Talon Resources Targets Ontario Gold Growth After AIM Move and Eagle Lake Acquisition, CEO Says. Watch here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAMI.L Regulatory News (AMI)

  • There is currently no data for AMI

Financing and Operations Update

1 Dec 2014 11:16

RNS Number : 4670Y
African Minerals Ltd
01 December 2014
 



1 December 2014

African Minerals Limited

("African Minerals", "AML", or "the Company")

Financing and Operations Update

African Minerals Limited, the developer, operator and 75% owner of the Tonkolili Iron Ore Project (the "Project") in Sierra Leone, today provides a financing and operations update.

Summary

Operations to be put on care and maintenance until such time as $102m restricted cash is released and/or, AML secures additional short term funding.

Controlled shut down initiated at operations in Sierra Leone due to insufficient working capital, severely impacted by low iron ore prices, which has prevented implementation of cost reduction strategies.

The Company's ordinary shares will remain suspended while there remains a fundamental uncertainty in the financial position of the Company.

Q3 export sales of 4.4Mt (Q2 2014: 4.3Mt); average direct cash costs of $36/t (Q2 2014: $38/t) and all-in cash costs of $45/t (Q2 2014: $47/t).

Further to the announcement on 20 November 2014, the Company announces that the $102m of restricted cash has yet to be released due to continued disagreements between AML and Shandong Iron and Steel Group ("SISG"). AML continues to use its best efforts to obtain SISG's authorisation to release these funds, however there remains no certainty of this, or of its timing.

As previously announced AML commenced a process to sell down a partial interest in its stake in the Tonkolili mine. AML is talking to several groups who have expressed strong interest, and discussions are being progressed as quickly as possible, though there is no certainty a transaction will be forthcoming.

In the absence of sufficient working capital AML has commenced a temporary controlled shut down of its operations in Sierra Leone. Without a significant injection of working capital, AML is unable to initiate the cost reduction strategies which would return the operations to cash flow positive status even at recent low iron ore prices.

The receipt of funds from shipments in recent weeks, including from SISG, provides the operating companies with sufficient funds to meet critical payments necessary to maintain the security, safety, and, to the extent necessary, evacuation of staff and contractors in Sierra Leone, and to maintain salary payments in the short term. This plan allows for the continued safeguarding of the Company's assets and will allow for a rapid ramp up and resumption of operations when a financial solution is achieved.

With all available funds being used for the security and safety of personnel and assets during this temporary shutdown, the Company's subsidiaries have not been able to make in full the repayment under the PXF Facility due at the end of November. The Company is in discussions with its Lenders about this and future obligations under the PXF Facility, however these discussions are only likely to progress successfully once AML and SISG as shareholders of the Project have agreed a financial solution.

Alan Watling, Chief Executive Officer of African Minerals, said:

"Initiating a temporary shutdown of operations towards care and maintenance in Sierra Leone, while extremely regrettable, is a necessity given the Company's financial status and uncertainty over the timing of the release of the restricted funds. While the operating performance of the Project has been impressive during 2014, with Q3 exports of 4.4Mt at an average direct cash cost of $36/t, in spite of the wet season, the fall in iron ore prices and the operational challenges caused by the Ebola disease outbreak has meant the Project has continued to operate at a loss. While management is convinced Tonkolili remains a world class low operating cost asset, the absence of sufficient working capital has prevented the Company from implementing the cost cutting strategies required to return the Project back to a cash flow positive status even in the current depressed iron ore price environment.

Management is doing everything possible to procure the agreement of a funding solution between AML and SISG. The Company greatly appreciates the support shown by the Government of Sierra Leone, our local suppliers and communities, and all our contractors during what we hope is only a temporary suspension of operations."

Frank Timis, Executive Chairman of African Minerals, said:

"Following my visit to Sierra Leone last week I wish to thank the Government of Sierra Leone and all our local suppliers and communities in which we operate for their continued support and understanding of the situation. We are very grateful that the Government has pledged its assistance to help secure the safety and security of our people and assets in these difficult times. We have allocated all available funds to these critical activities and to keeping the operating assets in a condition that operations can be quickly restarted, which is of fundamental interest to all stakeholders. As part of this, local staff will continue to be employed on normal wages and will be allocated to care and maintenance activities."

Q3 Production and Exports Summary

Despite Q3 being the traditional heaviest part of the wet season, the Company's wet season strategies performed well. 5.2Mt of DSO was mined, along with 1.0Mt of other material, principally saprolitic hematite in readiness for Phase 2 expansion. 4.9Mt of this material was treated to produce 3.3Mt of product - 1.7Mt of lump, 1.3Mt of fines and 0.3Mt of A32, a notable decrease in A32 tonnes from the previous quarter which saw 0.9Mt of A32 being produced.

Total tonnage exported in Q3 was 4.4Mt, a 3% increase from the previous quarter. Dry tonnes shipped were 3.9Mt of DSO.

In Q3, 32% of production tonnage was delivered into the 6.5Mt SISG Discounted Offtake Agreement ("DOTA"), while a further 16% was SISG Equity ore.

