Less Ads, More Data, More Tools Register for FREE

Pin to quick picksCircle Oil Plc Regulatory News (COP)

  • There is currently no data for COP

Operating Update

20 Mar 2014 07:00

RNS Number : 7422C
Circle Oil PLC
20 March 2014
 



20 March 2014

 

Circle Oil Plc 

("Circle" or the "Company")

 

Operating Update

 

Circle Oil Plc (AIM: COP), the international oil and gas exploration, development and production company, is pleased to announce the following operating update.

 

 

Egypt

 

Al Amir SE Field ("AASE") and the Geyad Field

 

The AASE-19 well has now been hooked up as a Shagar producer and was producing at a rate of 517 bopd gross and 0.397 MMscf/d on 14 March, the first full 24 hours of production. The rig has moved to drill the infill AASE-21 well located about 1,000 metres south-east of the AASE-4 well and 800 metres north-west of the AASE-1X well to appraise both the Shagar and Rahmi sands for production.

 

Current gross daily production from the AASE and the Geyad Field continues at approximately 11,200 bopd and 11 MMscf/d.

 

Following completion of the current AASE-21 well, the rig is planned to move on to drill an infill support injector well in the north central part of the field prior to release on sub contract. In parallel, reservoir engineering studies are being advanced to develop a dynamic reservoir model to assess reservoir behaviour for the future. This will provide the necessary interactive picture for the effective and efficient management of the two producing fields going forward. This period of reservoir management study will also permit the planning of any future infill drilling both for producers and injectors to maximise reserve recovery for the medium and long term.

 

 

Oman

 

Block 49

 

The tender process for the forthcoming Block 49 commitment well is at the evaluation stage. The well provisionally named Shisr-1 is to be drilled on the north-western dip-slope of the Ghudun-Khasfah high, approximately 60 kilometres south-west and updip of the Dauka-1 well.

 

The well is targeting an Intra Haima seismic anomaly with an updip pinchout of the Safiq sands. The well is expected to be drilled to a TD of 2,500 metres with a top target at 2,350 metres with pre-drill P50 STOOIP 56 MMbo, with recoverable prospective resources estimated 14 MMbo.(1) Drilling is planned to commence within H1 2014 and is expected to take up to approximately 45 days without testing. This commitment well is regarded as high risk with a GCOS of 10-12% and completes Circle's commitment on the Block.

 

Block 52

 

The planned inshore 2D seismic survey on Block 52 is due to commence on 21 March with the seismic vessel MV Hindsagar. The programme is, as previously announced, to acquire 850 kilometres of 2D seismic data to map and prioritise the three inshore leads identified through interpretation of existing 2D data.

 

Oman 2013 bid round

 

In Oman, as previously indicated, the Company bid for an onshore Block in the 2013 bid round and continues to progress its bid with the relevant authorities.

 

 

Morocco

 

Sebou and Lalla Mimouna Permits

 

The drilling campaign scheduled to start in mid to end January 2014 has been delayed and all preparations slowed by the continuing seasonal rains in the Rharb. As in previous years significant areas within the concession area are subject to flooding which has been known to continue into late spring. Well proposals are now completed for the first six wells which are located on both permits with the first to be drilled in the Sebou permit. The Company is presently planning to drill 12 wells which includes the KAB-1 re-drill.

 

Current gross daily production from our producing gas wells in the Sebou permit is 7 MMscf/d.

 

 

Tunisia

 

Mahdia Block

 

Plans are well advanced for the drilling of the Mahdia commitment well with long lead items prepared for shipment, main and sub contractor tenders issued with some awarded and others under commercial evaluation or awaiting ETAP approvals. Subject to final negotiation and Tunisian authorities' approvals the drilling unit has been selected. A farm-out exercise is also underway with a number of companies signed-up to attend the data room this month with further promotion underway.

 

The licence is within the vicinity of many producing fields, including the Tazerka, Birsa, Oudna, and Halk El Menzel oil fields, and the Maamoura gas field. The most recent discovery, the Mahdia-2 well, located approximately 20 kilometres west of the Block, tested approximately 2,700 bopd from the Serdj carbonate reservoir. This is one of the several possible reservoir horizons proven by producing plays in the region.

 

The Mahdia exploration well provisionally designated El Medouini-1 is planned to test the stacked play potential of the El Mediouni prospect, including both the primary Birsa Sands target and the secondary fractured carbonates of the Ketatna and Abiod formations as well as the deeper Serdj carbonates. The Birsa Sands alone have an estimated pre-drill P50 case of 185 MMbbls STOOIP.(2) The El Mediouni-1 well will be drilled to a depth of up to 2,300 metres, targeting the stacked primary and secondary reservoir horizons between 1,000 metres and 2,100 metres in subsea depth. The recoverable prospective resources estimate for the El Medouini prospect is 46 MMbbls (2) for the Birsa objective alone, substantially larger than the recoverable commercial threshold for the area which sits at approximately 10 MMbo.

 

 

Annual Results

 

The Company is trading in line with management expectations and expects to issue its Preliminary Results announcement for the year ended 31 December 2013 at the end of May.

 

 

Prof Chris Green, CEO, said

 

"Circle is now entering an exciting and busy operational period in all of its geographies. We were pleased with the results of the sidetrack of the AASE-19 well, which will provide additional oil and gas production from the Al Amir SE field. Drilling operations offshore Tunisia and onshore Oman approach and we await the end of our frustrating delays in Morocco and being able to start our multi-well drilling campaign."

