GreenRoc Accelerates their World Class Project to Production as Early as 2028. Watch the full video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAtalaya Mining Regulatory News (ATYM)

Share Price Information for Atalaya Mining (ATYM)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 417.00
Bid: 415.50
Ask: 417.50
Change: -7.00 (-1.65%)
Spread: 2.00 (0.481%)
Open: 421.00
High: 425.00
Low: 411.00
Prev. Close: 424.00
ATYM Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Refined permit roadmap for Rio Tinto mine start-up

17 Dec 2009 07:00

RNS Number : 2682E
EMED Mining Public Limited
17 December 2009
 



AIMEMED 17 December 2009

 

FORMAL CONFIRMATION OF REFINED PERMIT ROADMAP FOR RIO TINTO MINE START- UP

EMED Mining Public Limited ("EMED Mining" or "the Company"), the AIM quoted mining exploration and development companyis pleased to advise that the Junta de (or "Government of") Andalucia has formally confirmed the permitting process, or "roadmap" to facilitate the start-up of the Rio Tinto Mine ("PRT"). 

The permitting roadmap is broadly in line with the summary provided in the Company's report of 24 November 2009 and accommodates recently-introduced regulatory changes. It deals with the specifics of this particular project, sets out additional information needed to complete permitting and confirms the general process for review and consultation with the relevant authorities and with the public. 

On the basis of this roadmap the Company is targeting the following timetable:

Q1-2010 to Q2-2010: 
submission of detailed reports and responses to regulatory queries and requests, in support of the Company's applications;
Q2-2010 to Q4-2010: 
public information and consultation;
further regulatory reviews in Andalucia and in Madrid; and
administrative approval of mineral rights and permits to allow start-up activities;
Q3-2010: shareholder approval;
Q4-2010: commencement of start-up activities; and 
2011: production, exact timing dependant on permit timing and any conditions attached

 

EMED Mining Managing Director, Mr Harry Anagnostaras-Adams said,

"The formal response of the regulatory authorities to the applications submitted by the Company is constructive and duly careful. We have been invited to proceed and will now build momentum by diligently working through the information and process requirements set out by the Junta de Andalucia. We look forward to keeping shareholders informed of developments throughout 2010."

Enquiries

EMED Mining

Fox-Davies Capital

RFC Corporate Finance

Bishopsgate Communications

Harry Anagnostaras-Adams

Daniel Fox-Davies

Stuart Laing

Michael Kinirons

+357 9945 7843

+44 (0)207 936 5230

+618 9480 2500

+44 (0)207 562 3350

www.emed-mining.com 

www.emed.tv

 

Notes to Editors: About EMED Mining Public Limited

EMED Mining was admitted to trading on AIM in May 2005. The Company is committed to responsible development of metal production in Europe, with an initial focus on copper and gold. 

The Group's region of interest are the tectonic belts spanning across Europe and over to the Middle East. The strategy is to evaluate exploration and development opportunities in several jurisdictions throughout this quality mineral belt and to promote sustainable development practices through the implementation of European Union and other international standards. The Company strictly implements its Environmental & Community Policies which includes:

Integrating environmental management into its business, planning and reporting processes;

Promoting a strong environmental ethic throughout the Company and the community;

Complying with, as a minimum, all applicable local and European Union laws and regulations; and

Communicating with community stakeholders in a responsible and transparent manner.

EMED Mining has now established a strong position in the following selected zones:

The copper-mining districts of Cyprus and Spain which are probably among the best known in the world for their base metal endowment. The Company's first priority is to start-up production in Spain and commence generating profits as from 2011. 

Exploration areas in Slovakia are centred on a cluster of volcanic centres. Low-detection geochemical methods are being applied to these areas for the first time together with open-pit bulk mining concepts. The principal targeted mineralisation style is low-grade, bulk-mineable porphyry gold. The Company has announced a significant gold discovery at Biely Vrch and, with its mining consultants AMC Consultants (UK) Ltd, has completed a positive scoping study on its potential development.

