Roundtable Discussion; The Future of Mineral Sands. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAntofagasta Regulatory News (ANTO)

Share Price Information for Antofagasta (ANTO)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 2,168.00
Bid: 2,179.00
Ask: 2,181.00
Change: -42.00 (-1.90%)
Spread: 2.00 (0.092%)
Open: 2,207.00
High: 2,226.00
Low: 2,166.00
Prev. Close: 2,210.00
ANTO Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Q3 2014 PRODUCTION REPORT

29 Oct 2014 07:00

RNS Number : 5238V
Antofagasta PLC
29 October 2014
 



NEWS RELEASE, 29 OCTOBER, 2014

Q3 2014 PRODUCTION REPORT

FULL YEAR GUIDANCE UNCHANGED

HIGHLIGHTS

PRODUCTION

· Copper production in Q3 2014 was 169,200 tonnes, a 5.0% decrease compared with the previous quarter, principally due to lower throughput at Los Pelambres and Centinela concentrates

· Copper production in the first nine months of the year was 3.9% lower than in the same period last year primarily due to lower grades

· Gold production was 64,700 ounces in Q3 2014, a 3.4% decrease on Q2 2014 due to lower throughput at Centinela concentrates as a result of planned maintenance, which was partly offset by higher grades

· Molybdenum production at Los Pelambres was 2,300 tonnes in Q3 2014, compared with 1,600 tonnes in the previous quarter, principally due to higher grades

 

CASH COSTS

· Cash costs before by-product credits in Q3 2014 were $1.85/lb, a 2.6% decrease compared with Q2 2014. This decrease mainly related to lower energy costs at Los Pelambres and the one-off signing bonus between Centinela concentrates and its labour unions that was paid in Q2 2014

· Cash costs before by-product credits for the first nine months of the year at $1.86/lb were 3.9% higher than in the corresponding period last year due to the one-off signing bonuses paid this year at Los Pelambres and Centinela concentrates and the completion of mining activities at the lower cash cost Mirador pit by Centinela cathodes in 2013

· Net cash costs for the first nine months of 2014 were $1.44/lb, 8.3% higher than the same period last year primarily due to higher cash costs before by-product credits and lower realised gold prices

GUIDANCE

· The Group remains on track to meet its full year guidance of 700,000 tonnes of copper, 270,000 ounces of gold and 7,500 tonnes of molybdenum and net cash costs of $1.45/lb

OTHER

· As part of the programme to reduce power costs, the El Arrayán wind farm was commissioned in July and now provides Los Pelambres with some 20% of its power needs. Following this, in September 2014, Los Pelambres signed Power Purchase Agreements with two solar power providers for a total of 50MW of power

 

 

 

GROUP PRODUCTION AND CASH COSTS

Q3

Q2

 

YTD

 

 

 

2014

2014

%

2014

2013

%

Copper production

kt

169.2

178.8

(5.0)

517.3

538.3

(3.9)

Gold production

koz

64.7

67.0

(3.4)

188.5

230.6

(18.3)

Molybdenum production

kt

2.3

1.6

43.8

5.5

6.7

(17.9)

Cash costs before by-product credits

$/lb

1.85

1.90

(2.6)

1.86

1.79

3.9

Net cash costs

$/lb

1.42

1.45

(2.1)

1.44

1.33

8.3

MINING OPERATIONS

Los Pelambres

Los Pelambres produced 94,900 tonnes of copper in Q3 2014 compared with 100,900 tonnes in the previous quarter. This decrease was mainly due to lower throughput as result of the suspension of mining activities following the fatal accident in September and harder ore, which was partially offset by increased grades. The 3.9% decrease in production to 291,500 tonnes in the first nine months of 2014 compared with the same period last year was due to lower grades during the first half of the year.

Molybdenum production increased by 43.8% to 2,300 tonnes in Q3 2014, from 1,600 tonnes in the previous quarter, primarily due to significantly higher grades. Production at 5,500 tonnes was 17.9% lower in the first nine months of 2014 compared with the same period last year due primarily to lower grades.

