Operations Update and 2019 Guidance

15 Jan 2019 07:00

RNS Number : 0671N
Atalaya Mining PLC
15 January 2019
 

15 January 2019

Atalaya Mining Plc. ("Atalaya" or the "Company")

 Fourth Quarter 2018 Operations Update and 2019 Guidance

New records established at Proyecto Riotinto

 

Atalaya Mining Plc. (AIM:ATYM, TSX:AYM), the European mining and development company, is pleased to announce its operations update for the fourth quarter of 2018 and to provide guidance for 2019.

 

Notably, 2018 copper production at Proyecto Riotinto was 42,114 tonnes, up 13% from 37,164 tonnes produced in 2017 and in the upper range of the revised and increased guidance provided to the market on 22 November 2018. Copper production of 11,172 tonnes during Q4 2018 once again represents a new quarterly record.

 

Proyecto Riotinto

Q4

Q3

Full year

2018

2017

2018

2018

2017

2019 Guidance

Ore mined

(M tonnes)

2.8

2.5

2.8

10.8

9.3

11.4

Waste mined

(M tonnes)

4.3

5.7

3.2

17.7

19.8

17.8

Ore milled

(M tonnes)

2.6

2.3

2.5

9.8

8.8

11.4

Cu grade

(%)

0.48

0.44

0.50

0.49

0.49

0.47

Cu recovery

(%)

88.99

86.11

88.40

88.30

85.45

85 - 87

Cu production

(tonnes)

11,172

8,622

11,055

42,114

37,164

45,000 - 46,500

 

During 2018 the plant processed 9.8 Mt of ore with an average copper head grade of 0.49% and a recovery rate of 88.30%. In comparison to the rates for 2017, throughput and metallurgical recoveries have increased as a result of continuous improvements. Throughput has increased from 8.8 Mtpa in 2017 to 9.8 Mtpa in 2018 and recoveries have improved from 85.45% in 2017 to 88.30% in 2018. Copper head grade was consistent with estimates. On a quarterly basis, throughput, recoveries and copper grade have improved compared with Q4 2017 and Q3 2018.

 

Guidance for copper production in 2019 is estimated to be in the range of 45,000 to 46,500 tonnes. This year is anticipated to be a transitional one given the commissioning of the plant expansion in mid-2019, which will increase production within the range of 50,000 to 55,000 tonnes in 2020.

 

In terms of ore milled, 2.6 million tonnes were processed during the quarter, reporting a slight increase from previous quarters. Copper head grade was in line with plans. The increase in copper production during the quarter is mainly attributable to the increase in ore milled and improved metallurgical recoveries.

 

Mining operations are progressing according to plan and at similar levels to previous quarters. On a combined basis, ore, waste and marginal ore amounted to 2.5 million m3 in Q4 2018 versus 2.2 million m3 in Q3 2018. Additional mining equipment is available on site in anticipation of the increase in production scheduled for H2 2019.

 

On-site concentrate inventories at the end of the quarter were approximately 4,667 tonnes. All concentrate in stock at the beginning of the quarter and produced during the quarter was delivered to the port at Huelva.

 

Copper prices slightly decreased during the quarter compared with the previous quarter, with an average realised price per pound of copper payable, including the QPs closed in the period, of $2.85/lb compared with $2.89/lb in Q3 2018. The average copper spot price during the quarter was $2.80/lb. The realised price during the quarter, excluding QPs, was approximately $2.79/lb.

 

Cash operating costs for Q4 2018 are expected to be lower than the 2018 cost guidance ranges previously provided of $2.15-2.30/lb. Further details on costs will be provided with the 2018 Financial Statements to be reported in March 2019.

 

Exploration is progressing well at the Atalaya pit where massive sulphides and stockwork mineralisation are being targeted. The first 2,900 m of a 19,000 m drilling campaign have already been drilled with positive preliminary results received. Geological modelling of the upper and lower sections of the orebody is in progress. Drilling around the high-grade underground workings in Filon Sur is also ongoing with 9,900 m drilled out of a programme of 17,400 m.

 

Expansion to 15Mtpa at Proyecto Riotinto

 

The 15Mtpa expansion project is progressing according to schedule. Engineering and procurement are now completed with equipment delivered to site. All efforts are now concentrated around site construction activities. Overall progress completion at the end of December 2018 was over 80%. Earthworks are completed while civil engineering works are being finalised. Installation of mechanical equipment is completed in the flotation and concentrate handling areas. Structural steel works have been finalised in the flotation area with piping installation underway. Piping is completed in the concentrate handling area with electrical installation well advanced. The milling area is the critical path of the expansion project that is scheduled for mechanical completion at the end of Q2 2019.

 

Proyecto Touro

 

The environmental impact assessment process was completed during the quarter. Since submission of the latest studies and reports during the previous quarter, a number of queries have been addressed and cleared as part of the consultation and permitting process. The next step in the permitting process is the evaluation of the project from a regulatory perspective.

 

Legal Update

 

On 26 September 2018, Atalaya released the receipt of ruling from the Tribunal Superior de Justicia de la Junta de Andalucia ("Receipt of Ruling of EeA Claim"), where the Company announced that the Court had ruled in favour of certain claims made by an environmental group against the government of Andalucia and Atalaya. Whilst the ruling invalidates the granting of the AAU (Authorization Ambiental Unificada) on procedural grounds, it does not suspend it and the ruling is still subject to appeal and therefore not currently enforceable.

