Financing and Operations Update

1 Dec 2014 11:16

RNS Number : 4670Y
African Minerals Ltd
01 December 2014
 



1 December 2014

African Minerals Limited

("African Minerals", "AML", or "the Company")

Financing and Operations Update

African Minerals Limited, the developer, operator and 75% owner of the Tonkolili Iron Ore Project (the "Project") in Sierra Leone, today provides a financing and operations update.

Summary

Operations to be put on care and maintenance until such time as $102m restricted cash is released and/or, AML secures additional short term funding.

Controlled shut down initiated at operations in Sierra Leone due to insufficient working capital, severely impacted by low iron ore prices, which has prevented implementation of cost reduction strategies.

The Company's ordinary shares will remain suspended while there remains a fundamental uncertainty in the financial position of the Company.

Q3 export sales of 4.4Mt (Q2 2014: 4.3Mt); average direct cash costs of $36/t (Q2 2014: $38/t) and all-in cash costs of $45/t (Q2 2014: $47/t).

Further to the announcement on 20 November 2014, the Company announces that the $102m of restricted cash has yet to be released due to continued disagreements between AML and Shandong Iron and Steel Group ("SISG"). AML continues to use its best efforts to obtain SISG's authorisation to release these funds, however there remains no certainty of this, or of its timing.

As previously announced AML commenced a process to sell down a partial interest in its stake in the Tonkolili mine. AML is talking to several groups who have expressed strong interest, and discussions are being progressed as quickly as possible, though there is no certainty a transaction will be forthcoming.

In the absence of sufficient working capital AML has commenced a temporary controlled shut down of its operations in Sierra Leone. Without a significant injection of working capital, AML is unable to initiate the cost reduction strategies which would return the operations to cash flow positive status even at recent low iron ore prices.

The receipt of funds from shipments in recent weeks, including from SISG, provides the operating companies with sufficient funds to meet critical payments necessary to maintain the security, safety, and, to the extent necessary, evacuation of staff and contractors in Sierra Leone, and to maintain salary payments in the short term. This plan allows for the continued safeguarding of the Company's assets and will allow for a rapid ramp up and resumption of operations when a financial solution is achieved.

With all available funds being used for the security and safety of personnel and assets during this temporary shutdown, the Company's subsidiaries have not been able to make in full the repayment under the PXF Facility due at the end of November. The Company is in discussions with its Lenders about this and future obligations under the PXF Facility, however these discussions are only likely to progress successfully once AML and SISG as shareholders of the Project have agreed a financial solution.

Alan Watling, Chief Executive Officer of African Minerals, said:

"Initiating a temporary shutdown of operations towards care and maintenance in Sierra Leone, while extremely regrettable, is a necessity given the Company's financial status and uncertainty over the timing of the release of the restricted funds. While the operating performance of the Project has been impressive during 2014, with Q3 exports of 4.4Mt at an average direct cash cost of $36/t, in spite of the wet season, the fall in iron ore prices and the operational challenges caused by the Ebola disease outbreak has meant the Project has continued to operate at a loss. While management is convinced Tonkolili remains a world class low operating cost asset, the absence of sufficient working capital has prevented the Company from implementing the cost cutting strategies required to return the Project back to a cash flow positive status even in the current depressed iron ore price environment.

Management is doing everything possible to procure the agreement of a funding solution between AML and SISG. The Company greatly appreciates the support shown by the Government of Sierra Leone, our local suppliers and communities, and all our contractors during what we hope is only a temporary suspension of operations."

Frank Timis, Executive Chairman of African Minerals, said:

"Following my visit to Sierra Leone last week I wish to thank the Government of Sierra Leone and all our local suppliers and communities in which we operate for their continued support and understanding of the situation. We are very grateful that the Government has pledged its assistance to help secure the safety and security of our people and assets in these difficult times. We have allocated all available funds to these critical activities and to keeping the operating assets in a condition that operations can be quickly restarted, which is of fundamental interest to all stakeholders. As part of this, local staff will continue to be employed on normal wages and will be allocated to care and maintenance activities."

Q3 Production and Exports Summary

Despite Q3 being the traditional heaviest part of the wet season, the Company's wet season strategies performed well. 5.2Mt of DSO was mined, along with 1.0Mt of other material, principally saprolitic hematite in readiness for Phase 2 expansion. 4.9Mt of this material was treated to produce 3.3Mt of product - 1.7Mt of lump, 1.3Mt of fines and 0.3Mt of A32, a notable decrease in A32 tonnes from the previous quarter which saw 0.9Mt of A32 being produced.

Total tonnage exported in Q3 was 4.4Mt, a 3% increase from the previous quarter. Dry tonnes shipped were 3.9Mt of DSO.

In Q3, 32% of production tonnage was delivered into the 6.5Mt SISG Discounted Offtake Agreement ("DOTA"), while a further 16% was SISG Equity ore.

Average direct cash costs in Q3 were $36/t, a reduction from $38/t in Q2. All-in cash costs were also down to $45/t, from $47/t in Q2.

