The latest Investing Matters Podcast episode featuring Jeremy Skillington, CEO of Poolbeg Pharma has just been released. Listen here.
Https://www.betting.net/reviews/watch-and-wager/
It’s worth noting that Watch and Wager are registered with a wide range of overseeing agencies. The list spans to Rosecroft Raceway, the Thoroughbred Owners of California, the Maryland Racing Commission, the Colorado Department of Revenue, Monarch Content Management as well as boasting an operators license that was issued by the California Horse Racing Board – these licenses are up there with some of the best online gambling sites and are trustworthy and authentic through and through.
Akatara
Overall progress of the project had reached 95.72% completion at the end of March 2024. Pre-commissioning and commissioning activities commenced in November 2023 and continued into early Q1 2024 for utility systems, with further progression towards commissioning for the process system. Commercial production remains on track to start in Q2 2024.
Nice to hear on the presentation that there are demands from others on akatara gas - PB indicated that they already have capacity to offer gas to a second contractor at 20% premium and there are demands for more- they are potentially going to be looking at upgrades in the future to meet demands.
At least we get an update on montara...
The Prohibition Notice that was issued in June 2022 is expected to remain open until each tank within the FPSO that can contain oil has been inspected and a technical file note demonstrating its fitness for service has been issued to NOPSEMA. Jadestone is currently methodically executing a tank restoration program, which resulted in 6 centre, 5 centre, 5 port, 5 starboard and both slops tanks being removed from the Prohibition Notice during 2023. Work is ongoing on the remaining tanks and once all are completed, the Prohibition Notice is expected to be fully lifted. Jadestone continues to engage closely and transparently with the regulator about the progress of the inspection work. The NOPSEMA Level 4 investigation into the 2C loss of containment is ongoing.
On akatara...
Currently, the Group is focused on testing all equipment, testing, cleaning and reinstatement of interconnecting pipe, electrical and instrument testing at both the gas plant and metering station, and the hydrotesting of the gas pipeline. Overall progress of the project had reached 95.72% completion at the end of March 2024. Pre-commissioning and commissioning activities commenced in November 2023 and continued into early Q1 2024 for utility systems, with further progression towards commissioning for the process system. Commercial production remains on track to start in Q2 2024.
Akatara...
During testing, one well achieved a maximum flow rate of approximately 9 million cubic feet per day (mmcf/d), with data from the well test supporting the current Akatara 2P reserves estimate. The well is designated to supply pre-commissioning and commissioning gas for the AGPF, while the second well is intended for use as an injector/disposal well.
A campaign with a 550 HP rig to work-over the planned five wells commenced in Q1 2024. Currently, four out of five well workovers have been completed and tested at an aggregate stabilised rate of c.30 mmcf/d, ready to deliver the gas production required to fulfil the daily contract quantity under the gas sales agreement.
Published a week ago re akatara...
htTps://www.linkedin.com/posts/exakta-ip_lemang-akatara-localenvironment-activity-7186327407023296512-u5UA
For this ambitious project, Exakta was appointed to supply its API 674 #PositiveDisplacement reciprocating pumps for transferring #Water to the injection well. #Robust by nature, our 3C Triplex Series can withstand tropical climates marked by equatorial rainfall and violent storms, while proper mass balancing ensures quiet and #VibrationFree operation.
From the accounts...
On 9 April 2024, the Group announced the closing of a new €25.0 million facility with Kommunalkredit Austria AG (Kommunalkredit), which was used to repay the outstanding balance on the RBL facility
This should generate 47gwh of power when up and running...
Bletchingley
The Bletchingley gas to wire project now has full planning consent, environmental permits and a secured grid connection. Further work by the Distribution Network Operator is underway to optimise the grid connection routing. Subject to this being finalised, expected imminently, the project is now "shovel ready".
The development of the Stoke-on-Trent project has taken longer than anticipated..
This due diligence was conducted during the year and the technical and commercial aspects of the geothermal heat provision within the project were signed off by the consultant towards the end of Q3 2023. Subsequent to the year end, SSE, as lead applicant have submitted a project change request to the GHNF which seeks to amend both the capital grant as well as the timetable within which that grant will be spent. A decision is expected in the second quarter of 2024.
Tax losses
The Group has gross total tax losses and similar attributes carried forward of £362.1 million (2022: £355.3 million). Deferred tax assets have been recognised in respect of tax losses and other temporary differences where the Directors believe it is probable that these assets will be recovered based on a five-year profit forecast or to the extent that there is offsetting deferred tax liabilities. Such recognised tax losses include £109.5 million (2022: £123.2 million) of ringfence corporation tax losses which will be recovered at 30% of future taxable profits, £92.6 million (2022: £119.8 million) of supplementary charge tax losses which will be recovered at 10% of future taxable profits and £4.3 million (2022: £1.9 million) of losses arising under the EPL regime which will be recovered at 35% of future taxable profits.
HTtps://youtube.com/shorts/0CZUuQli6LE?feature=shared
Dated 18th april 2024 short clip at akatara, not sure when it was filmed though
Canaccord Genuity Group reaffirmed their buy rating on shares of Star Energy Group (LON:STAR – Free Report) in a report released on Tuesday, MarketBeat reports. Canaccord Genuity Group currently has a GBX 55 ($0.70) price objective on the stock.
https://www.defenseworld.net/2024/04/10/star-energy-group-lonstar-receives-buy-rating-from-canaccord-genuity-group.html