Fully funded Work Programme18 Apr 2019 10:32
I’d expect first reporting on this next week. Looks very cheap given the targeted 50% production growth, low risk Workovers/appraisals and regular news flow expectations.
Summary Work Programme
2019
· From now through mid-year an aggregate of at least 10 workovers in Puesto Flores (oil), Estancia Vieja (oil/gas), Puesto Prado (oil) and Las Bases (gas) will be carried out. The rig is currently being mobilised to the first well location
· By end of May, the renovation and commissioning of the oil treatment plant in Puesto Prado. The commencement of deliveries of oil from the field direct to local refineries will give enhanced margins (current production 150 bopd from this area)
· From end of May through to November the first phase repair, upgrading and commissioning of the multi-million dollar value gas plant in Las Bases in order for it to have the capacity to handle initially up to 250,000 m3 of gas of President's own gas per day by end of October. The pipeline is already transporting approximately 20,000 m3 per day of third party gas for which a tariff is payable to President
· In any event by mid-year gas flow will commence to the market from the Las Bases and Estancia Vieja fields through temporary facilities
· From July through end of the year a target of seven new production/appraisal wells
· By end September, the erection and completion of 14 km of new overhead electric lines between Estancia Vieja and Puesto Flores fields and the commissioning of an electricity generation plant to power the latter field from the former's gas and to sell surplus electricity generated to the grid
· By end October, the commencement of increased volumes of gas flowing through the building, completion and commissioning of a brand new 16 km section of 4" steel pipeline to be laid between Puesto Prado and Las Bases replacing the limited capacity 3" flexible pipeline between those points
· The commencement of a further workover programme from October, details to be advised once the results of the present campaign are reviewed
· The continuation of infrastructure works throughout the year