Operational Update

1 May 2013 07:30

RNS Number : 7052D
Empyrean Energy PLC
01 May 2013
Β 

1 May 2013

Β 

Empyrean Energy PLC

("Empyrean" or the "Company"; Ticker: (EME))

Sugarloaf Project: Onshore Texas, USA

Β 

Operational Update

Β 

Β·; Further increase in the 2013 drilling schedule at Sugarloaf AMI

Β 

Empyrean Energy (AIM: EME), the condensate and gas producer, is pleased to announce that further to the announcement on 6 March 2013, Marathon Oil Corporation (NYSE: MRO) has informed Empyrean that eight gross wells have been added to the drilling schedule for 2013. This brings the total gross wells anticipated to be drilled during calendar year 2013 up to 38 from the previously reported 30 wells. Clarification had been sought on a well that was spud in January and which had been inadvertently omitted from the updated drill schedule the Sugarloaf AMI partners had received recently - this well has been confirmed and included.

Β 

The current drilling schedule includes a program to test at least two Austin Chalk wells within the Sugarloaf AMI. The Austin Chalk overlies the Eagle Ford Shale which has been the focus of development activity to date. The most recent independent reserves report released by Empyrean on 14 December 2012 booked reserves based predominantly on Eagle Ford Shale locations. Successful testing and viable production from these Austin Chalk wells has the potential to add significantly to recoverable reserves and value.

Β 

Empyrean holds approximately 3 percent working interest in the Sugarloaf AMI. Recently received information confirms that there were 81 gross wells in production at the end of March 2013, an increase of 2 gross wells over the 79 gross wells known to be in production at the time of Empyrean's operational update dated 19 April 2013.

Β 

As previously stated, the 2013 drilling schedule may be subject to further revisions and change during the course of the year.

Β 

Β 

Empyrean CEO, Tom Kelly commented "Empyrean welcomes the inclusion of additional wells to an already exciting 2013 drilling schedule. Of particular importance are the Austin Chalk wells that have potential for a significant impact on reserves."

Β 

The information contained in this announcement was completed and reviewed by the Technical Director of Empyrean Energy Plc, Mr Frank Brophy BSc (Hons) who has over 40 years experience as a petroleum geologist.

Β 

Β 

Β 

Β 

Β 

For further information

Empyrean Energy plcΒ 

Tom Kelly

+618 9480 0111

Β 

Shore Capital

Anita Ghanekar

Edward Mansfield

+44 (0) 207 408 4090

Β 

Jonathan Charles

Lionsgate Communications

E: jcharles@lionsgatecomms.com

M: +44 (0)7791 892509Β 

www.lionsgatecomms.comΒ 

Β 

Β 

Notes to Editors:

Β 

Empyrean Energy Plc is an AIM listed (Ticker : EME) condensate and gas exploration and production company focused on the Eagle Ford Shale, Texas, USA. Other assets include a 10% working interest in the Riverbend Project, Texas, just north of the prolific Brookeland Field (Austin Chalk) as well as a 57.2% interest in the Eagle Oil Pool Development Project located in the San Joaquin Basin, southern California.

Β 

Empyrean's portfolio includes an interest in over 80 producing wells with scaleable growth potential from further development and exploration upside.

Β 

Β 

This information is provided by RNS
The company news service from the London Stock Exchange
Β 
END
Β 
Β 
MSCMMGGKVMLGFZG
Date   Source Headline
13th Dec 20177:14 amRNSDirector Retirement
12th Dec 20173:15 pmRNSInterim Results
11th Dec 20179:46 amRNSDempsey and Sacramento Basin Q&A report
8th Dec 20177:57 amRNSDempsey 1-15 well production update
4th Dec 20177:38 amRNSDempsey Gas well update
14th Nov 20177:28 amRNSDempsey Gas Well Update
1st Nov 20177:12 amRNSDempsey Gas Well Update
4th Oct 20177:00 amRNSDempsey Gas Well Update
28th Sep 201712:26 pmRNSNew Company Website
18th Sep 20177:45 amRNSDempsey Gas Well to Flow Test Multiple Zones
13th Sep 20177:23 amRNSFurther Significant Gas Shows at Dempsey
12th Sep 201710:00 amRNSHolding(s) in Company
11th Sep 20171:03 pmRNSResults of AGM
11th Sep 201710:08 amRNSCorporate Presentation
8th Sep 20177:29 amRNSSignificant Gas Shows at Dempsey 1-15 Well
7th Sep 20177:00 amRNSSeismic Data Results Exceed Expectations
4th Sep 20177:26 amRNSSignificant Gas Shows Continue at Dempsey
1st Sep 20177:11 amRNSHolding(s) in Company
31st Aug 20177:22 amRNSSignificant Gas Shows Continue at Dempsey
30th Aug 20178:21 amRNSSignificant Gas Shows in reservoir at Dempsey
29th Aug 20177:00 amRNSSignificant Gas Shows
23rd Aug 20177:25 amRNS3D survey Completed in Block 29/11 Offshore China
21st Aug 20177:51 amRNSDempsey 1-15 Natural Gas Well Drilling Update
18th Aug 201710:17 amRNSPosting of Annual Report and Notice of AGM
15th Aug 20171:30 pmRNSFinal Results
14th Aug 20177:20 amRNSDempsey 1-15 Natural Gas Well Drilling Update
9th Aug 20177:20 amRNSDempsey 1-15 Natural Gas Well Drilling Update
3rd Aug 20177:37 amRNS1Tcf+ Dempsey Natural Gas Well Drilling Ahead
2nd Aug 20173:30 pmRNSRaises £1,000,000 before costs at 8.5p per share
1st Aug 20178:01 amRNSDrilling to commence at Dempsey Well, California
20th Jul 20177:47 amRNSOperations Update for 1+ Tcf Dempsey Gas Well
10th Jul 20177:02 amRNSDrilling Contract Signed for 1Tcf+ Dempsey Well
6th Jul 20177:10 amRNSDrilling Permit Granted for 1Tcf+ Dempsey Well
5th Jul 20178:09 amRNSCompletion of Mako Well and Stabilised Flow Rates
28th Jun 20177:38 amRNSMako South-1 Gas Flow Test Results
26th Jun 20177:48 amRNSMako South-1 Well Drilling and Testing Update
21st Jun 20177:53 amRNSIncreased interest in Sacramento Basin Projects
20th Jun 20175:31 pmRNSEmpyrean raises £660,000
19th Jun 201711:15 amRNSHolding(s) in Company
19th Jun 20178:17 amRNSMako South-1 Well Drilling Update
16th Jun 20177:45 amRNSProjects Update
15th Jun 20179:11 amRNSOperational Presentation
15th Jun 20178:00 amRNSHolding(s) in Company
14th Jun 20179:16 amRNSAppointment of Board Director
13th Jun 201711:10 amRNSPlacing and Option Exercise to Advance Portfolio
13th Jun 201710:00 amRNSOption Amendment
8th Jun 201711:00 amRNS3D Survey Commences on Block 29/11, China
30th May 201712:30 pmRNSProjects Update
15th May 20171:43 pmRNSMulti Project Farm-In, Sacramento Basin,California
15th May 20179:30 amRNSDirector/PDMR Shareholding

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.