Permitting Update

23 May 2013 07:00

RNS Number : 3811F
EMED Mining Public Limited
23 May 2013
 



 

AIM: EMED

TSX: EMD 23 May 2013

EMED Mining Public Limited

("EMED Mining" or the "Company")

Permitting Progress Update

for Commencement of Site Works at Rio Tinto Copper Project

Highlights

·; Production commissioning from the first mine remains scheduled to start mid-2014, and the ramp up of its production remains scheduled for the following 18 months;

·; The Environmental Plan ("AAU") to have the same conditions with regards to the tailings management facility ("TMF") as set last month by the Department of Industry for Administrative Standing ("AS");

·; The Company has completed the design work to satisfy these TMF conditions, after reviews with the regulators and CEDEX, the government's independent expert.

 

EMED Mining, the Europe-based minerals development and exploration company, reports further progress towards the commencement of permitted preliminary site works in Q3-2013, commissioning production at the first planned mine in mid-2014 and ramping up its production over the subsequent 18 months. Of particular note from a regulatory viewpoint is the satisfactory settlement of conditions which determine refinements to the TMF, so that the AAU and AS can now be finalised as precursors to the major site works.

 

Background

The two principal regulatory authorities, the Andalucian Government's Departments of Industry and Environment have both now formally written to confirm their requirements for finalising AS and AAU respectively; essentially, that the two sets of documents reflect the conditions for AS as summarised in the Company's announcement dated 15 April 2013. As previously reported, these conditions were set by the Department of Industry to refine the TMF to reflect the following design parameters:

·; restricting the existing dam wall to the previously permitted height;

·; the future transition to high density tailings to reduce water on the tailings deposit;

·; the progressive sealing of the surface of the tailings deposit during operations; and

·; ensuring sufficient holding capacity to support initial base case production plans.

All these refinements have been satisfactorily dealt with and settled by the Company and its advisers for civil engineering, tailings handling, hydrology and restoration, after discussion with the regulators and the Government's independent technical review agency CEDEX. This followed the drilling and other due diligence programs completed in March 2013, having been implemented after the Company's acquisition on 28 August 2012 of the two thirds of the TMF previously owned by third parties.

The project timetable has been refined to preserve the plan to start commissioning production in mid-2014. The formalisation of the AAU and AS are now on a revised path for completion around the end of Q3-2013, having taken into account the TMF conditions set last month. Some site housekeeping along with starting personnel training is scheduled for Q3-2013.

 

Harry Anagnostaras-Adams, Managing Director and CEO of EMED Mining, commented:

"We are immensely pleased that the Government has, through its actions, reiterated its policy commitment to the restart. The Andalucian Government's two regulatory authorities which issue the key permits required for construction have now confirmed the same conditions will be applied to the tailings management facility, to serve both their environmental and economic agendas in a complementary and integrated manner.

"Environmentally, the conditions make the plan safer, allow progressive environmental restoration during operations and avoid the premature disturbance of more land. Economically, the conditions preserve the base case for production and, in due course, will also serve expansion scenarios after the refinements have been optimised in the field during operations.

"The Company and the authorities will continue to adjust the timetable for permitting and start-up activities to ensure site activities escalate in a prudent sequential manner that is in line with regulatory permitting and to start commissioning production in mid-2014."

 

For more information please contact:

EMED Mining

Harry Anagnostaras-Adams

+357 9945 7843

RFC Ambrian

Stuart Laing

+61 8 9480 2500

Fox-Davies Capital

Susan Walker

+44 203 463 5022

Bishopsgate Communications

Nick Rome

+44 207 562 3350

Proconsul Capital

Andreas Curkovic

+1 416 577 9927

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCKLLFLXEFBBBL
Date   Source Headline
19th Nov 20207:00 amRNSQ3 2020 Financial Results
28th Oct 20207:00 amRNSApproval of feasibility study using E-LIX System
21st Oct 20207:00 amRNSAcquires Masa Valverde Polymetallic VMS Project
15th Oct 20207:00 amRNSThird Quarter 2020 Operations Update
24th Sep 20207:00 amRNSDevelopment of solar plant at Proyecto Riotinto
13th Aug 20207:00 amRNSQ2 and H1 2020 Interim Financial Statements
15th Jul 20207:00 amRNSQ2 2020 Operations Update
9th Jul 20207:00 amRNSGrant of share options and Director Shareholding
25th Jun 202012:32 pmRNSResult of AGM
25th Jun 20207:00 amRNSAGM Statement
1st Jun 20207:00 amRNSJunta de Andalucía validates Mining Permits
28th May 20207:00 amRNSNotice for the AGM in light of COVID-19
14th May 20207:00 amRNS1st Quarter Financial Results
7th May 20207:00 amRNSAAU granted by the Junta de Andalucía
15th Apr 20207:00 amRNSFirst Quarter 2020 Operations Update
7th Apr 20204:41 pmRNSSecond Price Monitoring Extn
7th Apr 20204:36 pmRNSPrice Monitoring Extension
7th Apr 20207:00 amRNSResults for the year ended 31 December 2019
6th Apr 20207:00 amRNSOperations Recommence at Proyecto Riotinto
30th Mar 20207:00 amRNSCompany Update - COVID 19 Developments
27th Mar 20207:00 amRNSPostponement of 2019 Full Year Results
17th Mar 20207:00 amRNSCompany Update - COVID 19
16th Mar 20204:40 pmRNSSecond Price Monitoring Extn
16th Mar 20204:36 pmRNSPrice Monitoring Extension
25th Feb 20207:04 amRNSDirector share purchase
30th Jan 20207:00 amRNSPositive Legal Update on Proyecto Riotinto
29th Jan 20207:00 amRNSUpdate on Proyecto Touro Permitting
16th Jan 20207:00 amRNSQ4 2019 Operations Update and 2020 Guidance
20th Dec 20199:02 amRNSHolding(s) in Company
21st Nov 20197:00 amRNSThird Quarter Financial Results
17th Oct 20197:00 amRNSThird Quarter 2019 Operations Update
19th Sep 201912:10 pmRNSHolding(s) in Company
19th Aug 20197:00 amRNSFull Mechanical Completion of 15Mtpa Expansion
15th Aug 20197:00 amRNSQ2 and H1 2019 Interim Financial Statements
11th Jul 20197:00 amRNSSecond Quarter 2019 Operations Update
10th Jul 20197:00 amRNSGranting of share options and PDMR Shareholding
5th Jul 20197:00 amRNSAppointment of Broker
27th Jun 20191:00 pmRNSResult of AGM
27th Jun 20197:00 amRNSAGM Statement
30th May 20197:00 amRNSNotice of AGM and 2018 Annual Report
30th May 20197:00 amRNSDirector/PDMR Shareholding
23rd May 20197:00 amRNS1st Quarter Financial Results
26th Apr 20191:30 pmRNSLegal Update
15th Apr 20197:00 amRNSFirst Quarter 2019 Operations Update
4th Apr 20197:00 amRNSResults for the year ended 31 December 2018
29th Mar 20197:00 amRNSLegal Update
15th Jan 20197:00 amRNSOperations Update and 2019 Guidance
22nd Nov 20187:00 amRNS3rd Quarter Results
1st Nov 201812:25 pmRNSResult of Appeal
12th Oct 20184:40 pmRNSSecond Price Monitoring Extn

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.