Operations update, Spain

4 Aug 2011 13:03

RNS Number : 7628L
Leni Gas & Oil PLC
04 August 2011
 



Immediate Release

4 August 2011

 

 

Leni Gas & Oil PLC

("LGO" or the "Company")

 

Operations Update, Spain

 

 

Leni Gas & Oil plc today announces the reinstatement of production at the Hontomin-2 well in Northern Spain, and its immediate plans for further production enhancement at the Ayoluengo Field

 

During the last few weeks, operations at Hontomin have focused on cleaning the well and the perforating of an additional reservoir zone shallower than the previously producing interval. These operations were successfully concluded and the well was returned to production on the evening of the 29 July 2011.

 

A total of 13.5 metres of perforations were opened between 1349.5 and 1365 metres including 7.5 metres in new reservoir zones which were identified on wireline logs run earlier in July. The well continues to clean-up with water cut reducing and oil production increasing. The well is producing approximately 180 bfpd and the water cut has been falling over the last 4 days. During the last 24 hour period the well produced 15 barrels of oil and production is expected to continue to rise significantly as the static fluid level in the well is reduced and the new perforations contribute to oil flow. In October 2010, Hontomin-2 reached a production rate of over 85 bopd which was achieved without the 7.5 metres of newly opened perforations.

 

The Company-owned Cardwell rig has now been returned from Hontomin to the main Ayoluengo field 30 kilometres away where several wells from the recent well intervention program will be returned to production. Wells Ayo-22 and Ayo-32 are expected to be brought back on production within the next few weeks. Further routine maintenance work to other producing wells, including Ayo-18 and Ayo-40, also requiring the use of the Company's Cardwell service rig, will be undertaken and this is expected to lead to further improvements in overall production rates which have been performing as expected.

 

Design work for chemical stimulation in order to treat the scale and wax found in wells during the recent work-overs and further enhance production is progressing and field trials are planned for the autumn.

 

Neil Ritson, LGO's Chief Executive, commented:

"Hontomin-2 is an important well and we firmly expect further improvements in production as it cleans up. The return of the rig to Ayoluengo will allow us to consolidate the gains made during the recent interventions and therefore production from Spain is expected to exceed 400 bopd in the next few months. We are happy with the recent progress made in Spain and intend to update shareholders on further developments as soon as possible."

 

 

Competent Person's Statement:

The information contained in this announcement has been reviewed and approved by Neil Ritson, Chief Executive Officer and Director for Leni Gas & Oil Plc who has 35 years of relevant experience in the oil industry. Mr. Ritson is a member of the Society of Petroleum Engineers, an Active Member of the American Association of Petroleum Geologists and is a Fellow of the Geological Society of London.

 

 

Enquiries

 

Leni Gas & Oil plc

David Lenigas

Neil Ritson

+44 (0)20 7440 0645

 

Panmure Gordon

Katherine Roe

+44 (0) 20 7459 3600

Hannah Woodley

 

Shore Capital

Pascal Keane +44 (0) 20 7408 4090

Jerry Keen

 

Pelham Bell Pottinger

Mark Antelme

+44 (0) 20 7861 3232

Henry Lerwill

 

Beaumont Cornish Limited

Rosalind Hill Abrahams

Roland Cornish

+44(0) 20 7628 3396

 

 

Glossary

 

bfpd - barrels fluid per day

bopd - barrels oil per day

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCDKQDKBBKDBFK
Date   Source Headline
8th Apr 200912:09 pmRNSStatement Re-Gulf of Mexico
30th Mar 20097:00 amRNSEastern Hungary - Pen?szlek Development Expansion
20th Mar 200910:57 amRNSFour new Blocks in Gulf of Mexico
19th Mar 200911:54 amRNSHungary - Maiden Development Resources Report
19th Mar 200911:29 amRNSGulf of Mexico - MMS Lease Sale 208
10th Mar 20091:43 pmRNSCO2 sequestration development agreement
5th Mar 20092:59 pmRNSMonthly Production Update - February
25th Feb 20099:09 amRNSIncrease in Gulf of Mexico Oil & Gas Production
5th Feb 20097:00 amRNSHolding(s) in Company
4th Feb 200911:39 amRNSSignificant Shareholding
3rd Feb 20097:00 amRNSMonthly Production Update - January
29th Jan 20095:58 pmRNSHolding(s) in Company
21st Jan 200912:00 pmRNSHungary Production Update and New Developments
12th Jan 200911:00 amRNSMexico Production Update
9th Jan 20094:49 pmRNSRe Options
9th Jan 20097:00 amRNSMonthly Production Update - December
6th Jan 200910:19 amRNSCompletion & Production of Eugene Island
17th Dec 20087:00 amRNSSpain - Increased Production and Development Plans
12th Dec 20087:00 amRNSSpain - Increased Recoverable Reserves
11th Dec 20087:00 amRNSMonthly Production Update - November
1st Dec 200811:39 amRNSDrilling Update
12th Nov 20087:00 amRNSMonthly Production Update - October
10th Nov 20087:00 amRNSStatement re CO2 sequestration
31st Oct 200810:52 amRNSTotal Voting Rights
23rd Oct 20081:07 pmRNSHungary 3D Seismic Commencement replacement
23rd Oct 200812:23 pmRNSHungary 3D Seismic Commencement
23rd Oct 20087:00 amRNSMalta 2009 Work Program Approved
22nd Oct 20087:00 amRNSUnaudited Second Interim Results
21st Oct 20087:00 amRNSIncreased Oil Resources Identified In Spain
16th Oct 20082:05 pmRNSIssue of Equity
10th Oct 20087:00 amRNSAppointment of Broker
9th Oct 200812:32 pmRNSOperations Update - Gulf of Mexico
8th Oct 20087:00 amRNSMonthly Production Update
6th Oct 200812:00 pmRNSOperations Update - Gulf of Mexico
6th Oct 20087:00 amRNSOperations Update
30th Sep 20082:12 pmRNSTotal Voting Rights
25th Sep 20084:00 pmRNSUpdate on previously announced issue of equity
8th Sep 20087:00 amRNSMonthly Production Update
29th Aug 20083:41 pmRNSAccounting Reference Date
26th Aug 20084:17 pmRNSGulf of Mexico Operations Upd
19th Aug 200812:25 pmRNSHungary Gas Production Update
14th Aug 200810:10 amRNSSignificant Shareholding
12th Aug 200812:03 pmRNSIncrease in stake in Gulf of
12th Aug 200810:15 amRNSGas production commences in H
8th Aug 20083:25 pmRNSProduction Update
31st Jul 20084:00 pmRNSTotal Voting Rights
29th Jul 20084:52 pmRNSGulf of Mexico Update
29th Jul 20081:59 pmRNSPlacement
21st Jul 20082:16 pmRNSUpdate on Investment
21st Jul 200811:32 amRNSUpdate on Investment

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.