BNG operational update

17 Jan 2019 07:00

RNS Number : 3149N
Caspian Sunrise plc
17 January 2019
Β 

Caspian Sunrise PLC

("Caspian Sunrise" or the "Company")

BNG operational update

Β 

The Board of Caspian Sunrise are pleased to provide the following operational update at its flagship BNG asset.

Β 

Deep Well A5

Β 

Background

Β 

The well was drilled in 2013 to a depth of 4,432 meters. High pressure resulted in the well becoming blocked with excess drilling fluid and debris from the reservoir.

Β 

Subsequently a side-track at an angle of 15 degrees from a depth of 4,082 meters was successfully completed and a 5-inch liner run to the new bottom of the well.

Β 

Potential oil-bearing intervals of 105 meters have been identified.

Β 

For 15 days between 23 October 2017 and 27 November 2017 the well flowed at the rate of approximately 3,800 bopd before being restricted by a partial blockage, resulting in the flow rate falling to some 1,000 bopd.

Β 

Recent attempts to clear the well have been hampered by unwanted metal being lost in the well. Attempts to pull the metal from the well were not successful and the Company decided to remove the unwanted metal by using specialist milling tools to grind it down to a level where it should not interfere with the operation of the well.

Β 

Current position

Β 

Caspian Sunrise is pleased to report that milling operations continue to make progress at a current depth of 4,152 meters and expects to be in a position to test the well in the not too distant future.

Β 

Deep Well 801

Β 

Background

Β 

Deep Well 801 was originally drilled to a depth of 5,050 meters reaching Total Depth in July 2015. As with the other deep wells drilled at BNG the well was blocked by a combination of excess drilling fluids and rocks from the potential reservoir.

Β 

For an extended period, the Company sought to remove the blockage with the use of chemicals and by periodically opening and closing the well as pressures grew. During that time oil flowed to the surface under its own pressure.

Β 

In May 2018 the Company announced it successfully completed a 350 meter side-track from a depth of 4,501 meters by-passing the blocked pipe. A 5-inch liner was run to the new bottom of the borehole at a total depth of 4,852 meters.

Β 

During the drilling of the side-track we encountered four potentially oil-bearing intervals. The first of 6 meters between 4,535 and 4,541 meters; the second is of 20 meters between 4,554 and 4,574 meters; the third is of 59 meters between 4,635 and 4,694 and the fourth is of 36 meters betweenΒ 4,812 and 4,848 meters. Subsequently we perforated 75 meters of the intervals identified.Β 

Β 

Recently, the Company's approach with this well has been to allow the build-up of pressure inside and outside the tubing to reach its natural maximum. Caspian Sunrise plans at the appropriate time to divert this natural pressure back into the well to stimulate oil flow.

Β 

The pressure outside the tube built to some 610 ATM in December 2018, with pressure in the well reaching 380 ATM (ATM is the standard unit of pressure where one ATM is equivalent to 1.01325 bar). The well was opened before Christmas for several days to relieve the pressure outside the tube, which fell to around 100 ATM.

Β 

Current position

Β 

The pressure outside the tube is currently 490 ATM with the pressure in the tubing 300 ATM. Caspian Sunrise is now waiting for the natural pressure in the well to build further before looking to use that pressure to further stimulate the well ahead of testing.

Β 

Deep Well A6

Β 

Background

Β 

Deep Well A6 was drilled on the Airshagyl structure in 2015. The well was drilled to a depth of 4,516 meters but given the experience gained in drilling the earlier deep wells, the drilling phase proved easier although issues were encountered when drilling through the salt layer.

Β 

Caspian Sunrise has twice attempted without success to perforate up to a 60-meter section of the 100-meter oil bearing interval, using different contractors on each occasion. After further investigation it appeared that both attempts to perforate the well failed with little or no penetration of the casing to allow oil to flow.

Β 

Current position

Β 

We have appointed new advisers experienced with getting deep high-pressure wells to flow. In January 2019, a new well intervention plan will be finalised, after which the required personnel and equipment will be mobilised to commence the workover.

Β 

Deep Well A8

Β 

Background

Β 

Deep Well A8, was spudded on Nov. 23, 2018 with a planned Total depth of 5,300 meters. The well will target the same pre-salt carbonates that were successfully identified in the Deep Well A5. We also plan to evaluate deeper carbonate targets of Devonian to Mississippian ages.

Β 

Based on our interpretation of the 3D seismic data we expect to encounter the top of the salt layer at a depth of about 3,900 meters.

Β 

The well is being drilled in two parts. The first 4,100 meters, to the expected base of the salt layer, will be drilled by Sinopec, with a separate contract issued to drill the final stages of the well.

Β 

Current position

Β 

The 17 Β½ inch hole was drilled according to plan to 2,000m (Lower Cretaceous) with casing was set and cemented. The next drilling stage with diameter of 12 ΒΌ inches has begun and reached a depth of 2,127 meters without incident. We expect to reach 4,100 meters in April 2019 with completion, and an initial well test in Q3 2019.

Β 

Shallow Wells - MJF structure

Β 

Production levels

Β 

Total oil production in December 2018 from the 5 wells operational in the MJF structure and the 4 wells in the South Elemes structure was 49,255 barrels, (average of 1,589 bopd), with the domestic price at which the oil was sold rising to some $21-22 per barrel.

