Development Update for New Liberty

31 Jan 2013 07:00

RNS Number : 7512W
Aureus Mining Inc.
31 January 2013
 



 

31January 2013

 

Aureus Mining Inc.

 

TSX : AUE

 

AIM : AUE

NEWS RELEASE

 

DEVELOPMENT UPDATE FOR NEW LIBERTY GOLD PROJECT - EARLY WORKS CONSTRUCTION HAS COMMENCED

 

Aureus Mining Inc. ("Aureus" or the "Company")is pleased to provide an update for the early works construction and development program at the New Liberty Gold Project in Liberia ("New Liberty" or the "Project"). The key workstreams are:

 

·; Marvoe Creek Diversion Channel, measuring 2.6km, has been cleared, with excavation and berm construction to commence in February 2013

·; 20km stretch of laterite road to New Liberty has been regraded

·; Detailed airborne topography survey has been completed

·; Additional housing, office space and maintenance areas currently under construction

 

Following the completion of the Project's feasibility study, in order to meet the schedule of first gold production in December 2014, the Company's operations team has been focused upon project optimisation studies and the commencement of early works to run alongside the optimisation of the Project's definitive feasibility study.

International Construction and Engineering ("ICE"), an international company with strong experience in Liberia and South Africa, has been appointed to perform the civil and earthworks component of the development of New Liberty.

The following work, critical to the successful development of New Liberty, is currently underway:

·; The Marvoe Creek Diversion Channel has been cleared, with excavation and berm construction to commence in February 2013. Pictures are included on the Company's website via the following links:

http://aureus-mining.com/wp-content/uploads/2013/01/Marvoe-Creek-1.jpg

http://aureus-mining.com/wp-content/uploads/2013/01/Marvoe-Creek-2.jpg

 

·; The 20km stretch of laterite road to New Liberty has been regraded. Installation of five 100-ton bridges will take place in February, ready for safe transportation of plant and equipment to New Liberty to meet construction schedule. Pictures are included on the Company's website via the following links:

http://aureus-mining.com/wp-content/uploads/2013/01/Road-Upgrade-1.jpg

http://aureus-mining.com/wp-content/uploads/2013/01/Road-Upgrade-2.jpg

 

·; Airborne Light Detection and Ranging (LiDAR) topography survey completed at both New Liberty and Weaju. Interpretation has given a detailed topographical model and high resolution imagery for the project sites:

http://aureus-mining.com/wp-content/uploads/2013/01/LiDAR-1.jpg

 

·; Additional housing, office space and maintenance areas currently under construction. Pictures are included on the Company's website via the following links:

http://aureus-mining.com/wp-content/uploads/2013/01/Construction-1.jpg

http://aureus-mining.com/wp-content/uploads/2013/01/Construction-2.jpg

 

·; ICE will perform the earthworks and civil construction for the New Liberty process plant site as well as the construction of the Tailings Storage Facility, which are scheduled to commence in the second half of 2013

 

Commenting on the development of New Liberty, David Reading, Chief Executive Officer of Aureus, stated:

 

"We are delighted to have ICE, who has extensive country specific experience, assisting us with the development of New Liberty. We are making excellent progress on the Marvoe Creek diversion and have completed the work on the 20km road to site that will allow the infrastructure to be safely transported. We are meeting our timetable and milestone targets to deliver Liberia's first commercial gold mine and have a first gold pour by the end of December 2014."

 

Commenting on the appointment of ICE, Chief Executive Officer of ICE, Joseph Crane, stated:

 

''It is an honour to be working with the Aureus team on this exciting project to build Liberia's first commercial gold mine. Our executive team has over 20 years of building and construction experience in Liberia, with the bulk of our workforce coming from the local community, Grand Cape Mount County and throughout Liberia. We are committed to building this project safely with a strong emphasis on protecting the environment and providing employment, management and business opportunities to the local population. ICE will provide an on-time delivery to Aureus and will meet the budget and technical requirements to produce the first gold pour by the end of December 2014.''

 

Contact Information

Aureus Mining Inc.