Exploration in Turkey and Saudi Arabia via 29%-owned KEFI Minerals Plc. KEFI Minerals owns carefully selected licence areas in Turkey, as well as an extensive proprietary database of regional and specific exploration data providing a pipeline of further projects to evaluate. It is the operator of joint ventures in Turkey with Centerra Gold Inc of Canada and in the Kingdom of Saudi Arabia with local construction and investment group ARTAR. See www.kefi-minerals.com 

Further background as regards PRT: the Company has progressed the Rio Tinto Mine project as follows:

Completed geological investigations and verified mineral resources and ore reserves in compliance with the JORC Code;

Completed base case plans for operating a 14-year mine plan to extract ore reserves and to invest in drilling and other activities with a view to expanding and improving the project;

Acquired 100% of the project (the mine, its associated land and the associated mineral rights along with the plant and its associated land) from vendor company Mantesur Andavalor via (now) wholly-owned subsidiary EMED Tartessus SL;

Settled with the vendor company's principal creditor MRI Group which is now a shareholder of EMED Mining and has been appointed sales and marketing agent for the project;

Terminated all involvement in the project by previous controllers of the vendor company and commenced legal proceedings for their non-performance and enjoined the Company in their prosecution for criminal offences. A similar stance has been taken by MRI Group which is supporting EMED Mining's plans. 

Established support for the Company's plans from the communities and the Government;

Determined approach with the various authorities to assimilate regulatory changes and keep to timetable. Received clearance from the regulatory authorities to submit the full set of detailed reports and applications for permission to start-up;

For further information on the Company's activities, visit www.emed-mining.com or www.emed.tv

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCGUGMWPUPBPPQ
Date   Source Headline
25th Jan 20109:12 amRNSResult of EGM
14th Jan 20107:00 amRNSUpdate of site activities at Proyecto Rio Tinto
6th Jan 20103:45 pmRNSEGM Circular
24th Dec 20099:07 amRNSIssue of Share Options
23rd Dec 20099:09 amRNSResult of EGM
17th Dec 20097:00 amRNSRefined permit roadmap for Rio Tinto mine start-up
4th Dec 20093:33 pmRNS?3.27 million placing
1st Dec 200912:11 pmRNSManaging Director's Presentation - Mines and Money
30th Nov 20097:00 amRNSProyecto Rio Tinto Update
27th Nov 200910:38 amRNSIssue of Shares
24th Nov 20097:00 amRNSRio Tinto Mine - permit processes move forward
26th Oct 20097:00 amRNSQuarterly Report
21st Oct 20097:00 amRNSUpdate on gold exploration in Slovakia
12th Oct 20097:00 amRNSBiely Vrch Gold Mine - positive scoping study
30th Sep 20097:00 amRNSProyecto Rio Tinto Update
24th Sep 20097:00 amRNSInterim Results
12th Aug 20098:45 amRNSResult of EGM
30th Jul 20097:00 amRNSQuarterly Report
27th Jul 20097:00 amRNS?2.9 million Placing
1st Jul 20099:30 amRNSProyecto Rio Tinto - Copper Project Update
23rd Jun 20099:00 amRNSManaging Directors AGM Presentation
19th Jun 20099:00 amRNSProyecto Rio Tinto Laboratory Update
18th Jun 20094:35 pmRNSManaging Director Presentation
11th Jun 200910:30 amRNSFinance Facility Update
9th Jun 20099:46 amRNSConvertible Loan Financing Update
5th Jun 20094:16 pmRNSIssue of share options
1st Jun 200910:30 amRNSChairman's AGM Statement and Result of AGM
29th May 20097:00 amRNSFinance Facility Update
26th May 20097:00 amRNSUpdate on Gold Exploration in Slovakia
15th May 20099:30 amRNSIssue of Shares
11th May 20097:00 amRNSFinal Results
1st May 20099:07 amRNSIssue of Shares
7th Apr 20097:00 amRNSQuarterly Report
2nd Apr 20097:00 amRNSNotice of AGM
1st Apr 20097:00 amRNSDrawdown of Tranche A of Convertible Loan
23rd Mar 20098:32 amRNSResult of EGM
20th Mar 20093:15 pmRNSIssue of Shares
5th Mar 20097:00 amRNSConvertible Secured Loan Facility
24th Feb 20092:41 pmRNSIssue of Shares
23rd Feb 20097:00 amRNSSlovakia drilling update
12th Feb 20099:22 amRNSBridging Finance Facility
11th Feb 200910:41 amRNSIssue of Shares
2nd Feb 20097:00 amRNSQuarterly Report
21st Jan 200910:56 amRNSTermination of GMP Securities Europe as Co-Broker
14th Jan 200912:37 pmRNSResignation of Director
1st Dec 20087:00 amRNSUPDATE ON GOLD EXPLORATION IN SLOVAKIA
25th Nov 20087:00 amRNSExtension of Mine Life Plan
14th Nov 20087:00 amRNSAppointment of Lead-arranger for Financing
29th Oct 20087:01 amRNSQuarterly Report
29th Oct 20087:00 amRNSAppointment of Director

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.