 

Glossary

boepd

barrels of oil equivalent per day

bopd

barrels of oil per day

GCOS

Geological Chance of Success

MD

Measured Depth

MMbo

Million barrels of oil

MMbbls

Million barrels

MMscf/d

Million standard cubic feet of gas per day

P50

50% chance of success

STOOIP

Stock Tank Oil Originally in Place

2D

Two Dimensional

3D

Three Dimensional

(1) Circle internal estimate post 2009 3D seismic interpretation

 

(2) Circle internal estimate post evaluation of 2013 3D seismic survey

 

In accordance with the guidelines of the AIM Market of the London Stock Exchange, Dr Stuart Harker, VP Geology, also with over 30 years experience, is the qualified persons as defined in the London Stock Exchange's Guidance Note for Mining and Oil and Gas companies, who have reviewed and approved the technical information contained in this announcement. Dr Harker has relied on primary information supplied by the operator in carrying out his review.

 

 

For further information contact:

 

Circle Oil Plc (+44 20 7638 9571)

Professor Chris Green, CEO

 

Investec (+44 20 7597 5970)

Chris Sim

George Price

James Rudd

 

Liberum Capital Limited (+44 20 3100 2222)

Simon Atkinson

 

Citigate Dewe Rogerson (+44 20 7638 9571)

Martin Jackson

Shabnam Bashir

 

Murray Consultants (+353 1 498 0320)

Joe Murray

Joe Heron

 

 

Notes to Editors

 

Circle Oil Plc (AIM: COP) is an international oil & gas exploration, development and production Company holding a portfolio of assets in Morocco, Tunisia, Oman, and Egypt with a combination of low-risk, near-term production, and significant upside exploration potential. The Company listed on AIM in October 2004.

 

Internationally, the Company has continued to expand its portfolio over the past years and now has assets in the Rharb Basin, Morocco; the Ras Marmour Permit in southern Tunisia; the Mahdia Permit offshore Tunisia, and the Zeit Bay area of Egypt. Circle also has the largest licensed acreage of any company in Oman. In addition to its prospective Block 52 offshore, Circle has an ongoing exploration programme in Block 49 onshore.

 

Circle's strategy is to locate and secure additional licences in prospective hydrocarbon provinces and, through targeted investment programmes, monetise the value in those assets for the benefit of shareholders. This could be achieved through farm-outs to selected partners who would then invest in and continue the development of the asset into production, or Circle may opt to use its own expertise to appraise reserves and bring assets into production, generating sustained cash flow for further investment.

 

Further information on Circle is available on its website at www.circleoil.net

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLJLMJTMBMBTTI
Date   Source Headline
8th Aug 20117:00 amRNSAppointment of Non-Executive Director
22nd Jul 20117:00 amRNSOperating Update Egypt
28th Jun 201110:11 amRNSPosting of Annual Report
20th Jun 20117:00 amRNSPreliminary Results
14th Jun 20113:14 pmRNSShareholdings in Company
9th Jun 20113:37 pmRNSBoard Change
8th Jun 20119:43 amRNSResources Update
26th May 20117:00 amRNSOperational Update - Morocco
23rd May 20117:00 amRNSOperating Update Egypt
19th Apr 20117:00 amRNSOperating Update Egypt
15th Apr 201110:00 amRNSDrilling Update Morocco
15th Mar 201112:20 pmRNSDrilling Update Morocco
11th Mar 20114:30 pmRNSStatement re: Libya Oil Holdings Ltd
10th Mar 201111:17 amRNSShareholdings in Company
8th Mar 20111:55 pmRNSShareholdings in Company
7th Mar 20114:37 pmRNSShareholdings in Company
10th Feb 20114:44 pmRNSShareholdings in Company
10th Feb 201111:25 amRNSShareholdings in Company
8th Feb 20112:18 pmRNSShareholdings in Company
8th Feb 20117:00 amRNSDrilling Update Morocco
2nd Feb 20114:16 pmRNSShareholdings in Company
2nd Feb 20114:05 pmRNSTR-1: Notification of Major Interest In Shares
31st Jan 20113:18 pmRNSUpdate Egypt
24th Jan 20117:00 amRNSDrilling Update Morocco
12th Jan 20114:27 pmRNSShareholdings in Company
10th Jan 20117:00 amRNSOperational Update Egypt
4th Jan 20117:00 amRNSDrilling Update Morocco
20th Dec 20107:00 amRNSEgypt Production and Drilling Update
26th Nov 201011:11 amRNSTotal Voting Rights - Month-End Disclosure
26th Nov 201011:08 amRNSBlock Listing Six Monthly Return
22nd Nov 201012:57 pmRNSOperational Update Egypt, Oman and Tunisia
29th Oct 201011:00 amRNSDrilling Update
28th Oct 201012:21 pmRNSBlocklisting Application and Exercise of Options
28th Oct 201012:19 pmRNSTR-1 Form
27th Oct 20104:20 pmRNSExercise of Options
26th Oct 20105:15 pmRNSExercise of Options
26th Oct 20105:15 pmRNSExercise of Options
26th Oct 20103:57 pmRNSHolding(s) in Company
26th Oct 20103:57 pmRNSHolding(s) in Company
21st Oct 20105:02 pmRNSHolding(s) in Company
21st Oct 20105:02 pmRNSHolding(s) in Company
20th Oct 20107:00 amRNSExercise of Options and Director's Dealings
18th Oct 20107:00 amRNSOperational Update
16th Sep 20103:06 pmRNSAnnual General Meeting
14th Sep 20107:00 amRNSInterim Results
13th Sep 20107:00 amRNSOperational Update - Egypt
9th Sep 20107:00 amRNSOperational Update Morocco and Oman
10th Aug 20107:00 amRNSOperating Update
6th Aug 20103:59 pmRNSShareholdings in Company
5th Aug 20102:30 pmRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.