RE: Web site19 Jul 2024 12:00
Bobbill, in order to start to filling capacity at Sable, they need the modular concentrators to be in place and we don’t know when that is likely to happen, I doubt it will be before the end of this year.
If you look at the diagram on the website, it shows Munkoyo producing 2,000 tonnes of copper annually, based on 20,000 tonnes / month processing module upgrading material from 1.5% to 5%. At the moment they are sending material to Sable (targeting 25,000 tonnes / month) without upgrading it. If you assume 3% average grade (they quote 3-4% in the RNS), that would be potentially 1,500 tonnes of copper annually. Project G is similar although targeting 20,000 tonnes / month of feed to Sable, which would be potentially 1,200 tonnes of copper annually. So a combined total of 2,700 tonnes of copper (potentially) annually. The game changer would be when that material gets upgraded first before going to Sable.