Akatara project21 Aug 2024 20:43
get rid of pop up - choose amdal tab and then see jadestone file below..translate page
https://amdalne****nlhk.go.id/#/
development activities of akatara oil and gas field, lemang block, west tanjung jabung regency, jambi province by jadestone energy (lemang) pte.ltd.
current activities:
procurement of land of approximately 64.86 ha for all production and supporting facilities in the akatara field;
-change in the operating model from oil and gas production to gas production with lpg and condensate as by-products in the form of:
*operation of a gas processing facility (gas processing facility, gpf) with a capacity of 25 mmscfd;
*operation of a liquid petroleum gas processing facility (lpg plant) with a capacity of 3 mmscfd; and
*operation of a condensate processing facility (condensate plant) with a capacity of 1,200 bbls;
*operation of 29 wells including 24 development wells, 2 injection wells, and 3 workover wells, with details: pad a 2 workover wells and 2 development wells; pad b one (1) well
*use of water based mud (wbm) and synthetic based mud (sbm) drilling mud;
-operation of roads and bridges from the well pad to the gas processing facility (gpf) or from one well pad to another and continuing to the gpf with a total road length of approximately 16 km and a right of way (row) width of 21 m;
-installation and operation of pipes with details:
*flowline pipes with a diameter of 4 inches - 12 inches at the well pad location to the production facility (pf)/gas production facility (gpf) including pad a-pf/gpf, pad b pf/gpf, pad d- pf/gpf, pad ca pf/gpf, pad da- pf/gpf, pad ed a- pf/gpf, pad fda- pf/gpf and pad gda-pf/gpf
*testing pipe with a diameter of 4 inches
*produced water distribution pipe with a diameter of 4 inches - 8 inches from gpf to injection wells. the maximum produced water that is distributed is approximately 450 bwpd; and
*distribution pipe (sales/export pipe) with a diameter of 8 inches along approximately 17 km from gpf to the transportasi gas indonesia (tgi) tie-in point pipe;
*operation of condensate production that is trucked to pertamina's tempino main gathering station in muaro jambi regency and/or taken directly by buyers at the gas processing facility (gpf);
*repair and maintenance of the main access road along approximately 5 kilometers from gpf to the public road; and
*maintenance/care of main and supporting facilities including replacement of pipes on the existing row in emergency conditions
planned activities:
additional land acquisition of 29.3 ha (production facilities: 5.5 ha, alternative road 2.6 ha, well pad exploration well & access road 21.2 ha)
additional production capacity: gas 8.5 mmscfd, lpg 64.6 t/day and condensate 21.8 bcpd