RE: Havieron28 Mar 2026 11:13
@TomE
The boxcut improvements started backend of last year. The entrance to the tunnel has been extended outwards with reinforced concrete floors, walls and ceilings. It was about 10 meters beyond the original entrance last time we got information. Adjacent to the entrance a concrete base has been laid for the conveyor belt. There is some work going on in the tunnel itself too. There is a host of contractors on site that have shared videos and photos. Bamps, E1, SureAsBlazes, Dip666, Paddy, Rotherby and a few others LTH’s have seen them. Jetcrete plant is being utilised on site. Speculation is the second conveyor tunnel work may be underway. I’m told that the concrete ceiling will eventually be built all the way to the top of the slope. The work is currently being done only on the night shifts because the temperature (38-45C°) in the day is too hot for curing the concrete correctly.