RE: Civil works15 Feb 2022 13:03
James, it is shameful indeed, there really is no excuse for not having a firm 1st gas date at this stage, but here we re trying to make sense of it.
The only delivery issues with equipment listed are the 3 packages (dehydration, J-T, and Condensate stabilisation) which are shown as circa 70% complete. Looks like the confirmed order for these did not get to them on time - fancy that!
In any case though, these Vendors are not restricted by Council working hours and they can work overtime, including shifts - down to Angus to incentivise them.
Another package that concerns me and not talked much about is the Control & Safety system(s). I hope they have gone to a reputable Vendor.
Howey, I don’t see how Angus is going to answer the question on PP & EA approvals in any positive manner. I asked this question and was posted up on IQs twice since last October, yet here we are.
These approvals are not in Angus hands but Angus should be in constant contact with these authorities and chasing them up.