I can't see any way that those 'targets' can be achieved.
As BG points out, the full 3D seismic data is not available until mid-year (and we don't know whether that includes the interpretation of the data). Until they have that, they don't know the new pad location (assuming it is needed) and until they know the pad location, they won't know where to lay the pipeline.
And as drogereky points out, there are many other items to be sorted.
So no! No chance.