RE: Dividends18 Nov 2017 08:20
Probably closer to 2020 for production, or early 2020, if not bought out. After bfs and financing this year. H1 2018 is detailed design and engineering, order long lead items, commence access and infrastructure. 18 month for the construction. So will be later in 2019 if perfect and if they get the H1 activities done early in the period.
I think you have the profit figures wrong for years 1/2. 17.5ktpa first two years, 35ktpa years 3/4.