Rig due to mobilise17 May 2023 15:11
A bit of a slip this week, but at least there is promise for greater things. The rig is already secured and .
"The rig is expected to mobilise in early-June 2023 targeting a mid-June spud. Drilling operations are expected to take 25 days to reach the prognosed TD drilling depth of 2255m (1709m True Vertical Depth), with an additional 12 days scheduled for testing. The drilling pad has been prepared and the 20" conductor pipe has been set at 85 metres"
"It is anticipated that once completed, the SCHB-2 well will be tied-in to existing production facilities at the Schwarzbach site which will take approximately 12 days to complete."