RE: New interview out29 Aug 2024 15:48
One of my main takeaways from the interview concerned securing the drilling permit for Hussar. The schedule, included as part of the recent presentation, shows the drilling permit being secured by the end of this month. Given the scope of work required to achieve it, I was concerned about the proposed completion date. However, TH said during the interview that in order to lodge the application for the drilling permit, they required funding to be in place, which they now have. He then went on to say "... every part of the paperwork, the applications, all of that was already done; it just required the money and then of course it required the engagement of Aztech Well Construction to manage the whole process for us."
Although I have concerns about the possibility of securing the permit by the end of this month, it seem highly probable that the work already undertaken means the drilling permit will be in place to allow drilling to commence in December.