Gas sales in 201622 Jun 2021 09:08
The audited financial amounts for the year ended 31 December 2016 (the "current period", "period" or "reporting period") are compared to the audited seven-month period ended 31 May 2015 ("prior period") unless otherwise stated.
Operational Highlights
· 24% increase in gas sales: 3,566mmscf gross gas sold (12 months/2015: 2, 868mmscf)
· 10.23mmscf/d average gas production (12 months/2015: 8.13mmscf/d)
· 15km pipeline laid as part of Bonaberi extension - 50km total network
· Matanda licence 75% interest in 1,235km2 Matanda Block assigned to the Company, adding 2.8tcf net prospective resources in Northern Matanda Field
· Logbaba drilling programme commenced targeting additional gas reserves
This was 5 years ago and still made a loss of $30ml
and still nowhere near enough customers, have things changed?