Cash costs before by-product credits in Q3 2014 were $1.51/lb compared with $1.59/lb in the previous quarter. This was principally due to lower energy prices complemented by the commissioning of the El Arrayán wind farm in July, which now provides Los Pelambres with some 20% of its power needs. Following this, in September, Los Pelambres signed Power Purchase Agreements with two solar power providers for a total of 50MW of power. Net cash costs were $0.05/lb lower at $1.06/lb in Q3 2014 compared with the previous quarter primarily reflecting increased production of molybdenum, which was partly offset by lower realised molybdenum prices.

Net cash costs for the first nine months of 2014 were $1.15/lb, compared with $1.18/lb in the first nine months of 2013 primarily as gold production increased by 23.5%.

 

 

LOS PELAMBRES

 

Q3

Q2

 

YTD

 

 

 

2014

2014

%

2014

2013

%

Daily ore throughput

kt

175.7

191.0

(8.0)

176.5

175.8

0.4

Copper grade

%

0.69

0.67

3.0

0.69

0.73

(5.5)

Copper recovery

%

88.6

89.7

(1.2)

90.0

89.9

0.1

Copper production

kt

94.9

100.9

(5.9)

291.5

303.4

(3.9)

Copper sales

kt

89.9

94.2

(4.6)

279.9

305.7

(8.4)

Molybdenum grade

%

0.018

0.011

63.6

0.014

0.015

(6.7)

Molybdenum recovery

%

81.1

81.5

(0.5)

82.9

81.5

1.7

Molybdenum production

kt

2.3

1.6

43.8

5.5

6.7

(17.9)

Molybdenum sales

kt

2.5

1.7

47.1

5.8

6.2

(6.5)

Gold production

koz

17.0

18.1

(6.1)

50.5

40.9

23.5

Gold sales

koz

15.4

15.8

(2.5)

46.8

40.9

14.4

Cash costs before by-product credits*

$/lb

1.51

1.59

(5.0)

1.58

1.55

1.9

Net cash costs

$/lb

1.06

1.11

(4.5)

1.15

1.18

(2.5)

 

* Includes tolling charges of $0.22/lb in Q3 and Q2 2014, $0.21 in 2014 YTD and $0.17/lb in 2013 YTD

Centinela concentrates (previously Esperanza)

Centinela produced 41,400 tonnes of payable copper in concentrates in Q3 2014, compared with 43,100 tonnes in the previous quarter, primarily due to lower throughput after a semi-annual maintenance shutdown at the plant. The 5.6% decrease in production to 123,700 tonnes in the first nine months of 2014 compared to the same period in 2013 was principally due to lower throughput and grades.

Gold production was 47,700 ounces in Q3 2014, 1,200 ounces lower than in the prior quarter due to lower throughput at the processing plant. Gold production in the first nine months of the year was 27.2% lower than in the same period last year as a result of declining grades. 

Cash costs before by-product credits were $2.44/lb in Q3 2014 compared with $2.50/lb in the previous quarter. This reduction in costs is explained by the one-off bonus payments following labour negotiations paid in Q2 2014. Net cash costs at $1.76/lb in Q3 2014 were in line with the previous quarter.

Compared with the first nine months of 2013, cash costs before by-product credits were 3.0% higher, primarily due to the payment of the one-off bonus in May 2014 and higher tolling charges. Net cash costs for the first nine months of 2014 were $1.65/lb compared with $1.29/lb in the same period last year. This is primarily due to the decrease in the gold price and production compared to the same period last year.

