SHORTERS REBUTTAL Part 3b23 Nov 2021 21:27
...making it difficult for the company to entice Warrant holders or employees to exercise their rights – thus provide cash to Angus Energy.
Short Seller Observation 11: Angus Energy don’t have the necessary approvals to get to First Gas and never will
Actual Reality Observation 11:
Again the Short Sellers forget to note the existing approvals:
N/158/00804/20, 12th June 2020
Approval for development ancillary to mining operations comprising the installation of processing facilities, including metering refrigeration unit manifold, glycol dehydration unit, acoustically-housed compression and generation equipment, pipework and manifold at the Saltfleetby 'B' site.
Planning Permission, N/180/00971/20 PL/0060/20, 7th August 2020
Planning Permission for Saltfleetby-Theddlethorpe Pipeline Extension. Installation and operation of an underground gas pipeline up to 750 metres in length, connecting the existing Saltfleetby/Theddlethorpe underground gas pipeline to the National Grid National Transmission System, Theddlethorpe via the Uniper gas distribution terminal.
Planning Permission, N/158/1011/21 PL/0073/21, 26th July 2021
Planning Permission for Saltfleetby – Theddlethorpe. For a sidetrack drilling operation from an existing borehole at Saltfleetby B wellsite to enable a lateral borehole to be drilled up to 1500m to the SW at Saltfleetby B Wellsite.
However, there are in train outstanding permissions and I suspect the Short Sellers are betting these don’t come in or get approved as stated in CPR:
“HSE (Surface facilities) HSE (Pipeline repressurisation)
Hazop completed. Awaiting final sign-off of Safety Case (largely agreed) and MAPD.
Expected approval date: early December 2021.
HSE SF7 sidetrack Actions: HSE plan submitted; awaiting independent well engineer certificate; layout drawing; and hazop early November 2021.
Expected approval date: early December 2021.
Environment Agency (to operate process equipment) Environment Agency (Pipeline repressurisation)
Actions: Application submitted February 2021; Noise modelling; Flare gas system details requested.
Expected approval date: December 17th 2021.
National Grid plc Network Entry Agreement and Acceptance
National Grid attend the metering factory acceptance tests, hazop and all relevant inspections.”