RE: Looking forward29 Apr 2024 08:42
On akatara...
Currently, the Group is focused on testing all equipment, testing, cleaning and reinstatement of interconnecting pipe, electrical and instrument testing at both the gas plant and metering station, and the hydrotesting of the gas pipeline. Overall progress of the project had reached 95.72% completion at the end of March 2024. Pre-commissioning and commissioning activities commenced in November 2023 and continued into early Q1 2024 for utility systems, with further progression towards commissioning for the process system. Commercial production remains on track to start in Q2 2024.