 

CENTINELA CONCENTRATES

 

Q3

Q2

 

YTD

 

(PREVIOUSLY ESPERANZA)

 

2014

2014

%

2014

2013

%

Daily ore throughput

kt

84.6

88.4

(4.3)

85.1

87.3

(2.5)

Copper grade

%

0.65

0.62

4.8

0.64

0.65

(1.5)

Copper recovery

%

88.5

88.2

0.3

88.1

87.7

0.5

Copper production

kt

41.4

43.1

(3.9)

123.7

131.1

(5.6)

Copper sales

kt

38.4

46.8

(17.9)

124.2

125.2

(0.8)

Gold grade

%

0.27

0.26

3.8

0.27

0.32

(15.6)

Gold recovery

%

74.9

71.8

4.3

72.5

80.4

(9.8)

Gold production

koz

47.7

48.9

(2.5)

138.0

189.6

(27.2)

Gold sales

koz

41.2

52.3

(21.2)

135.1

176.7

(23.5)

Cash costs before by-product credits*

$/lb

2.44

2.50

(2.4)

2.38

2.31

3.0

Net cash costs

$/lb

1.76

1.75

0.6

1.65

1.29

27.9

 

* Includes tolling charges of $0.25/lb in Q3 2014, $0.24/lb in Q2 2014, $0.24/lb in 2014 YTD and $0.20/lb in 2013 YTD

 

Centinela cathodes (previously El Tesoro)

Centinela produced 22,000 tonnes of copper cathodes in Q3 2014 similar to the 22,300 tonnes produced in the previous quarter. Production in the first nine months of 2014 was 11.1% lower than in the same period last year. This decrease was mainly due to lower grades and recoveries following the completion of mining activities at the higher grade Mirador pit in Q4 2013, partially offset by higher throughput.

Cash costs decreased by 3.6% to $1.86/lb in Q3 2014 compared with the previous quarter primarily due to the weakening of peso and lower input costs. Cash costs in the first nine months of 2014 were $1.82/lb compared to $1.28/lb last year again primarily reflecting the lower cost of production from processing the higher grade Mirador ore last year.

 

CENTINELA CATHODES

 

Q3

Q2

 

YTD

 

(PREVIOUSLY EL TESORO)

 

2014

2014

%

2014

2013

%

Daily ore throughput

kt

23.1

25.2

(8.3)

24.7

19.4

27.3

Copper grade

%

1.34

1.20

11.7

1.27

1.63

(22.1)

Copper recovery

%

68.4

72.7

(5.9)

71.6

78.8

(9.1)

Copper production - heap leach

kt

19.6

19.7

(0.5)

60.5

70.2

(13.8)

Copper production - total *

kt

22.0

22.3

(1.3)

68.0

76.5

(11.1)

Copper sales

kt

21.4

22.0

(2.7)

66.5

74.8

(11.1)

Cash costs

$/lb

1.86

1.93

(3.6)

1.82

1.28

42.2

 

* Includes production from ROM material

Michilla

 

Copper production at Michilla was 10,900 tonnes during the third quarter, 12.1% lower than in the previous quarter largely as a result of slippage in the mine plan that delayed access to the higher grade areas of the Lince pit. The 24.9% increase in production to 34,100 tonnes in the first nine months of the year compared with the same period last year was due to higher grades and recoveries at the mine.

Cash costs increased slightly to $2.47/lb in Q3, compared with $2.28/lb in the previous quarter primarily due to lower production in the quarter. Cash costs for the first nine months of 2014 were $2.41/lb compared with $3.35/lb in the same period last year. This decrease was primarily due to lower stripping costs, a weaker peso and less processing of higher cost, third party ores.

MICHILLA

 

Q3

Q2

 

YTD

 

 

 

2014

2014

%

2014

2013

%

Daily ore throughput

kt

11.0

12.9

(14.7)

12.0

11.5

4.3

Copper grade

%

1.12

1.12

0.0

1.10

0.92

19.6

Copper recovery

%

80.5

79.2

1.6

79.9

77.3

3.4

Copper production - heap leach

kt

9.0

10.8

(16.7)

29.1

22.6

28.8

Copper production - total

kt

10.9

12.4

(12.1)

34.1

27.3

24.9

Copper sales

kt

11.0

11.9

(7.6)

33.2

26.3

26.2

Cash costs

$/lb

2.47

2.28

8.3

2.41

3.35

(28.1)

Antucoya

 

The construction of Antucoya remains on time and on budget with 94% total progress (including design, engineering, procurement and construction) and 87% construction progress as at 30 September 2014. During the quarter, several milestones were achieved including completion of pre-stripping and the inauguration of the truck shop.