Also during the quarter, Plant 1G plant was successfully commissioned and was ramping up to its intended capacity. Together with the 1B and 1D plants, the processing capacity at the mine is now in excess of 27Mtpa.

 

Contacts:

African Minerals Limited

+44 20 3435 7600

Matthew Hird / Francis O'Neill

Tavistock Communications

+44 20 7920 3150

 Jos Simson / Nuala Gallagher / Mike Bartlett

Jefferies

44 20 7029 8000

Nick Adams / Alex Collins

 

About African Minerals

African Minerals operates the Tonkolili Iron Ore Project (the "Project") in Sierra Leone, with a JORC compliant resource of 12.8Bnt. The Project, which currently has a 60+ year mine-life, is being developed in a number of staged expansions. In 2013, African Minerals completed sales of 12.1Mt to its customers.

Phase II expansion contemplates the production of an expanded tonnage including the establishment of a high grade concentrate product with the project ramping up to 25Mtpa.

The Company has also developed significant port and rail infrastructure to support the operation of the Project, via its subsidiary African Rail and Port Services (SL) Limited ("ARPS"), in which the Government of Sierra Leone ("GoSL") has a 10% free carried interest.

The Project companies are currently owned 75% by AML, and 25% by Shandong Iron and Steel Group ("SISG"), except for ARPS, which is currently owned 75% by AML and 25% by SISG, with the GoSL having the right to a 10% free carried interest from AML.

www.african-minerals.com

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUAAARSOAURAA
Date   Source Headline
21st Aug 20097:00 amRNSLicensing Resolution
19th Aug 20094:06 pmRNSChange of Directors
14th Aug 20097:00 amRNSHalf Yearly Report
12th Aug 20099:27 amRNSHolding(s) in Company
3rd Aug 20099:36 amRNSHolding(s) in Company
23rd Jul 20094:54 pmRNSHolding(s) in Company
22nd Jul 200911:49 amRNSAdditional Listing on Exercise of Share Options
22nd Jul 20097:00 amRNSHolding(s) in Company
17th Jul 20095:09 pmRNSAdmission of Shares to Trading
10th Jul 200912:34 pmRNSResult of AGM
6th Jul 200911:44 amRNSAdditional Listing on Exercise of Share Options
2nd Jul 20097:45 amRNSCash Placing in excess of US$100 million
1st Jul 20094:40 pmRNSSecond Price Monitoring Extn
1st Jul 20094:35 pmRNSPrice Monitoring Extension
24th Jun 20093:46 pmRNSAdditional Listing
16th Jun 20092:56 pmRNSAdditional Listing
15th Jun 200912:05 pmRNS2008 Annual Report & Accounts & AGM Notice Posted
2nd Jun 200911:05 amRNSNotification of major interests in shares
27th May 200910:19 amRNSHolding(s) in Company
26th May 20097:00 amRNS2008 Audited Results
19th May 20097:00 amRNSTonkolili Update
12th May 20094:40 pmRNSSecond Price Monitoring Extn
12th May 20094:35 pmRNSPrice Monitoring Extension
11th May 20094:04 pmRNSHolding(s) in Company
5th May 20094:43 pmRNSChange of Registered Office
16th Apr 20094:40 pmRNSSecond Price Monitoring Extn
16th Apr 20094:35 pmRNSPrice Monitoring Extension
16th Apr 200911:15 amRNSMarampa Test Results
2nd Mar 20094:40 pmRNSSecond Price Monitoring Extn
2nd Mar 20094:35 pmRNSPrice Monitoring Extension
27th Feb 20094:40 pmRNSSecond Price Monitoring Extn
27th Feb 20094:35 pmRNSPrice Monitoring Extension
20th Feb 20097:00 amRNSDirectors Share Options
4th Feb 20097:00 amRNSChange of Directors
2nd Feb 20097:00 amRNSTonkolili Resource Update
22nd Jan 20097:00 amRNSInvestment in Marampa
16th Dec 20087:00 amRNSAppointment of CEO
15th Dec 20084:41 pmRNSSecond Price Monitoring Extn
15th Dec 20084:36 pmRNSPrice Monitoring Extension
11th Dec 20084:40 pmRNSSecond Price Monitoring Extn
11th Dec 20084:35 pmRNSPrice Monitoring Extension
9th Dec 20087:00 amRNSMineral rights update
8th Dec 20082:18 pmRNSStatement re: Strategic Option Agreement
4th Dec 20084:40 pmRNSSecond Price Monitoring Extn
4th Dec 20084:35 pmRNSPrice Monitoring Extension
3rd Dec 20084:40 pmRNSSecond Price Monitoring Extn
3rd Dec 20084:35 pmRNSPrice Monitoring Extension
3rd Dec 200811:49 amRNSLondon Mining Announcement
25th Nov 20084:44 pmRNSSecond Price Monitoring Extn
25th Nov 20084:39 pmRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.