RE: Do we know24 Jul 2023 08:19
Looks my original guesstimate of stable gas flow rates using the pump, during week commencing 7th August was way too optimistic.
So, let's assume the rig is in place to do the dewaxing by this Wednesday, the 26th. They said the dewaxing will take 5 days, so that takes us to the 31st. Installation begins perhaps on the 2nd August. They previously said installation would take 8 days. Could be a bit less if some electrical work, for example, has been done while the rig was away. So, the pump COULD be running around the 9th. Briana said in her email it was expected to take about 10 days to get the data the DGH wanted. So, my new guesstimate is that we may get the improved flow rates in week starting 21st August. Could be later but hard to see how it could be much earlier.