RE: Platinum hits all time highs in Rands20 Apr 2023 10:43
We already know they wont be at full capacity at Roan this quarter. I posted about that the other day:
“ I suspect many shareholders are as confused as I was over the expected timeline for Roan, so I have gone through the RNS and the presentations to try and get a clearer picture. This is what I got:
From the RNS:
“The final phase of the Roan project ramp-up is scheduled for early April 2023 to complete the commercialisation of the Southern Copper Refining project expected during May 2023. Upon reaching commercial production, the Roan copper concentrator is expected to contribute 550 tonnes of copper per month to the production of Sable Refinery with a further 130 tonnes per month of copper from third party supplies.”
Commercialisation is when the budgeted throughput of copper (550 Tonnes / month) is reached. This isn’t the same as reaching name-plate capacity.
From the presentation:
Roan expected to reach 800+ Tonnes / month capacity “post the current period”
“We have a conservative number on Roan’s production profile to allow for some downtime during the upgrade.”
Upgrade of front end expected to be done within an 8 week period once it commences.
So what we might expect to hear next, during May, is that we have reached commercialisation. Because of the upgrade to the front end (an 8 week period approximately) there will be some reduction in capacity. I guess that’s why they are not expecting to reach full capacity during the current period. Leon said that there is some downtime already built in to the numbers.”