David Reading / Jeremy Cave

Tel: +44(0) 20 7010 7690

 

 

Buchanan

Bobby Morse / Gordon Poole

Tel: +44 (0) 20 7466 5000

RBC Capital Markets (Nominated Adviser and Joint Broker)

Martin Eales / Richard Hughes

Tel: +44(0) 20 7653 4000

GMP Securities Europe LLP (Joint Broker)

Richard Greenfield / Alexandra Carse

Tel: +44(0) 20 7647 2800

 

About Aureus Mining Inc.

The Company's assets include the New Liberty gold deposit in Liberia (the "New Liberty Gold Project" or the "Project"), which has an estimated proven and probable reserve of 910,000 ounces of gold grading 3.3 g/t and an estimated measured and indicated mineral resource of 1,143,000 ounces of gold grading 3.6 g/t and an estimated inferred mineral resource of 593,000 ounces of gold grading 3.2 g/t. A feasibility study has been completed on the Project and construction has commenced with initial earthworks. The Project is expected to have an eight and a half year mine life and annual production of 120,000 ounces for the first five years of production. The Company has financed the Project's equity funding requirement and is in advanced discussions with interested parties to fund the balance.

The New Liberty Gold Project is located within the Bea Mountain mining licence, which covers 457 km² and has a 25 year, renewable, mineral development agreement. The Bea Mountain mining license also hosts the proximal gold targets of Ndablama, Gondoja and Weaju, which are the focus of exploration programs during 2013. The contiguous Archaen Gold exploration licence, which covers 89 km², is also a focus of exploration for 2013, with Leopard Rock being the main target.

The Company also has gold exploration permits in Cameroon.

 

Forward-looking Statements 

This press release contains certain forward-looking information. All information, other than information regarding historical fact, that addresses activities, events or developments that Aureus Mining believes, expects or anticipates will or may occur in the future is forward-looking information. Forward-looking information contained in this press release includes, but may not be limited to, the future plans and objectives of Aureus Mining and their anticipated future growth, mineral resource estimates and the anticipated exploration and development activities of Aureus Mining. The foregoing and any other forward-looking information contained in this press release reflects the current expectations, assumptions or beliefs of Aureus Mining based on information currently available to Aureus Mining. With respect to the forward-looking information contained in this press release, Aureus Mining has made assumptions regarding, among other things: general business, economic and mining industry conditions; and it has also been assumed that no material adverse change in the price of precious and/or base metals occurs, no unusual geological or technical problems occur and no significant events occur outside of the normal course of Aureus Mining's respective business.

Such forward-looking information is subject to a number of risks and uncertainties that may cause actual results or events to differ materially from current expectations, including: risks normally incidental to exploration and development of mineral properties; uncertainties in the interpretation of results from drilling and test work; the possibility that future exploration, development or mining results will not be consistent with expectations; uncertainty of mineral resources estimates; adverse changes in precious and/or base metal prices; and future unforeseen liabilities and other factors including, but not limited to, those listed under "Risk Factors" in the Preliminary Prospectus of Aureus Mining Inc. dated April 20, 2011, a copy of which is available on SEDAR at www.sedar.com, and in the Aureus Mining Admission Document, a copy of which is available at www.aureus-mining.com.

Any mineral resource figures referred to in this press release are estimates and no assurances can be given that the indicated levels of minerals will be produced. Such estimates are expressions of judgment based on knowledge, mining experience, analysis of drilling results and industry practices. Valid estimates made at a given time may significantly change when new information becomes available. While Aureus Mining believes that the mineral resource estimates in respect of their respective properties are well established, by their nature mineral resource estimates are imprecise and depend, to a certain extent, upon statistical inferences which may ultimately prove unreliable. If such mineral resource estimates are inaccurate or are reduced in the future, this could have a material adverse impact on Aureus Mining, as applicable. Due to the uncertainty that may be attached to inferred mineral resources, it cannot be assumed that all or any part of an inferred mineral resource will be upgraded to an indicated or measured mineral resource as a result of continued exploration.

Forward-looking information speaks only as of the date on which it is made and, except as may be required by applicable law, Aureus Mining disclaims any obligation to update or modify such forward-looking information, either as a result of new information, future events or for any other reason.

