Project G28 May 2025 10:54
I have a concern with communications on Project G. Previous RNS stated copper concentrate being produced in October 2024! Todays note says drilling to start in June 2025 but apparently it was underway in October 2024 as well. Is there any production at G or not? Something does not add up and needs clarification from the company!
7th October 2024
Project G targeted to commence operations and delivery of pre-concentrated run-of-mine (ROM) to the Sable Refinery (Sable) by December 2024
Under the Agreement, Jubilee is appointed manager and operator of the open-pit operations with immediate effect
Project G will ramp up over a 6-month period to reach 3,000 tonnes per month of pre-concentrate material through a Jubilee on-site module, and delivery of an additional 350 copper units per month (4,200 per annum) to Sable for further refining.
Resource drilling program currently underway, targeting a potential increase of production to 20-25ktpm ROM ore.
13th January 2025
Following the completion of Jubilee's due diligence on Project G during August 2024, the Company acquired a majority interest in Project G.
The project aims to expand existing operations to achieve an initial mining rate of 10ktpm by February 2025. Project G includes an on-site facility designed to pre-concentrate mined ROM material, with an immediate capacity to produce 3kt Cu Conc per month, containing 10% to 15% copper. Lower-grade copper will be stockpiled for future on-site processing. First copper concentrate was produced at Project G during October 2024.
28th May 2025
Project G is scheduled to commence drilling of the resource during June 2025. The Company aims to follow a similar implementation strategy to Munkoyo, with a portion of the mined reef being upgraded on site using physical separation techniques, while the remainder of ore is processed further using chemical extraction techniques.
The Project G mining operations are adjacent to an existing mining operation, as well as a new developing mine, which offers the potential to collaborate on the implementation of a central processing unit. The area has already established infrastructure such as power and roads allowing for a faster implementation process.
The final targeted scale of the mining project and potentially shared processing facility will be finalised on the back of a completed drilling program and current negotiations to collaborate on the processing facility.