🔥 NTVO RNS: Major Progress at Bonanza:- Todays RNS🔥18 Nov 2025 07:42
1. Surface Trenching & Geological Work — COMPLETED
20 trenches dug every 25m along the Bonanza vein (1.2–1.5m deep).
All trenches logged, photographed, structurally measured.
Systematic channel samples taken every 1m across exposed mineralisation.
Samples sealed on 16 Nov and first batch going to CERTIMIN (Lima) this week.
Why this adds value:
This work defines vein shape, thickness, grade variability and identifies the richest zones (ore shoots). It directly feeds into underground targeting and mine planning.
This is the core data needed before mining restarts.
2. Geological Modelling Underway
Field data is now being digitised.
Longitudinal sections and geological models being built.
This modelling identifies exactly where to mine first underground.
This is the transition point between exploration and production.
3. Underground Shaft Rehabilitation Has Started
Full topographic survey completed.
Engineering design for ladders, ventilation, platforms and water management has begun.
All support materials for phase 1 are already on site.
Why it matters:
They are preparing the mine for safe worker entry — the critical step before extraction restarts.
4. Operations Camp Expansion (20 → 40 Personnel)
Accommodation, water systems, electrics, generator, workshop areas, safety zones all being upgraded.
Starlink satellite system being installed.
This indicates long-term operational commitment — not just a short-term test.
5. Mining Contractors Now Visiting Site
Contractors invited to inspect Bonanza conditions.
They will soon submit formal tenders.
Technical/HSE teams will select a contractor after evaluation.
This is a commercial step directly linked to restarting output.
6. FIVE New High-Potential Ore Shoots Identified
Across the 300-hectare concession, the company has:
Verified multiple veins ("Zona Central" & "Zona Este").
Identified 5 new potential small-scale mining zones.
Historical grades up to 10 g/t confirmed by re-mapping.
This shows Bonanza is not a one-mine story — the concession may support multi-zone production.
What Happens Next (Expectations)
CERTIMIN assay results from trench samples.
Finalisation of geological models.
Further underground rehabilitation and mapping.
Mining contractor selection.
Final operational plan for restarting extraction.
🔥Summary🔥: Full trenching done, samples heading to CERTIMIN, shaft rehab started, contractors on-site, camp upgrade underway, and five new ore shoots found. NTVO is now weeks—not years—from returning to production.
Good luck!!!