Commodity prices and exchange rates

 

 

Q3

Q2

 

YTD

 

 

 

2014

2014

%

2014

2013

%

Copper

Market price

$/lb

3.17

3.08

2.9

3.15

3.35

(6.0)

Realised price

$/lb

3.02

3.28

(7.9)

3.06

3.26

(6.1)

Gold

Market price

$/oz

1,283

1,288

(0.4)

1,288

1,456

(11.5)

Realised price

$/oz

1,149

1,315

(12.6)

1,290

1,402

(8.0)

Molybdenum

Market price

$/lb

12.7

13.6

(6.6)

12.1

10.5

15.2

Realised price

$/lb

11.1

18.5

(40.0)

13.2

10.0

32.0

Exchange rates

Chilean peso

per $

577

554

4.2

561

488

15.0

 

The spot commodity prices for copper, gold and molybdenum as at 30 September 2014 were $3.06/lb, $1,212/oz and $10.6/lb respectively compared with $3.15/lb, $1,314/oz and $13.3/lb as at 30 June 2014.

The provisional pricing adjustments and hedging effects for the first nine months of the year for copper, gold and molybdenum were negative $108.7 million, negative $8.4 million and positive $6.0 million respectively.

Transport and water

Total volumes transported by the transport division were 1.9 million tonnes in Q3 2014, 3.5% higher than in the previous quarter, and 5.4 million tonnes in the first nine months of the year, 3.1% lower than in the same period last year.

The water division sold 12.2 million cubic metres in Q3 2014, 3.9% lower than in the previous quarter, and 37.8 million cubic metres in the first nine months of the year, 1.3% lower than in the same period last year.

Q3

Q2

 

YTD

 

 

 

2014

2014

%

2014

2013

%

Total tonnage transported

kt

1,853

1,790

3.5

5,372

5,542

(3.1)

Water volumes sold

mil m³

12.2

12.7

(3.9)

37.8

38.3

(1.3)

 

Tax changes in Chile

The Chilean tax reform bill (the "Bill") was enacted into law on 29 September 2014. The Bill is in line with the Group's expectations as it is unchanged from the draft commented on at the time of the Group's Half Yearly Financial Report published on 26 August 2014.

Under the Bill, companies can elect to pay corporate tax and withholding tax under two different systems, attributable or semi-integrated. This election must be made by the end of 2016 and the company must then stay under the chosen system for five years before it can make a new election. Each of the Group's companies in Chile will need to separately elect which system to adopt and this decision will depend on several factors, including the evaluation of the different financial implications and, where other shareholders have interests in the Group's companies, the views of these shareholders.

Under the attributable system, total corporation and withholding tax is unchanged at 35%, but the withholding tax element is payable when profits are earned regardless of whether dividends are distributed or not. If the Group's companies in Chile were in future to pay 100% of their earnings as dividends, there would be no impact on the total corporation and withholding tax paid by those companies, and at lower pay-out ratios the impact would be to bring forward tax payments rather than to increase the total tax paid over the life of the operation.

Alternatively, the semi-integrated system provides the same flexibility as the system previously in force, under which withholding tax is paid only when dividends are distributed. However under the semi-integrated system only 65% of the corporation tax paid can be used as a credit against the 35% withholding tax as opposed to the 100% credit under the previous system.

Corporation (first category) tax rates will increase from 20% in 2013 to 25% in 2017 under both systems, and further to 27% in 2018 under the semi-integrated system.

The Group is continuing to evaluate the impact of the two systems.

One consequence of the Bill is that the Group has to make a one-off increase to its deferred tax provision in the 31 December 2014 year-end results in order to reflect the new corporate tax rates. The impact of this on retained earnings will be in the range of $105 million to $150 million.

Safety

Sadly during the quarter, the Group experienced a fatal accident at Los Pelambres. Elena Ávila lost her life as a result of an accident involving the truck she was driving.

