Justin has kindly very quickly replied with this:
“Plug had been working with Carlton Power for quite some time across the three projects, and once an OEM is selected, it can be difficult, although not impossible, to displace. However, we should not lose sight of the fact that ITM has already announced several UK HAR-related selections or contracts. For example:
1) 17 June: Selected for two UK projects, utilising POSEIDON (as POSEIDON is a 20 MW solution, then this equates to at minimum of 40 MW)
2) 23 June: Announced a FEED for the Uniper 120 MW project within HAR2
3) 13 August: Contract announced with Morgen for 20 MW project within HAR1 (the RNS stated that this is related to the announcement on 17 June)
4) 6 October: FEED contract for multiple NEPTUNE V units for a project within HAR 2
So, in total so far, a minimum of 170 MW of UK HAR projects and bear in mind that the majority of HAR 1 & HAR 2 projects have not announced the chosen OEM.”