Β 

Completed workovers

Β 

The remedial work at Well 146 has been completed with the well being re-perforated pending testing. If successful the Company would have 6 wells producing on the MJF structure.

Β 

MJF Licence upgrade

Β 

A recent change in the Kazakh regulations has reduced the period during which licence holders generally can appraise individual structures from 6 years to 5 years. In return there is no longer the requirement to make social contributions during the reduced 5-year appraisal period. This change is expected to result in material savings to the Company over the lifetime of the licence.

Β 

The entire BNG licence has now been converted to a 5-year appraisal period and the submission to move the MJF structure to a full production basis has been filed with the relevant Kazakh authorities. We continue to expect an early approval after which we would be able to sell the majority of the oil produced from the MJF structure by reference to world rather than domestic prices.

Β 

Following receipt of the full production licence for the MJF structure we plan to embark on an in-fill drilling campaign for up to 10 new shallow wells, which we expect would increase the productive capabilities of the MJF structure from its current approximately 2,000 bopd to an enlarged approximately 4,000 bopd.

Β 

Β 

Β 

Ends

Β 

Caspian Sunrise PLC

Β 

Clive Carver

Executive Chairman

+7 727 375 0202

Β 

Β 

WH Ireland, Nominated Adviser & Broker

Β 

James Joyce

Jessica Cave

James Sinclair-Ford

Β 

+44 (0) 207 220 1666

Yellow Jersey PR

Tim Thompson

Henry Wilkinson

Β 

+44 (0) 203 735 8825

Β 

Qualified Person

Β 

Mr. Nurlybek Ospanov, Caspian Sunrise PLC's Chief Geologist / Technical Director who is a member of the Society of Petroleum Engineers ("SPE"), has reviewed and approved the technical disclosures in this announcement.

Β 

This announcement has been posted to:

www.caspiansunrise.com/investors

Β 

The information contained within this announcement is deemed by the Company to constitute inside information under the Market Abuse Regulation (EU) No. 596/2014.

Β 

Β 

Β 

Β 

Β 

Β 

Β 

Β 

Β 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
Β 
END
Β 
Β 
UPDUNVBRKBAAAAR
Date   Source Headline
28th Jan 20118:58 amRNSOperations Update
27th Jan 20117:00 amRNSOperational Update
13th Jan 20117:00 amRNSGrant of Options and Directors' Shareholdings
12th Jan 20117:00 amRNSOperational and Business Update
10th Jan 201111:59 amRNSNW Konys Pilot Production Consent Update
7th Jan 20118:50 amRNSYelemes 135 Well Spud
13th Dec 20101:03 pmRNSNK 20 Well Spud
1st Dec 20107:00 amRNSOperational and Business Update
15th Nov 20107:00 amRNSOperational Update
8th Nov 20107:00 amRNSChange of Registered Address & Company Secretary
12th Oct 201010:17 amRNSSale of Ravninnoe Oil LLP Interest
16th Sep 20107:00 amRNSBNG Operational Update
8th Sep 20107:00 amRNSNotice of Results
10th Aug 20109:00 amRNSOperational Update
3rd Aug 20107:00 amRNSGalaz update
14th Jul 20107:00 amRNSRavninnoe and BNG Operations update
7th Jul 20107:00 amRNSHolding(s) in Company
2nd Jul 20102:36 pmRNSDirector/PDMR Shareholding
28th Jun 20107:00 amRNSChange of Registered Address
24th Jun 20105:23 pmRNSGrant of Options
18th Jun 20104:37 pmRNSDirectorate Changes and Result of the AGM
18th Jun 20107:00 amRNSReserves Upgrade and Operations Update
17th Jun 20108:35 amRNSLaunch of new website
1st Jun 20107:00 amRNSOperational Update
26th May 20107:22 amRNSDirector/PDMR Shareholding
24th May 20107:00 amRNSFinal Results
10th May 20107:00 amRNSOperational Update
29th Apr 20107:00 amRNSSale of Galaz Interest
16th Apr 201011:00 amRNSDrilling Update
7th Apr 201011:13 amRNSIssue of Equity
7th Apr 20108:08 amRNSOperational Update
1st Apr 20101:52 pmRNSExercise of warrants/Total Voting Rights
31st Mar 201011:11 amRNSOperational update and total voting rights
26th Feb 20107:00 amRNSDirector/PDMR Shareholding
19th Feb 20107:00 amRNSDirector/PDMR Shareholding
18th Feb 20107:00 amRNSGalaz Discovery
16th Feb 20107:00 amRNSGrant of Options
11th Feb 20105:38 pmRNSDirector/PDMR Shareholding
11th Feb 20107:00 amRNSSale of Galaz Interest
8th Feb 20109:40 amRNSIssue Of Equity
3rd Feb 201010:38 amRNSCorperate & Opertaional Update
14th Jan 201012:00 pmRNSRavninnoe Update
22nd Dec 200910:32 amRNSCompletion of Part Disposal
9th Dec 20097:00 amRNSManagement Changes
7th Dec 20093:38 pmRNSHolding(s) in Company
2nd Dec 20093:19 pmRNSHolding(s) in Company
2nd Dec 20093:12 pmRNSIssue of Equity
1st Dec 20099:11 amRNSGalaz Update
23rd Nov 200910:00 amRNSIssue of Equity
17th Nov 200911:09 amRNSResult of General Meeting

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.