 

As noted in the Receipt of Ruling of EeA Claim, both the Junta de Andalucia and Atalaya as co-defendant decided to and have filed an appeal with the Supreme Court in Spain. The Company will update the market with the result of the appeal in due course.

 

Alberto Lavandeira, CEO commented:

"2018 was characterised by continuous copper production increases and we are delighted once again to announce new quarterly and annual copper production records in this update. This confirms the success of the ongoing improvement measures that have been implemented by our operating teams at Proyecto Riotinto in recent years, giving us full confidence that value creation for the Company will continue as we expand and modernise operations at Riotinto in 2019. This will be further aided by the development of new projects like Touro in the near future."

 

About Atalaya Mining Plc

Atalaya is an AIM and TSX-listed mining and development group. It produces copper concentrates and silver by-product at its wholly owned Proyecto Riotinto site in southwest Spain, which is also undergoing a brownfield expansion. In addition, the Group has a phased, earn-in agreement for up to 80% ownership of Proyecto Touro, a brownfield copper project in the northwest of Spain which is currently in the permitting stage. For further information, visit www.atalayamining.com

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) no 596/2014.

Contacts:

Newgate Communications

Elisabeth Cowell / Adam Lloyd / Tom Carnegie

+ 44 20 7680 6550

4C Communications

Carina Corbett

+44 20 3170 7973

Canaccord Genuity (NOMAD and Joint Broker)

Martin Davison / Henry Fitzgerald-O'Connor / James Asensio

+44 20 7523 8000

BMO Capital Markets (Joint Broker)

Jeffrey Couch / Tom Rider / Michael Rechsteiner

+44 20 7236 1010

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
TSTSFUFWLFUSEIF
Date   Source Headline
19th Mar 201211:00 amRNSIssue of Equity
16th Mar 201212:14 pmRNSIssue of Equity
12th Mar 201212:00 pmRNSPassing of Resolutions
5th Mar 20127:00 amRNSMandate of Goldman Sachs for $175 million finance
21st Feb 20121:59 pmRNSIssue of Equity
17th Feb 20122:04 pmRNSDespatch of Circular and Notice of EGM
9th Feb 201212:00 pmRNSAPPOINTMENT OF NON-EXECUTIVE DIRECTOR
6th Feb 20128:14 amRNSProposed Subscription, Support and Arrangements
16th Jan 20127:00 amRNSQuarterly Operational Update
9th Jan 201212:15 pmRNSCorrecting Announcement re RCF and RMB
3rd Jan 201210:00 amRNSNon-Exercise of Option over Regua Tungsten Deposit
30th Dec 20117:00 amRNSIssue of Share Options
28th Dec 20112:57 pmRNSConversion of Loans
5th Dec 20117:00 amRNSProject Rio Tinto Update
1st Dec 20117:00 amRNSAppointment Of Non Executive Director
23rd Nov 20117:00 amRNSProject Rio Tinto Update
10th Nov 20117:00 amRNSQuarterly Financial Results
7th Nov 20117:00 amRNSFinancing Proposals Received for Rio Tinto Mine
27th Oct 20117:00 amRNSProject Rio Tinto Update
12th Oct 20117:00 amRNSPolitical Support for Rio Tinto Mine
6th Oct 20117:00 amRNSQuarterly Operational Update
5th Oct 20117:00 amRNSQuarterly Investor Briefing
4th Oct 20117:00 amRNSStatement Regarding First Private Clients Ltd
23rd Sep 20117:00 amRNSIssue of Shares
6th Sep 20112:05 pmRNSPermitting Update
11th Aug 20117:00 amRNSHalf Yearly Report
18th Jul 20114:12 pmRNSQuarterly Operational Update
21st Jun 20117:00 amRNSDirectors Dealings
16th Jun 20115:29 pmRNSResult of AGM
16th Jun 20114:00 pmRNSAGM Statement
7th Jun 20117:00 amRNSUnderground Potential at Proyecto Rio Tinto
2nd Jun 20117:00 amRNSPermitting Update
24th May 20117:30 amRNSIssue of Shares
24th May 20117:00 amRNSPermitting Milestone Achieved
18th May 20117:00 amRNSNotice of AGM
10th May 20117:00 amRNSExercise of Options
4th May 20117:00 amRNSQuarterly Financial Report
28th Apr 20117:00 amRNSIssue of Shares
19th Apr 20117:00 amRNSGovernment Departments Respond to PRT Submissions
11th Apr 20117:00 amRNSQuarterly Operational Update
6th Apr 20117:00 amRNSIssue of Shares
31st Mar 20117:00 amRNSFinal Results
15th Mar 20117:00 amRNSFurther Progress at Proyecto Rio Tinto
24th Jan 20119:01 amRNSQuarterly Report
21st Jan 20112:15 pmRNSIssue of shares
19th Jan 20117:00 amRNSDrilling Programs For Rio Tinto Copper Mine
17th Jan 20117:00 amRNSFavourable Department of Culture & Heritage Ruling
14th Jan 20117:00 amRNSSignificant Shareholding and Exercise of Warrants
11th Jan 20112:38 pmRNSOver-Allotment Option
23rd Dec 20107:00 amRNSIssue of Share Options

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.