Divorced I think, but who knows if that means they are separated. It was a while ago, but surprisingly we actually got an RNS about that one because she got half his shares. Which were no longer subject to further announcements about dumping them.
EMH submitted a project timeline to the JTF showing a DFS timeline of H1 2025 and a project commissioning timeline of 2030.
All the while not submitting an RNS to its shareholders (and potential shareholders) who have been left in the dark about the current 7 month delay on the DFS that was originally stated to be 8 months in duration.
But hey friends and enemies alike, how about we focus on what really matters. EMH have slipped a note under the radar this week adding another year onto the DFS timeline. Do you think it's a good time to buy? I was wondering about it last week, but after that news, I think I'll hold fire. Less risk buying Bitcoin right now
And Greenmachine, If you'd listened to my posts late Q4 then you wouldn't be losing money. How the F am I to blame if I explain to people the timelines are false and they decide to bash my comments instead of paying heed to them.
You're just expressing your own stupidity if you think that way.
If Espen hadn't filtered my posts he wouldn't be making such ill informed remarks either. Pot, Kettle, Black.
It's hardly an echo chamber of doom and gloom if this doom and gloom is about a recent JTF document that brings new light to the projects timeline. I timeline that is even worse than the one we were already given/notgiven
Share price down another 7% in Oz today. Continuing the downward trend of the last 2 years based on EMH never releasing news of the DFS, and on the second hand news that there's gonna be another year added to its delay.
Then also the second hand news that if a mine is developed, it won't be commissioned until 2030. That's 6 years away. In 2019 we were told 2025 which is also 6 years. Does this mean EMH is no further down the road than it was in 2019? If so, how will anyone know if in 2029 the commissioning date won't be 2035?
The only news EMH can release 7 months into 2024 is a rejection of the local community to build a processing plant and a tweet saying how confident one of their board members are in the project because of his tiny regular share purchase.
There's so much BS from the management here it's becoming entertaining.
Early May the CEO held an interview after a delay of 6 months on the DFS telling the world the DFS update will be in a few weeks, and the delay isn't a big deal because the DFS was complete apart from changes needed for the processing plant. 2 months later we find out through a third party that the delay is going to be 2 times longer than the original DFS timeline. Even when most of it was supposedly complete.
A fictional author couldn't even make this up.
I'd really love to understand how he can believe tripling the DFS timeline to shorten the permitting process is going to work out.
All of your statements are wrong Leon but it doesn't change the fact EMH just announced to the JTF that the DFS that we were initially told would take 8 months and arrive early Q4 2023 will not be here before H1 2025 a whole year and a half late.
They've also said commissioning won't take place until 2030. Given the track record of this company it will probably be some years after 2030 if EMH still exist.