Operations update, Spain

4 Aug 2011 13:03

RNS Number : 7628L
Leni Gas & Oil PLC
04 August 2011
 



Immediate Release

4 August 2011

 

 

Leni Gas & Oil PLC

("LGO" or the "Company")

 

Operations Update, Spain

 

 

Leni Gas & Oil plc today announces the reinstatement of production at the Hontomin-2 well in Northern Spain, and its immediate plans for further production enhancement at the Ayoluengo Field

 

During the last few weeks, operations at Hontomin have focused on cleaning the well and the perforating of an additional reservoir zone shallower than the previously producing interval. These operations were successfully concluded and the well was returned to production on the evening of the 29 July 2011.

 

A total of 13.5 metres of perforations were opened between 1349.5 and 1365 metres including 7.5 metres in new reservoir zones which were identified on wireline logs run earlier in July. The well continues to clean-up with water cut reducing and oil production increasing. The well is producing approximately 180 bfpd and the water cut has been falling over the last 4 days. During the last 24 hour period the well produced 15 barrels of oil and production is expected to continue to rise significantly as the static fluid level in the well is reduced and the new perforations contribute to oil flow. In October 2010, Hontomin-2 reached a production rate of over 85 bopd which was achieved without the 7.5 metres of newly opened perforations.

 

The Company-owned Cardwell rig has now been returned from Hontomin to the main Ayoluengo field 30 kilometres away where several wells from the recent well intervention program will be returned to production. Wells Ayo-22 and Ayo-32 are expected to be brought back on production within the next few weeks. Further routine maintenance work to other producing wells, including Ayo-18 and Ayo-40, also requiring the use of the Company's Cardwell service rig, will be undertaken and this is expected to lead to further improvements in overall production rates which have been performing as expected.

 

Design work for chemical stimulation in order to treat the scale and wax found in wells during the recent work-overs and further enhance production is progressing and field trials are planned for the autumn.

 

Neil Ritson, LGO's Chief Executive, commented:

"Hontomin-2 is an important well and we firmly expect further improvements in production as it cleans up. The return of the rig to Ayoluengo will allow us to consolidate the gains made during the recent interventions and therefore production from Spain is expected to exceed 400 bopd in the next few months. We are happy with the recent progress made in Spain and intend to update shareholders on further developments as soon as possible."

 

 

Competent Person's Statement:

The information contained in this announcement has been reviewed and approved by Neil Ritson, Chief Executive Officer and Director for Leni Gas & Oil Plc who has 35 years of relevant experience in the oil industry. Mr. Ritson is a member of the Society of Petroleum Engineers, an Active Member of the American Association of Petroleum Geologists and is a Fellow of the Geological Society of London.

 

 

Enquiries

 

Leni Gas & Oil plc

David Lenigas

Neil Ritson

+44 (0)20 7440 0645

 

Panmure Gordon

Katherine Roe

+44 (0) 20 7459 3600

Hannah Woodley

 

Shore Capital

Pascal Keane +44 (0) 20 7408 4090

Jerry Keen

 

Pelham Bell Pottinger

Mark Antelme

+44 (0) 20 7861 3232

Henry Lerwill

 

Beaumont Cornish Limited

Rosalind Hill Abrahams

Roland Cornish

+44(0) 20 7628 3396

 

 

Glossary

 

bfpd - barrels fluid per day

bopd - barrels oil per day

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCDKQDKBBKDBFK
Date   Source Headline
3rd May 20177:00 amRNSGroup Operational Update
2nd May 20174:20 pmRNSTotal Voting Rights
2nd May 20177:00 amRNS2016 Results and Investor Briefing
18th Apr 20177:00 amRNSWell GY-683 on initial production at 80 bopd
6th Apr 20177:00 amRNSSecond successful infill well, GY-683, Goudron
5th Apr 20177:00 amRNSAppointment of Joint Broker
3rd Apr 20177:05 amRNSResult of Offer via PrimaryBid
3rd Apr 20177:00 amRNSSpud of Well GY-683, Goudron Field, Trinidad
31st Mar 20175:59 pmRNSFundraising of £2.5 million
22nd Mar 20177:00 amRNSWell GY-682 production, Goudron Field
13th Mar 20177:00 amRNSSuccessful well GY-682,Goudron Field
9th Mar 20172:12 pmRNSShare Payments to Directors and TVR
8th Mar 201711:52 amRNSCapital re-organisation and TVR
7th Mar 20172:23 pmRNSResult of General Meeting, Capital Re-organisation
6th Mar 20177:00 amRNSSpud of well GY-682, Goudron Field Trinidad
27th Feb 20177:00 amRNSDrilling Update, Trinidad
15th Feb 20179:30 amRNSNotice of GM
13th Feb 20177:00 amRNSOperational Update, Trinidad
9th Feb 20177:00 amRNSUpdate La Lora Concession, Spain
30th Jan 20177:00 amRNSLa Lora Concession, Spain
24th Jan 20177:00 amRNSOperational Update
13th Jan 20174:15 pmRNSUpdate, Spain
10th Jan 20177:00 amRNSDirectorate Change
4th Jan 20177:00 amRNSDrilling Update, Goudron Field, Trinidad
21st Dec 20165:18 pmRNSDirector/PDMR dealings
21st Dec 20168:16 amRNSCorporate Update
14th Dec 20164:44 pmRNSHolding(s) in Company
13th Dec 20167:00 amRNSPlacing to raise £1.18 m, total voting rights
12th Dec 20167:00 amRNSDrilling Update, Goudron Field Trinidad
9th Dec 20161:27 pmRNSFirst Close with Lind Partners
7th Dec 20165:57 pmRNSHolding(s) in Company
7th Dec 20168:33 amRNSLoan repayment and signing new funding agreement
29th Nov 20167:00 amRNSSale of Oil in Spain
22nd Nov 20165:59 pmRNSHolding(s) in Company
4th Nov 20167:00 amRNSOperational Update and 3Q Production
6th Oct 20163:24 pmRNSHolding(s) in Company
4th Oct 201611:45 amRNSWebinar, Friday 7 October
30th Sep 20165:15 pmRNSTotal Voting Rights
29th Sep 201610:01 amRNSHolding(s) in Company
28th Sep 20167:00 amRNSHalf-year Report
27th Sep 20167:00 amRNSAdditional Recompletion Wells GY-668 and GY-288
23rd Sep 201611:28 amRNSPlacing and TVR
7th Sep 20166:33 pmRNSHolding(s) in Company
31st Aug 20165:50 pmRNSTotal Voting Rights
22nd Aug 20167:00 amRNSSuccessful recompletion of GY-277, Goudron Field
18th Aug 20162:59 pmRNSIssue of Shares for Services, Total Voting Rights
28th Jul 201610:41 amRNSRecompletion of Well GY-673, Goudron Field
18th Jul 20167:00 amRNSUpdated Resource Assessment, Goudron Field
4th Jul 20162:53 pmRNSResult of AGM
1st Jul 20165:35 pmRNSTotal Voting Rights

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.