Timescales31 Aug 2018 19:26
We have 91 days left of the drilling season (End of Nov).
Sinopec Rig
- SL 17 days left
- Mobilise to WH (300km) - 1 week max (based on timescales to move 1100km for SL)
- Rigged up - 2 weeks max (based on timescales to rig-up for SL)
- Spud Wild Horse 25 days (2017 Sinopec quoted 20 days however since appointed of MB decision to drill a little further TD 2000m)
Total number of days 63 days
Total number of float in drilling season 28 days
Petro China Rig
- Site Prep at Gazelle, well site construction and on site water well drilled for operations (2 weeks)
- Mobilise rig from Block XIX to Block XX (Gazelle) 30km (2 days Max).
- Previous DT drills in 2010/2011 took 14-19 days to spud, cement, case, mobilise to the next location and rig up (average of 1800m). Gazelle is 2200m TD therefore I expect this to reach TD in 3 weeks (21 days).
- 4th drill to be confirmed. Presentation (25th June) includes the 4th drill TD of 2000m (average TD in Block XX) therefore I'd expect this to be of similar timescales 3 weeks (21 days).
Total Number of days 58 days
Total Number of float in drilling season = 33 days
Total Number of float Q4 to end of drilling season = 61 days - 42 days drilling = 19 days
In between, parallel activites will take place inc
- Site Prep at Wild Horse (due to commence late August I expect this has already begun should the programme remain).
- Block XX rig contract (spud depends largely on rig availability, I suspect the contract will be signed once given the thumbs up from DQE, I expect this news to be imminent should the programme remain). News on multiple fronts; this could differ in content dependent on SL results. E.g. appraisal well SL-2 if positive.
- Site Prep at 4th drill (TBC). Potentially Heron. To be confirmed soon.
All complete guestimates on my part and all IMO however just wanted to provide some comfort to PIs that there is still time.