The reply in essence would seem to be right. All work is towards the DFS. Part of the work is to satisfy the RECAPE needs as this is an integral part of the process and requirements for the DIA.
RECAPE has not been delayed because of the DFS, but I would venture, is the other way round. It has been the lack of the missing easements that has prevented access to the land for the necessary geotechnical drilling results that then feed into RECAPE so the requirements of the DIA and subsequent EL and then I would suspect the fully loaded DFS. The question is why it has taken so long for the easements to get to the top of the pile. Another one for the Ministry for Chivvying Along.
Getting the easements, doing the work, getting the results, formatting the submission all before Christmas would require a wiggle that Marilyn Monroe would be proud of, but in reality, settling expectations into early next year is reasonable. Even my kids have stopped believing in Santa Claus.