Subsequent to the close of the quarter, three employees of one of our contractors were killed in a motor vehicle accident at Centinela.

The Group is committed to safeguarding the safety of all of its employees and contractors. The Group is currently assisting the contractor and the relevant authorities to investigate the causes of these accidents and to put in place further preventative and control measures to safeguard all of our employees and contractors. Production was halted to carry out the requisite investigations and has since resumed.

The Group is devoted to strengthening the safety culture of all of our operations and ensuring that all contractors share our goals and ambitions. To this end, a new safety and occupational health model was introduced at the beginning of the year and is being rolled out across the Group with the aim of reducing risks, especially fatal risks.

Antofagasta management and staff express their condolences to all the families and friends of those involved in these accidents.

Los Pelambres - El Mauro tailings dam

Since the El Mauro tailings dam began operating in 2008, there have been a series of legal claims by some members of the Caimanes community who live in the area. These claims have been through various courts and stages of appeal, but Los Pelambres has always complied with all applicable laws, regulations and controls. 

At the time that the Half Yearly Financial Report was published, the Supreme Court of Chile was considering an appeal made by some members of the community in connection with a claim that the El Mauro tailings dam was affecting their alleged water rights and the environmental condition of the Pupío stream. This claim had been rejected by the Trial Court of Los Vilos in November 2012 and was affirmed by the Court of Appeals of La Serena in August 2013. 

On 21 October 2014, the Supreme Court, by split decision, admitted the appeal and ordered Los Pelambres to submit to the Trial Court of Los Vilos, within one month, an implementation plan for the works required to ensure that the operation of the dam does not affect the normal flow and quality of the waters of the Pupío stream. 

Los Pelambres believes that the requirements of this order have already been met as Los Pelambres has undertaken significant works to ensure that the flow of the Pupío stream is not altered and that the operation of the tailings dam does not affect the quantity or quality of these waters - something that has been confirmed by accredited independent assessors and other public services in Chile and confirmed by the very same Supreme Court in a parallel decision. Nevertheless, Los Pelambres will provide the Court with a plan for suitable additional works to address the requirements of the Supreme Court and ensure continued compliance with all applicable laws, regulations and controls. 

The company will continue to update the market should there be any material developments.

Interim management statement

 

This report represents the Interim Management Statement for the purposes of the UK Listing Authority's Disclosure and Transparency Rules. Other than as set out above, there have been no material events or transactions, or significant changes to the financial position and performance of the Group, since 30 June 2014.

 

 

 

Investors - London Media (Brunswick)

Andrew Lindsay alindsay@antofagasta.co.uk Carole Cable antofagasta@brunswickgroup.com

Paresh Bhanderi pbhanderi@antofagasta.co.uk Robin Wrench antofagasta@brunswickgroup.com