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCNKKDKDBKBNDN
Date   Source Headline
10th Oct 20137:00 amRNSEXPECTED CLOSING OF US$16 MILLION OFFERING
3rd Oct 20137:00 amRNSUNDERWRITTEN FUND RAISE OF US$16.0 M
2nd Oct 20135:04 pmRNSAUREUS ANNOUNCES OFFERING TO RAISE APPROX US$15M
27th Sep 20139:00 amRNSBLOCK LISTING SIX MONTHLY RETURN
24th Sep 20137:00 amRNSRestated and Amended Mineral Development Agreement
23rd Sep 20137:00 amRNSECIC approves Project Debt Facility
13th Sep 201310:02 amRNSGrant of Stock Options
12th Sep 20137:00 amRNSAureus Mining Secures Debt Financing
6th Aug 20137:00 amRNSQ2 Financial Results and Operational Update
11th Jul 20137:00 amRNSNDABLAMA DELIVERS FURTHER HIGH GRADE GOLD
4th Jul 20137:00 amRNSTECHNICAL REPORT FILED FOR THE NEW LIBERTY PROJECT
1st Jul 20137:00 amRNSTotal Voting Rights
11th Jun 20133:00 pmRNSAnnual Meeting Results
11th Jun 20137:00 amRNSWEAJU DELIVERS FURTHER HIGH GRADE INTERCEPTS
22nd May 201312:47 pmRNSTR-1 Notification
20th May 20133:48 pmRNSNOTIFICATION OF MAJOR INTEREST IN SHARES
20th May 20137:00 amRNSNEW LIBERTY CONFIRMS STRONG FINANCIAL RETURNS
14th May 20137:00 amRNSNotice of Annual Meeting of Shareholders
9th May 20137:00 amRNSPublication of Q1 2013 Results
7th May 20137:00 amRNSBALL MILL ORDER FOR THE NEW LIBERTY GOLD PROJECT
26th Apr 20132:59 pmRNSTR-1 Notification
3rd Apr 20137:00 amRNSRelocation & Community Development Plans Approved
2nd Apr 20135:22 pmRNSTR-1: Notification of Major Interest in Shares
27th Mar 201310:00 amRNSBLOCK LISTING SIX MONTHLY RETURN
20th Mar 20137:00 amRNSFinancial Results For The Year Ended 31 December
20th Mar 20137:00 amRNSFINANCING FOR THE NEW LIBERTY GOLD PROJECT
18th Mar 20137:00 amRNSNotice of Preliminary Results
12th Mar 20137:00 amRNSHigh Grade Intercepts at Weaju Gold Target
1st Mar 201310:06 amRNSTotal Voting Rights
31st Jan 201310:00 amRNSTotal Voting Rights
31st Jan 20137:00 amRNSDevelopment Update for New Liberty
28th Jan 20137:00 amRNSGold Recovery at New Liberty Confirmed
22nd Nov 201211:39 amRNSNotification of major interest
22nd Nov 201211:38 amRNSNotification of major interest
19th Nov 20127:00 amRNSOperational Update
16th Nov 20122:29 pmRNSClosing Announcement
16th Nov 20127:00 amRNSExpected closure of offering
15th Nov 20127:00 amRNSResults for the Quarter ended 30 September 2012
5th Nov 20127:00 amRNSUnderwriting Agreement
2nd Nov 20127:00 amRNSAureus announces offering to raise US$80m
31st Oct 20127:00 amRNSTotal Voting Rights
22nd Oct 20122:00 pmRNSTECHNICAL REPORT FILED FOR THE NEW LIBERTY PROJECT
15th Oct 20127:00 amRNSENVIRONMENTAL PERMIT GRANTED
1st Oct 20127:00 amRNSNEW LIBERTY FEASIBILITY STUDY
28th Sep 20123:17 pmRNSBLOCK LISTING SIX MONTHLY RETURN
10th Sep 20127:00 amRNSExploration Drilling/Trenching Results
22nd Aug 201210:33 amRNSIssue of new common shares
15th Aug 20123:44 pmRNSGrant of Stock Options
13th Aug 20127:00 amRNSQ2 financial results for period ended 30 June 2012
2nd Aug 20127:00 amRNSAppointment of General Manager

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.