility.

The RBL has an accordion option of up to $200 million, for a total facility limit of up to $420 million.

In addition to the RBL, Energean has entered into a standalone bilateral letter of credit facility with ING. The facility will be an up to GBP 80 million facility provided for the purpose of issuing letters of credit for United Kingdom decommissioning obligations and obligations under the United Kingdom licences and does not impact upon the availability of the new RBL. 

This RBL, along with the cash held in Energean plc, will be used to fund the net consideration, as outlined above, plus transaction costs and ongoing working capital requirements of the combined portfolio.

 

Path to Transaction Close

Energean expects the transaction to close later in 2020, the main outstanding steps being:

 

1. Shareholder Circular and Prospectus

- Following publication of this announcement, Energean will seek formal approval of its Shareholder Circular and Prospectus from the FCA;

- Subject to the FCA's approval, Energean expects to publish both documents later today; and

- Shareholder approval for the transaction will be sought at a General Meeting, expected to be held on 20 July 2020; details of the General Meeting will be provided in the Shareholder Circular.

 

2. Government approvals

- All outstanding government approvals are expected to be granted in the coming months, with Egypt still planned to be the last approval granted for logistical reasons.

 

3. Completion of Algerian and Norway carve-outs from Edison E&P

 

4. Transaction completion and technical relisting of the Company's shares

- Expected to occur later in 2020, shortly after formal approvals from Egypt

 

 

Edison portfolio trading update

Average Working Interest production from the Edison E&P portfolio (assets to be acquired under the amended SPA) in the three months to 31 March 2020 was 52.2 kboed. Production of the combined group was 54.5 kboed, above the top end of the full year guidance range of 44.5 - 51.5 kboed.

Country

1Q 2020 Average Working Interest Production kboed[5]

Southern Europe[6]

12.3

Egypt

39.6

UK North Sea

2.6

Total Combined Group

54.5

 

At 31 May 2020, net receivables after provisions in Egypt were $214 million (31 December 2019: $222 million), of which $136 million (31 December 2019: $126 million) were classified as overdue.

In Egypt, the Abu Qir and NEA capital expenditure profiles have been optimised to reflect the current trading environment. Investment in NEA will now be incurred ahead of commencement of infill drilling at Abu Qir.

 

 

 

 

 

Consolidated Group - 2020 Pro Forma Guidance[7]

The production and financial data below reflects the combined Energean and Edison E&P forecasts for the full year of 2020. Edison E&P will be consolidated into Energean's financial statements from the date of transaction completion, which is expected later in 2020. Energean will benefit from net cash flows between the locked-box date of 1 January 2019 and the date of transaction completion, through an adjustment to the variable consideration. Edison E&P figures are unaudited and subject to change.

 

Previous Guidance

FY 2020

 

Updated Guidance

FY 2020

 

Working Interest Production

 

 

Egypt (kboed)

32 - 37

34 - 37

Southern Europe (kboed)

10.5 - 13

9.5 - 12.5

UK North Sea (kboed)

N/A

1 - 2

Total Pro Forma Production (kboed)

42.5 - 50.0

44.5 - 51.5

 

 

 

Operating Costs (Cost of Production plus G&A)

 

 

- Egypt ($ million)

 

55 - 60

- Southern Europe ($ million)

 

105 - 120

- UK North Sea ($ million)

 

25 - 30

- Energean plc ($ million)

 

15 - 20

- Edison HQ ($ million

 

25 - 30

Total Cost of Production plus G&A ($ million)

 

225 - 260

 

 

 

 

Previous Guidance

Update Guidance

Development and Production Capital Expenditure

 

 

- Israel ($ million)

580

580

- Egypt ($ million)

100

40 - 50

- Southern Europe ($ million)

90

35 - 40

- UK North Sea ($ million)

NA

10 - 15

Total ($ million)

770

665 - 685

 

 

 

Exploration Capital Expenditure (Firm)

 

 

- Israel ($ million)

5

5

- Egypt ($ million)

60

70

- Southern Europe ($ million)

5

5

- UK North Sea ($ million)

NA

15

Total ($ million)

70

95

 

 

 

Abandonment Expenditure ($ million)

-

-

 

 

 

Total Capital Expenditure ($ million)

840

760 - 780

 

Enquiries 

Investors and Analysts

 

Kate Sloan, Head of IR & ECM

Media

Tel: +44 (0)7917 608 645 

Sotiris Chiotakis Tel: +30 210 8174 242

 

Inside Information

Some of the information contained within this announcement is considered by Energean to constitute inside information, as defined under the EU Market Abuse Regulation, EU No.596/2014 ("MAR"). By the publication of this Announcement via a Regulatory Information Service, this inside information is now considered to be in the public domain. The person responsible for arranging for the release of this announcement on behalf of Energean is Russell Poynter, Company Secretary.

Forward looking statements

This announcement contains statements that are, or are deemed to be, forward-looking statements. In some instances, forward-looking statements can be identified by the use of terms such as "projects", "forecasts", "anticipates", "expects", "believes", "intends", "may", "will" or "should" or, in each case, their negative or other variations or comparable terminology. Forward-looking statements are subject to a number of known and unknown risks and uncertainties that may cause actual results and events to differ materially from those expressed in or implied by such forward-looking statements, including, but not limited to: general economic and business conditions; demand for the Company's products and services; competitive factors in the industries in which the Company operates; exchange rate fluctuations; legislative, fiscal and regulatory developments; political risks; terrorism, acts of war and pandemics; changes in law and legal interpretations; and the impact of technological change. Forward-looking statements speak only as of the date of such statements and, except as required by applicable law, the Company undertakes no obligation to update or revise publicly any forward-looking statements, whether as a result of new information, future events or otherwise. The information contained in this announcement is subject to change without notice.

