RE: Valuation12 Mar 2021 11:25
I think the timeline could be better than your highlight - see an extract from Reposol's Environmental Impact Statement (page 7)
https://www.repsolsinopecuk.com/files/Tain-ES.pdf
"The drilling of the Tain development wells is expected to commence in Q1 2022, with each well estimated to take up to 100 days including mobilisation and demobilisation. The installation of the subsea infrastructure, including pipeline, umbilical, manifold, subsea isolation valve (SSIV), production and umbilical riser replacement, etc. is targeted to take place from June to July 2022. The necessary modifications to the Bleo Holm topsides are targeted to be executed from June to December 2021. First oil from the Tain field development is targeted for August 2022. "