Telephone +44 20 7808 0988 Telephone +44 20 7404 5959

Investors - Santiago

Alejandro Rivera arivera@aminerals.cl

Telephone +56 2 2798 7000

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCMPBFTMBJTBLI
Date   Source Headline
30th Apr 20247:00 amRNSANTOFAGASTA PLC ANNOUNCES PRICING OF BOND
25th Apr 20247:00 amRNSFINAL DIVIDEND PAYABLE
17th Apr 20247:00 amRNSQ1 2024 PRODUCTION REPORT
3rd Apr 202411:00 amRNSNOTIFICATION OF TRANSACTIONS
28th Mar 20247:00 amRNS2023 REPORTING SUITE, 2024 AGM & CORPORATE UPDATE
19th Mar 20248:00 amRNSCENTINELA SECOND CONCENTRATOR FINANCING
20th Feb 20247:00 amRNSFULL-YEAR RESULTS FOR THE YEAR ENDED 31/12/2023
16th Feb 20247:00 amRNSUPDATED EMISSIONS TARGETS
15th Feb 20247:00 amRNS2023 FY RESULTS PRESENTATION & CONFERENCE DETAILS
30th Jan 20244:49 pmRNSAPPOINTMENT OF INDEPENDENT NON-EXECUTIVE DIRECTOR
17th Jan 20247:00 amRNSQ4 2023 PRODUCTION REPORT
2nd Jan 20247:00 amRNSNOTIFICATION OF TRANSACTION BY DIRECTOR / PDMR
20th Dec 20237:00 amRNSCENTINELA SECOND CONCENTRATOR PROJECT APPROVED
15th Dec 20232:24 pmRNSANTOFAGASTA ANNOUNCES INVESTMENT IN BUENAVENTURA
12th Dec 20237:00 amRNSDIRECTOR CHANGE AND CHANGES TO BOARD COMMITTEES
10th Nov 20237:00 amRNSPUBLICATION OF CLIMATE CHANGE REPORT
18th Oct 20237:00 amRNSQ3 2023 PRODUCTION REPORT
7th Sep 20237:00 amRNSINTERIM DIVIDEND PAYABLE
10th Aug 20237:00 amRNSHALF YEARLY FINANCIAL REPORT
3rd Aug 20237:00 amRNS2023 Half Year Results - Participation Details
31st Jul 20237:00 amRNSANTOFAGASTA RELEASES SOCIAL VALUE REPORT
20th Jul 20237:00 amRNSANTOFAGASTA RELEASES TAX REPORT
19th Jul 20237:00 amRNSQ2 2023 PRODUCTION REPORT
30th Jun 20237:00 amRNSReport on Payments to Govts
10th May 20236:37 pmRNSRESULTS OF 2023 ANNUAL GENERAL MEETING
10th May 20231:00 pmRNSCHAIRMAN’S COMMENTS AT THE 2023 AGM
2nd May 20237:00 amRNSFINAL DIVIDEND PAYABLE
19th Apr 20237:00 amRNSQ1 2023 PRODUCTION REPORT
18th Apr 20237:00 amRNSAPPOINTMENT OF INDEPENDENT NON-EXECUTIVE DIRECTOR
31st Mar 20238:38 amRNSPUBLICATION OF 2022 ANNUAL REPORT AND ACCOUNTS
30th Mar 20234:31 pmRNSNOTIFICATION OF TRANSACTIONS
14th Mar 20234:39 pmRNSCHANGES TO BOARD COMMITTEES
21st Feb 20237:00 amRNS2022 Full-year results announcement
14th Feb 20237:00 amRNS2022 Full Year Results - Participation Details
18th Jan 20237:00 amRNSQ4 2022 PRODUCTION REPORT
29th Dec 20228:34 amRNSLOS PELAMBRES ACCESS BLOCKED
15th Dec 20225:15 pmRNSANTOFAGASTA EXITS REKO DIQ PROJECT IN PAKISTAN
19th Oct 20227:00 amRNSQ3 2022 PRODUCTION REPORT
12th Oct 202210:15 amRNSNotice of Q3 2022 Production Report
4th Oct 20222:37 pmRNSLOS PELAMBRES DESALINATION PROJECT UPDATE
12th Sep 20227:00 amRNSPrecautionary Measure at Los Pelambres
9th Sep 20225:31 pmRNSInterim Dividend 2022 FX Rates
11th Aug 20227:00 amRNSHALF YEAR FINANCIAL REPORT FOR PERIOD TO 30.06.22
4th Aug 20227:00 amRNSNotice of Half Year Results 2022
20th Jul 20227:00 amRNSQ2 2022 PRODUCTION REPORT
11th Jul 20227:00 amRNSANTOFAGASTA RELEASES TAX REPORT
1st Jul 20227:00 amRNSREPORT ON PAYMENTS TO GOVERNMENTS
15th Jun 20227:00 amRNSLOS PELAMBRES CONCENTRATE PIPELINE INCIDENT UPDATE
14th Jun 20227:00 amRNSUPDATED MINERAL RESOURCES
7th Jun 202212:28 pmRNSLOS PELAMBRES - CONCENTRATE PIPELINE INCIDENT

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.