RE: Q125 Apr 2022 08:56
It's worth emphasising that the low Q1 production was already factored in to the guidance for 2022 which was announced on 31 January:
FY2022 Guidance:
· FY2022 production guidance of 87,000 - 97,000 oz of gold, with an AISC of US$1,300 - 1,450 per oz of gold
o Q1 2022 is forecast to be a lower production quarter versus the remaining quarters of 2022, with a ramp up from Q2 2022 expected, driven primarily by an additional five excavators becoming increasingly operational during Q1
o Further operational improvement measures at Yanfolila have been undertaken to ensure 2022 guidance forecasts are met, as detailed below