RE: Confidence building presentation17 Jul 2024 09:08
Final point to note - 2 years from today's interview given as timeline to secure environmental permit. Might be SC buying time/managing expectations, but we're a long way off construction (and even further off production). We essentially have $100m to get to that stage, with which we'll produce a FS and make a decision to go mining. At that point, we'll have access to the remaining $650m and will have to start thinking about raising the remaining $1bn - via debt, offtakes and at some point down the line equity.