It does not appear that many, if any, of you have any experience of permitting in Namibia - or anywhere else. That is fair enough. We cannot all be expert in everything.
Having checked with one of the major consultancies, opinion is that the ECC will follow the ML in timely fashion. It is issued by a different Ministry to the ML, namely MEFT. The ML comes first and the ECC second BUT the process for the ECC - the final hurdle commenced back in April with the submission of the SEIA and EMP to the MEFT. Both documents have been approved and we are in the final stages or furlong ( if you follow the horses).
Nothing wrong and nothing to do - except be patient, as ever. All the public meetings and consultations were completed successfully yonks ago😀