Second quarter production was negatively impacted by labour issues related to the illegal underground sit-in followed by an unprotected strike at CRM operations in early May. The labour issues were resolved with the signing of a two-year wage agreement with NUM (National Union of Mineworkers) and agreement on other disputed matters. With the suspension of 155 production workers, resources have been consolidated into the Zandfontein operations and the services of JIC Mining have been engaged on a fixed-term contract to restore full production at the Maroelabult section during the third quarter.
Concentrator recovery was also negatively affected by the labour disruption.
As reported on April 15, 2011, cement grout support packs are now being introduced into underground working panels thereby further enhancing ground support standards.
Based on the actual production results for the first half of 2011, the operating history of CRM and the budgeted plan for the remainder of 2011, the Company anticipates PGM production for the full year to be approximately 105,000 ounces.
Crocette is progressing well and on-reef development has commenced.
Work at the 90,000 tonne-per-month Mareesburg open-pit/concentrator project on the Eastern Limb continues. Fluor, an international engineering and construction company, was awarded the project management and construction management contract and K'Enyuka, a respected engineering company based in Johannesburg, was awarded the contract for the detailed design for the concentrator and support facilities. Site capture and planning have been ongoing and earthworks will commence on site in July 2011. Production startup is scheduled for late 2012.
The qualified person having reviewed the operating results presented in this press release is Mr. Brian Montpellier, P.Eng.
Eastplats will release its full second quarter results on Monday, August 15, 2011.