RE: Simple detail required17 Mar 2019 12:11
Hi triggerman,
There's a lot of layman-friendly info on the company website, under presentations, see www.hurricaneenergy.com.
The AM won't itself anchor, it will hook up /latch on to the buoy, which is tethered to the sea-bed. The hookup process is supposed (per Dr T) to take about 6 hours , in favourable conditions. If you've been following the company/thread for any time, you'll be aware that previous efforts to hook up have been frustrated.
The rate of 20,000bopd is a theoretical intended maximum, a practical cap is likely to be 17,000 bopd allowing for downtime...and this will likely only be achieved after several weeks of 'tweaking', in order to provide data for field reservoir analysis (flow-rates, pressure build-up, etc).
The time taken for commissioning aka 'first oil' has been indicated by Dr T as roughly 3 weeks, as we have seen with hookup this estimate is just that, an estimate/educated guess, and shouldn't be considered as more than 'indicative'.
HTH and ATB