ANOH on track for Q428 Jul 2023 07:19
"Regarding the Spur Line project, all line pipes required for all 23.3km spur line sections are now in country and have been delivered to the project site. The first phase of the spur line (5.5km length) has been completed, with another 4.5km currently in progress. Our government partner has confirmed the revised completion date of Q3 2023."
"In terms of upstream development, the drilling of the third well has been completed, and work on the fourth well is ongoing, with expected completion before the end of Q3 2023. Additionally, work on surface facilities required to deliver wet gas to the AGPC plant is in progress and expected to be completed by the upstream unit operator, SPDC, in Q4 2023."
This is our next dependable share price catalyst - great to hear still on track for Q4