 

About Energean plc

Energean is a London Premium Listed FTSE 250 and Tel Aviv 35 Listed E&P company with operations offshore Israel, Greece and the Adriatic. In August 2017 the Company received Israeli Governmental approval for the FDP for its flagship Karish-Tanin gas development project, where it intends to use the only FPSO in the Eastern Mediterranean to produce first gas in 2021. Energean has already signed firm contracts for 5.6 Bcm/yr of gas sales into the Israeli domestic market. Future gas sales agreements will focus on both the growing Israeli domestic market and key export markets.

Energean has nine exploration licences offshore Israel, and a 25-year exploitation licence for the Katakolo offshore block in Western Greece and additional exploration potential in its other licences in Western Greece and Montenegro.

On 4 July 2019, Energean announced the conditional acquisition of Edison E&P for $750 million plus $100 million of contingent consideration. On 23 December 2019, Energean announced the exclusion of the Algerian assets from the transaction. On 29 June 2020, Energean announced the exclusion of the Norwegian subsidiary from the transaction and a revised enterprise value at the locked-box date of the transaction (1 January 2019) of $284 million. The acquisition of Edison E&P, exclusive of the Algerian assets and Norwegian subsidiary, is expected to complete later in 2020.

 

www.energean.com

 

[1] As at the locked-box date of the transaction of 1 January 2019

[2] As at the locked-box date of the transaction of 1 January 2019

[3] As at the locked-box date of the transaction of 1 January 2019

[4] Italy, Greece and Croatia

[5] Gas has been converted to barrels of oil equivalent using a conversion factor of 5.8 mcf/boe.

[6] Italy, Greece, Croatia

[7] Assumes full year of Edison E&P is consolidated. Due to the locked-box date of the transaction of 1 January 2019, all losses/gains post this date for the assets to be retained within the transaction perimeter belong to Energean. Edison E&P will be consolidated for the purposes of the enlarged group's accounts from the date of transaction close.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDUWSWRRKUNUAR
Date   Source Headline
22nd Apr 20244:05 pmRNSDirector/PDMR Shareholding
19th Apr 20241:00 pmRNSAnnual Financial Report and Notice of AGM
10th Apr 20247:00 amRNSMorocco Farm-in Completed and Rig Contract Signed
10th Apr 20247:00 amRNSCompletion of Energean Transaction
4th Apr 20244:10 pmRNSDirector/PDMR Shareholding
4th Apr 20244:10 pmRNSDirector/PDMR Shareholding
4th Apr 20244:10 pmRNSDirector/PDMR Shareholding
2nd Apr 20243:53 pmRNSDirector/PDMR Shareholding
2nd Apr 20243:53 pmRNSDirector/PDMR Shareholding
21st Mar 20247:01 amRNSEnergean Israel Full Year 2023 Accounts
21st Mar 20247:00 amRNS2023 Full Year Results
6th Mar 20245:07 pmRNSBlock Listing Six Monthly Return
29th Feb 20247:00 amRNSKarish North Online and New GSPA Signed
22nd Feb 20247:00 amRNS4Q 2023 Dividend Declaration
9th Feb 20244:26 pmRNSHolding(s) in Company
31st Jan 202412:47 pmRNSChanges to Board Committee Membership
18th Jan 20247:00 amRNSTrading Statement & Operational Update
29th Dec 202310:30 amRNSTotal Voting Rights
20th Dec 202312:30 pmRNSDirector/PDMR Shareholding
13th Dec 20236:10 pmRNSConversion of Convertible Loan Notes
13th Dec 20237:57 amRNSSecondary placing of shares in Energean plc
7th Dec 20237:00 amRNSMorocco Country Entry
24th Nov 20233:41 pmRNSHolding(s) in Company
16th Nov 20237:01 amRNSEnergean Israel 3Q 2023 Accounts
16th Nov 20237:00 amRNSDirectorate Change and Board Committee Membership
16th Nov 20237:00 amRNS3Q 2023 Dividend Declaration
16th Nov 20237:00 amRNSTrading Statement & Operational Update
14th Nov 20237:00 amRNSDirectorate Change
12th Oct 20233:53 pmRNSDirector/PDMR Shareholding
25th Sep 20234:25 pmRNSDirector/PDMR Shareholding
11th Sep 20234:10 pmRNSDirector/PDMR Shareholding
7th Sep 20235:35 pmRNSTASE Record Date Correction
7th Sep 20233:48 pmRNSBlock Listing Six Monthly Return
7th Sep 20237:02 amRNSEnergean Israel Half Year 2023 Accounts
7th Sep 20237:00 amRNS2Q 2023 Dividend Declaration
7th Sep 20237:00 amRNSResults for Half Year Ended 30 June 2023
28th Jun 20237:00 amRNSPricing of US$750m Senior Secured Notes
19th Jun 20237:00 amRNSLaunch of US$650m Senior Secured Notes Offering
5th Jun 20233:57 pmRNSDirector/PDMR Shareholding
25th May 202310:42 amRNSDirector/PDMR Shareholding
22nd May 20231:27 pmRNSDirector/PDMR Shareholding
22nd May 20231:27 pmRNSDirector/PDMR Shareholding
22nd May 20231:27 pmRNSHolding(s) in Company
18th May 20233:07 pmRNSEnergean Israel 1Q 2023 Accounts
18th May 20231:47 pmRNSResult of AGM
18th May 20237:00 amRNS1Q 2023 Dividend Declaration
18th May 20237:00 amRNSTrading Statement & Operational Update
28th Apr 202312:00 pmRNSTotal Voting Rights
27th Apr 20232:30 pmRNSDirector/PDMR Shareholding
26th Apr 20232:30 pmRNSDirector/PDMR Shareholding

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.