Average direct cash costs in Q3 were $36/t, a reduction from $38/t in Q2. All-in cash costs were also down to $45/t, from $47/t in Q2.

Also during the quarter, Plant 1G plant was successfully commissioned and was ramping up to its intended capacity. Together with the 1B and 1D plants, the processing capacity at the mine is now in excess of 27Mtpa.

 

Contacts:

African Minerals Limited

+44 20 3435 7600

Matthew Hird / Francis O'Neill

Tavistock Communications

+44 20 7920 3150

 Jos Simson / Nuala Gallagher / Mike Bartlett

Jefferies

44 20 7029 8000

Nick Adams / Alex Collins

 

About African Minerals

African Minerals operates the Tonkolili Iron Ore Project (the "Project") in Sierra Leone, with a JORC compliant resource of 12.8Bnt. The Project, which currently has a 60+ year mine-life, is being developed in a number of staged expansions. In 2013, African Minerals completed sales of 12.1Mt to its customers.

Phase II expansion contemplates the production of an expanded tonnage including the establishment of a high grade concentrate product with the project ramping up to 25Mtpa.

The Company has also developed significant port and rail infrastructure to support the operation of the Project, via its subsidiary African Rail and Port Services (SL) Limited ("ARPS"), in which the Government of Sierra Leone ("GoSL") has a 10% free carried interest.

The Project companies are currently owned 75% by AML, and 25% by Shandong Iron and Steel Group ("SISG"), except for ARPS, which is currently owned 75% by AML and 25% by SISG, with the GoSL having the right to a 10% free carried interest from AML.

www.african-minerals.com

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUAAARSOAURAA
Date   Source Headline
16th Dec 201310:15 amRNSAdditional Listing on Exercise of Share Options
5th Nov 20137:00 amRNSQ3 2013 Production Report
26th Sep 20134:17 pmRNSRESOLUTIONS PASSED AT 2013 AGM
26th Sep 20137:00 amRNSProposed Strategic Investment
11th Sep 20137:00 amRNSrelated party transactions with Shandong
11th Sep 20137:00 amRNSInterim Results 2013
14th Aug 20137:00 amRNSDirectorate Change CEO
14th Aug 20137:00 amRNSDirectorate Change CFO
29th Jul 20137:00 amRNSQ2 2013 Production Report
22nd Jul 20134:33 pmRNSAdditional Listing on Exercise of Share Options
22nd Jul 20137:00 amRNSAppointment of Vice Chairman
28th Jun 20137:00 amRNSPosting of Annual Report and Accounts
26th Jun 201310:01 amRNSDirector/PDMR Shareholding
18th Jun 20137:00 amRNSAchievement of 20Mtpa export rate
22nd May 20138:58 amRNSHolding(s) in Company
14th May 201312:20 pmRNSHolding(s) in Company
14th May 201312:19 pmRNSHolding(s) in Company
14th May 201312:18 pmRNSHolding(s) in Company
19th Apr 20131:48 pmRNSAdditional Listing on Exercise of Share Options
18th Apr 201311:57 amRNSHolding(s) in Company
10th Apr 20137:00 amRNSFull Year Results
4th Mar 20137:00 amRNSAdditional Listing on Exercise of Share Options
5th Feb 20137:00 amRNSConfirmation of new financing arrangements
4th Feb 20137:00 amRNSChange of Nominated Adviser and Broker
14th Jan 20137:00 amRNSAppointment of Chief Operating Officer
4th Jan 20133:08 pmRNSDirector Share Dealing
27th Dec 20125:12 pmRNSDirector share dealing
18th Dec 20129:05 amRNSRaising of Limit of Ownership by CRM
18th Dec 20129:02 amRNSExpansion Update
17th Dec 20124:20 pmRNSOperational and Funding Update
13th Dec 20127:00 amRNSHolding(s) in Company
4th Dec 20127:00 amRNSHolding(s) in Company
23rd Nov 201212:00 pmRNSEstablishment of Finance Credit Facility
21st Nov 20125:44 pmRNSOperational and Financing Update Conference Call
21st Nov 201212:26 pmRNSOperational and Financing Update
1st Nov 20124:45 pmRNSRelated Party Transactions
11th Sep 20127:00 amRNSInterim Results
3rd Sep 20127:00 amRNSAppointment of Senior Personnel
24th Aug 20127:00 amRNSProject Update
2nd Aug 20123:34 pmRNSResult of AGM
17th Jul 20123:16 pmRNSAdditional Listing on Exercise of Share Options
13th Jul 20124:46 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
6th Jul 20125:44 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
6th Jul 201212:04 pmRNSGrant of Share Options
5th Jul 20124:45 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
4th Jul 20127:00 amRNSChange of directors
4th Jul 20127:00 amRNSAppointment of Chief Executive Officer
28th Jun 20124:16 pmRNS2011 Annual Report & Accounts and Notice of AGM
1st Jun 20126:36 pmRNSDirector/PDMR Shareholding
16th May 20125:33 pmRNSDirector share dealing

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.