RE: Wall Street Article13 Jan 2022 12:38
James, so far, the offsites work (i.e. the pipeline to TGT and NGG) appears to have been completed and is being pressure tested (today’s tweet).
The onsite work, the gas plant, is progressing extremely slow atm. We still have three civil works contracts to award (including concrete pour (foundations) and pipeline structural supports. Tank bundling I assume it will be completed after the tanks are installed. Equipment to deliver, install, precommission, commission and test. It takes time to do all this and now I am beginning to worry that we may not even flow gas in March.
Why isn’t site activity ramped up? I’d Angus waiting for the permits approval? Need more money?
Angus really needs to issue that schedule asap as in yesterday.
The market needs to see transparency and something other than slippages done. I am not happy with the fact that the latest delivery schedule has already slipped.