RE: Another Tweet and Another Element of the Project Being Progressed19 Nov 2021 19:18
Relax you shorters
ress2003
Price: 0.875
No Opinion
RE: Another Tweet and Another Element of the Project Being ProgressedToday 22:44
Also I wouldn’t be surprised if angs actually go down the route of anaerobic digesters!!, as it’s going to be very simple for them to do that if they got planning and EA approved,, as they would have all the infrastructure in place for the gas, it’s a easy 10k a day for them plus a CHP too, and it’s green energy too
ress2003
Price: 0.875
No Opinion
RE: Another Tweet and Another Element of the Project Being ProgressedToday 22:38
Like I said mid January is when your will know if there in front or behind, depends on contractors and
Suppliers
ress2003
Price: 0.875
No Opinion
RE: Another Tweet and Another Element of the Project Being ProgressedToday 22:37
The side track would be in a different location to where the gas line is, and then added to the main gas line to the Compressor
WG818
Price: 0.875
No Opinion
RE: Another Tweet and Another Element of the Project Being ProgressedToday 22:36
Thanks for the reply. So possible by Xmas then.
It’s going to be interesting watching the Twitter updates!
ress2003
Price: 0.875
No Opinion
RE: Another Tweet and Another Element of the Project Being ProgressedToday 22:35
Sorry I will answer , in my option I can’t see the side track happening till they go gas to grid, as in my opinion they will won’t to prove the concept of what they have first and that it’s all working as it should be without adding a side track into to this, but in all honestly they could to as it won’t effect the gas flow neither, it depends on how confident they are, see gas will flow through none return valves so there won’t be issues with a side track, it’s more about seeing how everything works once flowing,
ress2003
Price: 0.875
No Opinion
RE: Another Tweet and Another Element of the Project Being ProgressedToday 22:30
Hiya,,
Well the pipe work can come in 3mrts lengths and use a thing called sanpress, but most likely normal pipe work, flanges, welds etc, and pressure test,, the foundations don’t take that long it’s just a concrete bed, a bit of strutting etc and rebar, and frames, for the pipe work, nothing major at all, there will be say a few gas monitors analyses, and flow meters, so some minor electrical works, or 4 to 10 signals, or 24 volts maybe 240 volts depends on dpec really, but without reading there functional design specification I don’t know what they have spec, so hard to say, but it’s all relatively the same, but my guess would be about two weeks for concrete and two weeks for pipe work,, then test with nitrogen for pressure testing etc,,it comes down to the grid pressure tho too , and what they can go too, so pipe size for optimum gas flow and CV value too, CH4 tends to be around 95 per cent plus so a little too up and jobs a gooden etc,